Seal BUILDING
Permit Payment Receipt


CITY OF FRISCO
6101 Frisco Square Blvd, TX 75034
Phone: 972.292.5301
APPROVED DATE: 11/17/2021 PERMIT SUB-TYPE: MNEW PERMIT NO: B21-03116
JOB ADDRESS:
4250 GRIDIRON RD
FRISCO, TX 75034
DESC:   539144 SF, THE CASEY
OWNER:
FRISCO UL3 PARTNERS LP

FORT WORTH TX 76177-1552

CONTRACTOR:
Rampart Multifamily , LLC
800 Industrial Blvd
Grapevine TX 76051
ISSUED DATE:
11/17/2021
APPLIED DATE:
6/15/2021
EXPIRED DATE:
12/14/2024
SITE APN:
ADD288260
STATUS:
COMPLETED
APPLICANT:
Monica Miranda
8340 Meadow Road
Dallas TX 75231
LEGAL DESC:
COUNTY:
ZONING:
VALUATION:
2880000
FEE SUMMARY
INSPECTION SUMMARY
DRYWALL COMM 06/21/2023 DC2$35.00
FRAME COMM 08/24/2023 DC2$35.00
FRAME COMM 09/28/2023 DC2$35.00
DRYWALL COMM 10/12/2023 DC2$35.00
FRAME COMM 10/24/2023 DC2$35.00
DRYWALL COMM 10/24/2023 DC2$35.00
DRYWALL COMM 11/02/2023 DC2$35.00
DRYWALL COMM 11/14/2023 DC2$35.00
DRYWALL COMM 11/15/2023 DC2$35.00
ELECT FINAL COMM 11/16/2023 DC2$35.00
CREDIT CARD FEE$1.40
PERCENT CREDIT CARD FEE$0.70
PERCENT CREDIT CARD FEE$2.10
PERCENT CREDIT CARD FEE$0.70
PERCENT CREDIT CARD FEE$1.40
PERCENT CREDIT CARD FEE$0.70
PERCENT CREDIT CARD FEE$2.70
PERCENT CREDIT CARD FEE$2.14
PERCENT CREDIT CARD FEE$2.14
PERCENT CREDIT CARD FEE$0.70
PERCENT CREDIT CARD FEE$1.40
PERCENT CREDIT CARD FEE$2.10
PERCENT CREDIT CARD FEE$5.60
PERCENT CREDIT CARD FEE$4.20
PERCENT CREDIT CARD FEE$1.00
PERCENT CREDIT CARD FEE$1.00
PERCENT CREDIT CARD FEE$0.70
SET 6IN CMPND METER 05/17/2023 HDJ$100.00
FIRE FINAL 01/19/2024 JS3$50.00
AUTO PROCESSING FEE$6.00
COMMERCIAL FEE$21,595.76
COMMERCIAL BUILDING PERMIT FEE$6,620.34
COMMERCIAL MECHANICAL FEE$26,987.20
COMMERCIAL NEW APPLICATION FEE$300.00
COMMERCIAL PLUMBING FEE$48,552.96
SEWER IMPACT FEE$90,396.00
THOROUGHFARE IMPACT FEE$108,488.00
WATER IMPACT FEE$91,446.00
AUTO PROCESSING FEE$2.00
PLAN REVIEW FEE$100.00
SLAB COMM 08/10/2022 REED$35.00
FRAME COMM 05/19/2023 REED$35.00
FRAME COMM 06/14/2023 REED$35.00
FRAME COMM 06/20/2023 REED$35.00
LATH COMM 08/23/2023 REED$35.00
INSULATION COMM 09/15/2023 REED$35.00
FRAME COMM 09/20/2023 REED$35.00
INSULATION COMM 11/17/2023 REED$35.00
DRYWALL COMM 11/29/2023 REED$35.00
FIRE FINAL 12/13/2023 RJB$50.00
PLUMB TOP OUT COMM 10/10/2022 SDC$35.00
PLUMBING ROUGH-IN 10/10/2022 SDC$35.00
PLUMB TOP OUT COMM 10/11/2022 SDC$35.00
PLUMBING ROUGH-IN 10/12/2022 SDC$35.00
PLUMBING ROUGH-IN 11/23/2022 SDC$35.00
PLUMBING ROUGH-IN 11/28/2022 SDC$35.00
PLUMBING FINAL 10/02/2023 SDC$35.00
MECHANICAL FINAL 10/05/2023 SDC$35.00
PLUMB TOP OUT COMM 10/18/2023 SDC$35.00
PLUMB TOP OUT COMM 10/23/2023 SDC$35.00
MECHANICAL FINAL 10/26/2023 SDC$35.00
PLUMB TOP OUT COMM 04/18/2023 SME2$35.00
PLUMBING ROUGH-IN 04/22/2022 SMH$35.00
PLUMBING ROUGH-IN 04/26/2022 SMH$35.00
PLUMB TOP OUT COMM 08/04/2023 SMH$35.00
MECHANICAL FINAL 02/21/2024 SMH$35.00
6 INCH COMP METER$5,770.00
WATER METER DEPOSIT COMMERCIAL$1,100.00
Total Fees:$402,819.94
______  FOOTINGS COMM
______  FOOTINGS COMM
______  FOOTINGS COMM
______  FOOTINGS COMM
______  FOOTINGS COMM
______  FOOTINGS COMM
______  FOOTINGS COMM
______  FOOTINGS COMM
______  FOOTINGS COMM
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  FOOTINGS COMM
______  PLUMBING ROUGH-IN
______  FOOTINGS COMM
______  PLUMBING ROUGH-IN
______  FOOTINGS COMM
______  PLUMBING ROUGH-IN
______  FOOTINGS COMM
______  PAVING
______  ELECT ROUGH COMM
______  FLATWORK COMM
______  PLUMBING ROUGH-IN
______  ELECT ROUGH COMM
______  SLAB COMM
______  PLUMBING ROUGH-IN
______  FOOTINGS COMM
______  PAVING
______  FOOTINGS COMM
______  ELECT ROUGH COMM
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  PAVING
______  SLAB COMM
______  SLAB COMM
______  SLAB COMM
______  SLAB COMM
______  SLAB COMM
______  SLAB COMM
______  SLAB COMM
______  SLAB COMM
______  PLUMBING ROUGH-IN
______  CMUWALL
______  PLUMB TOP OUT COMM
______  PLUMB TOP OUT COMM
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  PLUMB TOP OUT COMM
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  PLUMB TOP OUT COMM
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  SLAB COMM
______  SLAB COMM
______  SLAB COMM
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  SLAB COMM
______  SLAB COMM
______  SLAB COMM
______  T-POLE COMM
______  SLAB COMM
______  FOOTINGS COMM
______  INSULATION COMM
______  CMUWALL
______  SHEATHING COMM
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  SHEATHING COMM
______  ELECT ROUGH COMM
______  T-POLE COMM
______  SLAB COMM
______  ELECT ROUGH COMM
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  PLUMB TOP OUT COMM
______  PLUMB TOP OUT COMM
______  MECHANICAL ROUGH
______  SLAB COMM
______  FRAME COMM
______  MECHANICAL ROUGH
______  PLUMB TOP OUT COMM
______  ELECT ROUGH COMM
______  FRAME COMM
______  PLUMB TOP OUT COMM
______  PAVING
______  ELECT ROUGH COMM
______  MECHANICAL ROUGH
______  SHEATHING COMM
______  MECHANICAL ROUGH
______  ELECT ROUGH COMM
______  ELECT ROUGH COMM
______  FRAME COMM
______  INSULATION COMM
______  SHEATHING COMM
______  MECHANICAL ROUGH
______  INSULATION COMM
______  FRAME COMM
______  SET 6IN CMPND METER
______  FIREINSULATION
______  METER PAYMENT
______  FRAME COMM
______  INSULATION COMM
______  ELECT ROUGH COMM
______  ELECT ROUGH COMM
______  FRAME COMM
______  INSULATION COMM
______  PLUMB TOP OUT COMM
______  SET 6IN CMPND METER
______  PLUMB TOP OUT COMM
______  INSULATION COMM
______  PLUMB TOP OUT COMM
______  PLUMB TOP OUT COMM
______  DRYWALL COMM
______  INSULATION COMM
______  PLUMB TOP OUT COMM
______  DRYWALL COMM
______  DRYWALL COMM
______  FRAME COMM
______  FIREINSULATION
______  FRAME COMM
______  MECHANICAL ROUGH
______  PLUMB TOP OUT COMM
______  INSULATION COMM
______  ELECT RELEASE COMM
______  DRYWALL COMM
______  INSULATION COMM
______  FIREINSULATION
______  MECHANICAL ROUGH
______  INSULATION COMM
______  FRAME COMM
______  ELECT ROUGH COMM
______  FIREINSULATION
______  DRYWALL COMM
______  FRAME COMM
______  FRAME COMM
______  DRYWALL COMM
______  FRAME COMM
______  ELECT RELEASE COMM
______  FRAME COMM
______  DRYWALL COMM
______  BRICKWALL TIE COMM
______  BRICKWALL TIE COMM
______  BRICKWALL TIE COMM
______  DRYWALL COMM
______  DRYWALL COMM
______  INSULATION COMM
______  FIREINSULATION
______  INSULATION COMM
______  SHEATHING COMM
______  PLUMB TOP OUT COMM
______  INSULATION COMM
______  FIREINSULATION
______  PLUMB TOP OUT COMM
______  ELECT RELEASE COMM
______  INSULATION COMM
______  FIREINSULATION
______  SHEATHING COMM
______  FIREINSULATION
______  INSULATION COMM
______  FIREINSULATION
______  INSULATION COMM
______  DRYWALL COMM
______  INSULATION COMM
______  GAS PRESSURE
______  FIREINSULATION
______  BRICKWALL TIE COMM
______  GAS PRESSURE
______  DRYWALL COMM
______  MECHANICAL ROUGH
______  MECHANICAL ROUGH
______  SHEATHING COMM
______  MECHANICAL ROUGH
______  GAS PRESSURE
______  PLUMB TOP OUT COMM
______  DRYWALL COMM
______  GAS PRESSURE
______  MECHANICAL ROUGH
______  PLUMB TOP OUT COMM
______  ELECT ROUGH COMM
______  INSULATION COMM
______  FRAME COMM
______  MECHANICAL ROUGH
______  MECHANICAL ROUGH
______  GAS PRESSURE
______  PLUMB TOP OUT COMM
______  BRICKWALL TIE COMM
______  FIREINSULATION
______  CEILING
______  PLUMB TOP OUT COMM
______  MECHANICAL ROUGH
______  DRYWALL COMM
______  CEILING
______  INSULATION COMM
______  DRYWALL COMM
______  SHEATHING COMM
______  FIRE RATED WALL COMM
______  SHEATHING COMM
______  LATH COMM
______  CEILING
______  MECHANICAL ROUGH
______  ELECT ROUGH COMM
______  FRAME COMM
______  LATH COMM
______  FRAME COMM
______  PLUMB TOP OUT COMM
______  INSULATION COMM
______  ELECT RELEASE COMM
______  ELECT RELEASE COMM
______  LATH COMM
______  DRYWALL COMM
______  ELECT RELEASE COMM
______  ELECT ROUGH COMM
______  FRAME COMM
______  MECHANICAL ROUGH
______  PLUMB TOP OUT COMM
______  PLUMB TOP OUT COMM
______  PLUMB TOP OUT COMM
______  LATH COMM
______  MECHANICAL ROUGH
______  PLUMB TOP OUT COMM
______  FRAME COMM
______  ELECT ROUGH COMM
______  LATH COMM
______  MISC FRAME COMM
______  MECHANICAL ROUGH
______  INSULATION COMM
______  FRAME COMM
______  FIREINSULATION
______  ELECT ROUGH COMM
______  LATH COMM
______  LATH COMM
______  ELECT ROUGH COMM
______  INSULATION COMM
______  MECHANICAL ROUGH
______  PLUMB TOP OUT COMM
______  PLUMB TOP OUT COMM
______  FRAME COMM
______  MECHANICAL ROUGH
______  ELECT ROUGH COMM
______  MECHANICAL ROUGH
______  MECHANICAL FINAL
______  INSULATION COMM
______  PLUMB TOP OUT COMM
______  FRAME COMM
______  FIREINSULATION
______  LATH COMM
______  PLUMBING FINAL
______  FRAME COMM
______  ELECT ROUGH COMM
______  DRYWALL COMM
______  FRAME COMM
______  PLUMBING FINAL
______  FRAME COMM
______  ELECT FINAL COMM
______  FIREINSULATION
______  INSULATION COMM
______  LATH COMM
______  PLUMBING FINAL
______  MECHANICAL FINAL
______  DRYWALL COMM
______  DRYWALL COMM
______  MECHANICAL FINAL
______  MECHANICAL ROUGH
______  DRYWALL COMM
______  DRYWALL COMM
______  INSULATION COMM
______  FIREINSULATION
______  FRAME COMM
______  ELECT ROUGH COMM
______  DRYWALL COMM
______  INSULATION COMM
______  PLUMBING FINAL
______  PLUMB TOP OUT COMM
______  MECHANICAL FINAL
______  INSULATION COMM
______  PLUMB TOP OUT COMM
______  MECHANICAL ROUGH
______  FIREINSULATION
______  FRAME COMM
______  PLUMB TOP OUT COMM
______  FRAME COMM
______  ELECT ROUGH COMM
______  DRYWALL COMM
______  ELECT FINAL COMM
______  MECHANICAL FINAL
______  FRAME COMM
______  DRYWALL COMM
______  PLUMBING FINAL
______  MECHANICAL ROUGH
______  FRAME COMM
______  MECHANICAL FINAL
______  ELECT FINAL COMM
______  DRYWALL COMM
______  MECHANICAL ROUGH
______  FRAME COMM
______  ELECT ROUGH COMM
______  FIREINSULATION
______  DRYWALL COMM
______  INSULATION COMM
______  INSULATION COMM
______  MECHANICAL FINAL
______  FIREINSULATION
______  STOCK AND FURNISH
______  ELECT ROUGH COMM
______  FRAME COMM
______  GAS PRESSURE
______  PLUMBING FINAL
______  MECHANICAL ROUGH
______  ELECT FINAL COMM
______  INSULATION COMM
______  FIREINSULATION
______  INSULATION COMM
______  DRYWALL COMM
______  DRYWALL COMM
______  PLUMBING FINAL
______  MECHANICAL ROUGH
______  ELECT FINAL COMM
______  MECHANICAL FINAL
______  PLUMBING FINAL
______  ELECT ROUGH COMM
______  INSULATION COMM
______  FRAME COMM
______  ELECT FINAL COMM
______  MECHANICAL FINAL
______  INSULATION COMM
______  DRYWALL COMM
______  FIREINSULATION
______  INSULATION COMM
______  FIREINSULATION
______  MECHANICAL FINAL
______  PLUMBING FINAL
______  ELECT ROUGH COMM
______  ELECT FINAL COMM
______  DRYWALL COMM
______  DRYWALL COMM
______  INSULATION COMM
______  PLUMBING FINAL
______  FIREINSULATION
______  ELECT FINAL COMM
______  MECHANICAL FINAL
______  PLUMBING FINAL
______  PLUMBING FINAL
______  DRYWALL COMM
______  DRYWALL COMM
______  MECHANICAL FINAL
______  PLUMBING FINAL
______  ELECT FINAL COMM
______  MECHANICAL FINAL
______  PLUMBING FINAL
______  MECHANICAL FINAL
______  PLUMBING FINAL
______  ELECT FINAL COMM
______  FIRE FINAL
______  BUILDING FINAL
______  BUILDING FINAL
______  MECHANICAL FINAL
______  BUILDING FINAL
______  BUILDING FINAL
______  PLUMBING FINAL
______  FIRE FINAL
______  COMM CO
______  COMM CO
______  DRYWALL COMM
______  ELEVATOR
______  FIRE FINAL
______  COMM CO
______  COMM CO
______  MECHANICAL FINAL
______  ELECT FINAL COMM
______  ELECT FINAL COMM
______  PLUMBING FINAL
______  MECHANICAL FINAL
______  ELECT FINAL COMM
______  PLUMBING FINAL
______  PLUMBING FINAL
______  MECHANICAL FINAL
______  ELECT RELEASE COMM
______  MECHANICAL FINAL
______  FOOTINGS COMM
______  ELECT FINAL COMM
______  PLUMBING FINAL
______  FIRE FINAL
______  COMM CO
______  PLUMBING FINAL
______  PLUMBING FINAL
______  ELECT FINAL COMM
______  FOOTINGS COMM
______  MECHANICAL FINAL
______  PLUMBING FINAL
______  ELECT FINAL COMM
______  FIRE FINAL
______  COMM CO
______  PLUMBING FINAL
______  MECHANICAL FINAL
______  ELECT FINAL COMM
______  ELECT FINAL COMM
______  PLUMBING FINAL
______  ELECT FINAL COMM
______  PLUMBING FINAL
______  MECHANICAL FINAL
______  PLUMBING FINAL
______  ELECT FINAL COMM
______  PLUMBING FINAL
______  ELECT FINAL COMM
______  PLUMBING FINAL
______  MECHANICAL FINAL
______  MECHANICAL FINAL
______  MECHANICAL FINAL
______  PLUMBING FINAL
______  FIRE FINAL
______  MECHANICAL FINAL
______  ELECT FINAL COMM
______  PLUMBING FINAL
______  MECHANICAL FINAL
______  PLUMBING FINAL
______  MECHANICAL FINAL
______  PLUMBING FINAL
______  ELECT FINAL COMM
______  FIRE FINAL
______  PLUMBING FINAL
______  COMM CO
______  PLUMBING FINAL
______  PLUMBING FINAL
______  MECHANICAL FINAL
______  ELECT FINAL COMM
______  PLUMBING FINAL
______  MECHANICAL FINAL
______  PAVING
______  ELECT FINAL COMM
______  MECHANICAL FINAL
______  MECHANICAL FINAL
______  PLUMBING FINAL
______  FLATWORK COMM
______  FIRE FINAL
______  FIRE FINAL
______  ELEVATOR
______  COMM CO
______  GAS RELEASE
______  COMM CO
______  ELEVATOR
______  ELEVATOR
______  INSPECTION ASSIST
______  ELEVATOR
______  COMM CO
______  COMM CO
Notes: