Seal BUILDING
Permit Payment Receipt


CITY OF FRISCO
6101 Frisco Square Blvd, TX 75034
Phone: 972.292.5301
APPROVED DATE: 8/25/2021 PERMIT SUB-TYPE: SNEW PERMIT NO: B21-03881
JOB ADDRESS:
6979 ALBANY PARK
FRISCO, TX 75034
DESC:   4321 AC, 5292 SF, 2 STORY
OWNER:
HT STONEBROOK LAND I LP
2200 ROSS AVE STE 4200W
DALLAS TX 75201

CONTRACTOR:
DARLING HOMES OF TEXAS LLC
6735 SALT CEDAR WAY, BLDG 1, STE 200
FRISCO TX 75034
ISSUED DATE:
8/25/2021
APPLIED DATE:
8/18/2021
EXPIRED DATE:
4/22/2023
SITE APN:
ADD221586
STATUS:
COMPLETED
APPLICANT:
Dallas Starts - DH
6735 Salt Cedar Way
Frisco TX 75034
LEGAL DESC:
COUNTY:
ZONING:
VALUATION:
0
FEE SUMMARY
INSPECTION SUMMARY
SLAB RES 12/07/2021 DC2$30.00
SHEATHING RES 01/17/2022 DC2$30.00
2NDS AND FRAMING 03/21/2022 DW2$30.00
2NDS AND FRAMING 03/25/2022 DW2$30.00
2NDS AND FRAMING 03/31/2022 DW2$30.00
FLATWORK RES 08/16/2022 DWF$30.00
FLATWORK RES 08/17/2022 DWF$30.00
PERCENT CREDIT CARD FEE$0.60
PERCENT CREDIT CARD FEE$1.80
PERCENT CREDIT CARD FEE$0.60
PLUMBING ROUGH-IN 03/08/2022 JWI$30.00
PTO AND MECH ROUGH 03/10/2022 JWI$30.00
GAS RELEASE 09/08/2022 MLM$30.00
AUTO PROCESSING FEE$0.00
FENCE FEE$20.00
RESIDENTIAL NEW PERMIT FEE$1,797.60
RESIDENTIAL FEE$158.76
RESIDENTIAL MECHANICAL FEE$159.00
RESIDENTIAL NEW APPLICATION FEE$300.00
RESIDENTIAL PLUMBING FEE$291.00
SEWER IMPACT FEE$2,344.00
THOROUGHFARE IMPACT FEE$119.00
WATER IMPACT FEE$2,151.00
INSULATION RES 04/19/2022 RWT$30.00
PTO AND MECH ROUGH 03/03/2022 SDC$30.00
PLUMB MECH FINAL 10/18/2022 SME2$30.00
PTO AND MECH ROUGH 03/01/2022 SMH$30.00
1 INCH PD METER$450.00
WATER METER DEPOSIT$125.00
Total Fees:$8,338.36
______  METER PAYMENT
______  T-POLE RES
______  SET 1 PD METER
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  SLAB RES
______  SLAB RES
______  SHEATHING RES
______  SHEATHING RES
______  PTO AND MECH ROUGH
______  PTO AND MECH ROUGH
______  PTO AND MECH ROUGH
______  PLUMBING ROUGH-IN
______  PTO AND MECH ROUGH
______  PTO AND MECH ROUGH
______  2NDS AND FRAMING
______  2NDS AND FRAMING
______  2NDS AND FRAMING
______  2NDS AND FRAMING
______  2NDS AND FRAMING
______  2NDS AND FRAMING
______  2NDS AND FRAMING
______  2NDS AND FRAMING
______  INSULATION RES
______  INSULATION RES
______  INSULATION RES
______  DRYWALL RES
______  BRICKWALL TIES RES
______  LATH RES
______  FLATWORK RES
______  FLATWORK RES
______  FLATWORK RES
______  GAS RELEASE
______  ELECT FINAL RES
______  GAS RELEASE
______  GAS RELEASE
______  PLUMB MECH FINAL
______  UTILITIES INSPECTION
______  PLUMB MECH FINAL
______  PLUMB MECH FINAL
______  PLUMB MECH FINAL
______  CO AND BUILD FINAL
Notes: