APPROVED DATE: 11/23/2021 PERMIT SUB-TYPE: MNEW PERMIT NO: B21-03767
JOB ADDRESS:
3101 GAYLORD PKWY
FRISCO, TX 75034
DESC:   363590 SF, HALL PARK - BLOCK D4
OWNER:
HALL 3101 GAYLORD II LLC

DALLAS TX 75201-2723

CONTRACTOR:
ANDRES CONSTRUCTION SERVICES LLC
3710 RAWLINS STREET STE 1510
DALLAS TX 75219
ISSUED DATE:
11/23/2021
APPLIED DATE:
8/12/2021
EXPIRED DATE:
3/10/2025
SITE APN:
ADD73902
STATUS:
ISSUED
APPLICANT:
Julieta Nicolakis
2001 Bryan St
Dallas TX 75081
LEGAL DESC:
COUNTY:
ZONING:
VALUATION:
98230000
FEE SUMMARY
INSPECTION SUMMARY
ELECT FINAL COMM 08/17/2023 DC2$35.00
ELECT FINAL COMM 09/14/2023 DC2$35.00
ELECT FINAL COMM 09/26/2023 DC2$35.00
ELECT FINAL COMM 10/24/2023 DC2$35.00
ELECT FINAL COMM 10/31/2023 DC2$35.00
COMM CO 11/16/2023 DC2$35.00
CREDIT CARD FEE$0.70
PERCENT CREDIT CARD FEE$127.80
PERCENT CREDIT CARD FEE$6.30
PERCENT CREDIT CARD FEE$5.90
PERCENT CREDIT CARD FEE$3.50
PLUMBING ROUGH-IN 01/07/2022 JWE2$35.00
AUTO PROCESSING FEE$6.00
COMMERCIAL FEE$14,573.60
COMMERCIAL BUILDING PERMIT FEE$186,831.84
COMMERCIAL MECHANICAL FEE$18,209.50
COMMERCIAL NEW APPLICATION FEE$300.00
COMMERCIAL PLUMBING FEE$32,753.10
SEWER IMPACT FEE$90,396.00
THOROUGHFARE IMPACT FEE$0.00
WATER IMPACT FEE$101,136.00
DRYWALL COMM 10/17/2022 REED$35.00
INSULATION COMM 03/20/2023 REED$35.00
INSULATION COMM 05/01/2023 REED$35.00
ELECT FINAL COMM 09/20/2023 REED$35.00
ELEVATOR 09/19/2023 RJB$50.00
MECHANICAL ROUGH 10/11/2022 SDC$35.00
PLUMB TOP OUT COMM 11/10/2022 SDC$35.00
PLUMB TOP OUT COMM 11/11/2022 SDC$35.00
PLUMBING ROUGH-IN 11/17/2022 SDC$35.00
MECHANICAL ROUGH 11/28/2022 SDC$35.00
MECHANICAL ROUGH 02/14/2023 SMH$35.00
PLUMB TOP OUT COMM 03/14/2023 SMH$35.00
PLUMBING ROUGH-IN 03/27/2023 SMH$35.00
MECHANICAL ROUGH 03/30/2023 SMH$35.00
PLUMBING FINAL 11/07/2023 SMH$35.00
PLUMB TOP OUT COMM 11/17/2023 SMH$35.00
6 INCH COMP METER$5,290.00
WATER METER DEPOSIT COMMERCIAL$1,100.00
Total Fees:$451,560.24
______  ELECT ROUGH COMM
______  ELECT ROUGH COMM
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  ELECT ROUGH COMM
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  ELECT ROUGH COMM
______  ELECT ROUGH COMM
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  ELECT ROUGH COMM
______  PLUMB TOP OUT COMM
______  DRYWALL COMM
______  DRYWALL COMM
______  MECHANICAL ROUGH
______  SHEATHING COMM
______  ELECT ROUGH COMM
______  PLUMB TOP OUT COMM
______  DRYWALL COMM
______  MECHANICAL ROUGH
______  DRYWALL COMM
______  PLUMB TOP OUT COMM
______  MECHANICAL ROUGH
______  DRYWALL COMM
______  ELECT ROUGH COMM
______  SHEATHING COMM
______  DRYWALL COMM
______  ELECT ROUGH COMM
______  FRAME COMM
______  MECHANICAL ROUGH
______  MECHANICAL ROUGH
______  SHEATHING COMM
______  INSULATION COMM
______  DRYWALL COMM
______  MECHANICAL ROUGH
______  MECHANICAL ROUGH
______  PLUMB TOP OUT COMM
______  PLUMBING FINAL
______  MECHANICAL ROUGH
______  MECHANICAL ROUGH
______  FRAME COMM
______  MECHANICAL FINAL
______  DRYWALL COMM
______  DRYWALL COMM
______  FRAME COMM
______  PLUMBING FINAL
______  PLUMB TOP OUT COMM
______  PLUMBING FINAL
______  ELECT ROUGH COMM
______  MECHANICAL ROUGH
______  PLUMBING ROUGH-IN
______  PLUMB TOP OUT COMM
______  SHEATHING COMM
______  ELECT ROUGH COMM
______  DRYWALL COMM
______  MECHANICAL ROUGH
______  PLUMB TOP OUT COMM
______  MECHANICAL ROUGH
______  SHEATHING COMM
______  PLUMB TOP OUT COMM
______  MECHANICAL ROUGH
______  ELECT ROUGH COMM
______  MECHANICAL ROUGH
______  DRYWALL COMM
______  ELECT RELEASE COMM
______  INSULATION COMM
______  SHEATHING COMM
______  METER PAYMENT
______  ELECT ROUGH COMM
______  ELECT ROUGH COMM
______  MECHANICAL ROUGH
______  SET 6IN CMPND METER
______  SHEATHING COMM
______  FRAME COMM
______  FRAME COMM
______  MECHANICAL ROUGH
______  DRYWALL COMM
______  ELECT ROUGH COMM
______  ELECT ROUGH COMM
______  MECHANICAL ROUGH
______  DRYWALL COMM
______  INSULATION COMM
______  INSULATION COMM
______  MECHANICAL FINAL
______  MECHANICAL ROUGH
______  SHEATHING COMM
______  ELECT ROUGH COMM
______  ELECT ROUGH COMM
______  PLUMB TOP OUT COMM
______  MECHANICAL ROUGH
______  MECHANICAL ROUGH
______  MECHANICAL ROUGH
______  ELECT FINAL COMM
______  MECHANICAL ROUGH
______  PLUMBING ROUGH-IN
______  PLUMB TOP OUT COMM
______  ELECT FINAL COMM
______  ELECT FINAL COMM
______  PLUMB TOP OUT COMM
______  PLUMBING ROUGH-IN
______  MECHANICAL ROUGH
______  MECHANICAL ROUGH
______  ELECT ROUGH COMM
______  SHEATHING COMM
______  FIRE FINAL
______  MECHANICAL ROUGH
______  PLUMB TOP OUT COMM
______  PLUMBING ROUGH-IN
______  FIRE FINAL
______  COMM CO
______  PLUMBING ROUGH-IN
______  PLUMB TOP OUT COMM
______  PLUMBING ROUGH-IN
______  PLUMB TOP OUT COMM
______  INSULATION COMM
______  MECHANICAL ROUGH
______  PLUMB TOP OUT COMM
______  PLUMBING ROUGH-IN
______  PLUMB TOP OUT COMM
______  PLUMB TOP OUT COMM
______  PLUMB TOP OUT COMM
______  ELECT ROUGH COMM
______  PLUMB TOP OUT COMM
______  SHEATHING COMM
______  ELECT ROUGH COMM
______  ELECT ROUGH COMM
______  MECHANICAL ROUGH
______  INSULATION COMM
______  MECHANICAL ROUGH
______  MECHANICAL ROUGH
______  SHEATHING COMM
______  GAS PRESSURE
______  PLUMB TOP OUT COMM
______  PLUMB TOP OUT COMM
______  MECHANICAL ROUGH
______  PLUMB TOP OUT COMM
______  COMM CO
______  PLUMB TOP OUT COMM
______  MECHANICAL ROUGH
______  PLUMB TOP OUT COMM
______  MECHANICAL ROUGH
______  MECHANICAL ROUGH
______  DRYWALL COMM
______  FRAME COMM
______  INSULATION COMM
______  ELECT ROUGH COMM
______  ELECT ROUGH COMM
______  ELECT ROUGH COMM
______  MECHANICAL ROUGH
______  SHEATHING COMM
______  PLUMB TOP OUT COMM
______  BRICKWALL TIE COMM
______  ELECT ROUGH COMM
______  PLUMB TOP OUT COMM
______  MECHANICAL ROUGH
______  PLUMB TOP OUT COMM
______  COMM CO
______  PLUMB TOP OUT COMM
______  PLUMB TOP OUT COMM
______  ELECT ROUGH COMM
______  ELECT ROUGH COMM
______  PLUMB TOP OUT COMM
______  MECHANICAL ROUGH
______  ELECT ROUGH COMM
______  PLUMB TOP OUT COMM
______  PLUMB TOP OUT COMM
______  MECHANICAL ROUGH
______  MECHANICAL ROUGH
______  PLUMB TOP OUT COMM
______  PLUMB TOP OUT COMM
______  ELECT ROUGH COMM
______  MECHANICAL ROUGH
______  MECHANICAL ROUGH
______  ELECT ROUGH COMM
______  MECHANICAL ROUGH
______  PLUMB TOP OUT COMM
______  COMM CO
______  MECHANICAL ROUGH
______  ELECT ROUGH COMM
______  FRAME COMM
______  DRYWALL COMM
______  MECHANICAL ROUGH
______  ELECT ROUGH COMM
______  PLUMB TOP OUT COMM
______  ELECT WALL COMM
______  INSULATION COMM
______  ELECT RELEASE COMM
______  ELECT ROUGH COMM
______  FRAME COMM
______  ELECT FINAL COMM
______  ELECT ROUGH COMM
______  ELECT ROUGH COMM
______  COMM CO
______  PLUMB TOP OUT COMM
______  PLUMB TOP OUT COMM
______  INSULATION COMM
______  FRAME COMM
______  INSULATION COMM
______  FRAME COMM
______  ELECT ROUGH COMM
______  ELECT ROUGH COMM
______  PLUMB TOP OUT COMM
______  PLUMBING ROUGH-IN
______  FIRE LIFE SAFETY
______  FIRE FINAL
______  DRYWALL COMM
______  FRAME COMM
______  PLUMB TOP OUT COMM
______  PLUMBING ROUGH-IN
______  ELECT ROUGH COMM
______  MECHANICAL ROUGH
______  ELECT ROUGH COMM
______  FIRE FINAL
______  FIRE LIFE SAFETY
______  COMM CO
______  ELECT ROUGH COMM
______  PLUMBING ROUGH-IN
______  PLUMB TOP OUT COMM
______  MECHANICAL ROUGH
______  INSULATION COMM
______  ELECT ROUGH COMM
______  DRYWALL COMM
______  FRAME COMM
______  ELECT ROUGH COMM
______  MECHANICAL ROUGH
______  PLUMB TOP OUT COMM
______  INSULATION COMM
______  FRAME COMM
______  DRYWALL COMM
______  ELECT ROUGH COMM
______  FRAME COMM
______  INSULATION COMM
______  DRYWALL COMM
______  INSULATION COMM
______  INSULATION COMM
______  ELECT ROUGH COMM
______  DRYWALL COMM
______  ELECT ROUGH COMM
______  INSULATION COMM
______  FRAME COMM
______  PLUMB TOP OUT COMM
______  GAS PRESSURE
______  MECHANICAL ROUGH
______  INSULATION COMM
______  GAS PRESSURE
______  MECHANICAL ROUGH
______  DRYWALL COMM
______  MECHANICAL ROUGH
______  PLUMB TOP OUT COMM
______  INSULATION COMM
______  INSULATION COMM
______  ELECT ROUGH COMM
______  ELECT ROUGH COMM
______  INSULATION COMM
______  ELECT ROUGH COMM
______  PLUMB TOP OUT COMM
______  DRYWALL COMM
______  DRYWALL COMM
______  MECHANICAL ROUGH
______  ELECT ROUGH COMM
______  ELECT ROUGH COMM
______  DRYWALL COMM
______  PLUMB TOP OUT COMM
______  ELECT RELEASE COMM
______  ELECT ROUGH COMM
______  ELECT RELEASE COMM
______  ELECT RELEASE COMM
______  ELECT ROUGH COMM
______  PLUMB TOP OUT COMM
______  ELECT ROUGH COMM
______  PLUMB TOP OUT COMM
______  ELECT ROUGH COMM
______  PLUMB TOP OUT COMM
______  MECHANICAL FINAL
______  PLUMB TOP OUT COMM
______  PLUMBING FINAL
______  MECHANICAL FINAL
______  MECHANICAL FINAL
______  ELECT RELEASE COMM
______  MECHANICAL FINAL
______  PLUMBING FINAL
______  MECHANICAL FINAL
______  PLUMBING FINAL
______  ELECT FINAL COMM
______  MISC ELECTRIC COMM
______  ELECT FINAL COMM
______  PLUMB TOP OUT COMM
______  ELECT ROUGH COMM
______  ELECTRICAL COMM
______  ELECT FINAL COMM
______  PLUMBING FINAL
______  ELECT FINAL COMM
______  ELECT FINAL COMM
______  STOCK AND FURNISH
______  MECHANICAL FINAL
______  ELEVATOR
______  ELECT FINAL COMM
______  FIRE FINAL
______  ELEVATOR
______  ELECT FINAL COMM
______  ELEVATOR
______  FIRE FINAL
______  PLUMBING FINAL
______  MECHANICAL FINAL
______  ELECT FINAL COMM
______  FIRE FINAL
______  ELECT FINAL COMM
______  FIRE FINAL
______  FIRE FINAL
______  ELECT FINAL COMM
______  MECHANICAL FINAL
______  FIRE FINAL
______  PLUMBING FINAL
______  BUILDING FINAL
______  COMM CO
______  FIRE FINAL
______  FIRE FINAL
______  PLUMBING FINAL
______  COMM CO
______  FIRE FINAL
______  PLUMBING FINAL
______  ELECT FINAL COMM
______  COMM CO
______  FIRE FINAL
______  ELECT FINAL COMM
______  MECHANICAL FINAL
______  COMM CO
______  ELECT FINAL COMM
______  PLUMBING FINAL
______  ELECT FINAL COMM
______  ELECT FINAL COMM
______  ELECT FINAL COMM
______  ELECT FINAL COMM
______  MECHANICAL FINAL
______  PLUMBING FINAL
______  COMM CO
______  FIRE FINAL
______  ELECT FINAL COMM
______  FIRE FINAL
______  MECHANICAL FINAL
______  PLUMBING FINAL
______  COMM CO
______  MECHANICAL FINAL
______  PLUMBING FINAL
______  COMM CO
______  MECHANICAL FINAL
______  PLUMB TOP OUT COMM
______  ELECT FINAL COMM
______  COMM CO
______  MECHANICAL FINAL
______  MECHANICAL FINAL
______  PLUMBING FINAL
______  FIRE FINAL
______  MECHANICAL FINAL
______  MECHANICAL FINAL
______  PLUMBING FINAL
______  COMM CO
______  MECHANICAL FINAL
______  MECHANICAL FINAL
______  MECHANICAL FINAL
______  PLUMBING FINAL
______  PLUMBING FINAL
______  MECHANICAL FINAL
______  COMM CO
______  FIRE FINAL
______  COMM CO
______  BRICKWALL TIE COMM
______  PLUMBING FINAL
______  COMM CO
______  PLUMBING FINAL
______  ELECT FINAL COMM
______  FIRE FINAL
______  ELECT FINAL COMM
______  PLUMBING FINAL
______  MECHANICAL FINAL
______  MECHANICAL FINAL
______  MECHANICAL FINAL
______  COMM CO
______  FIRE FINAL
______  MECHANICAL FINAL
______  MECHANICAL FINAL
______  MECHANICAL FINAL
______  COMM CO
______  PLUMBING FINAL
______  ELECT FINAL COMM
______  COMM CO
______  PLUMBING FINAL
______  ELECT FINAL COMM
______  COMM CO
______  COMM CO
______  COMM CO
______  COMM CO
______  COMM CO
______  COMM CO
______  COMM CO
______  COMM CO
______  COMM CO
______  COMM CO
______  COMM CO
The project described shall be built in accordance with plans and specifications submitted at time of applications. All provisions of law and ordinances governing this type of work will be complied with whether specified or not. Granting of a permit does not presume to give authority to violate or cancel the provisions of any other local or state law regulating construction or the performance of construction. (The City will not assume responsibility for workability of sanitary sewer on all lots. NOTICE: A Certificate of Occupancy Must be Issued Before Any Building is Occupied.)

(THIS IS A BASIC PERMIT VIEW ONLY)