BUILDING
PERMIT
Inspections Line: 972.292.5386 cut-off at 4 PM the business day before
OR
Request Inspections online at https:\\etrakit.friscotexas.gov\etrakit until 7:00 AM same day
Contact assigned inspector for cancellation.
|
CITY OF FRISCO
6101 Frisco Square Blvd, TX 75034
Phone: 972.292.5301
|
APPROVED DATE: 7/29/2021
|
PERMIT SUB-TYPE: SNEW
|
PERMIT NO: B21-03065
|
JOB ADDRESS: 12205 FARMSTEAD DR FRISCO, TX 75033 |
DESC:
7709 AC, 9819 SF, 2 STORY |
|
OWNER:
NEWMAN VILLAGE CONSTRUCTION LLC
9801 CAMFIELD WAY FRISCO TX 75033
|
CONTRACTOR:
VCH CONSTRUCTION LP
17814 DAVENPORT RD STE 113 DALLAS TX 75252
|
ISSUED DATE: 7/29/2021
APPLIED DATE:7/8/2021
EXPIRED DATE:1/8/2024
SITE APN:ADD191042
STATUS:COMPLETED
|
|
APPLICANT:
Loy Lowary
17814 Davenport Rd Dallas TX 75252
|
LEGAL DESC:
COUNTY:
ZONING:
VALUATION: 0
|
|
FEE SUMMARY
|
INSPECTION SUMMARY
|
T-POLE RES 09/02/2021 BC | $30.00 |
SHEATHING RES 01/14/2022 BC | $30.00 |
1 INCH PD METER | $450.00 |
WATER METER DEPOSIT | $125.00 |
2NDS AND FRAMING 08/08/2022 CAB | $30.00 |
2NDS AND FRAMING 08/10/2022 CAB | $30.00 |
PTO AND MECH ROUGH 05/31/2022 CI | $30.00 |
PTO AND MECH ROUGH 07/08/2022 CI | $30.00 |
PLAN REVIEW FEE | $50.00 |
CREDIT CARD FEE | $11.50 |
CREDIT CARD FEE | $1.20 |
PERCENT CREDIT CARD FEE | $1.80 |
PERCENT CREDIT CARD FEE | $2.40 |
PERCENT CREDIT CARD FEE | $2.40 |
PERCENT CREDIT CARD FEE | $2.00 |
PERCENT CREDIT CARD FEE | $0.60 |
2NDS AND FRAMING 07/14/2022 JWE2 | $30.00 |
AUTO PROCESSING FEE | $6.00 |
FENCE FEE | $20.00 |
RESIDENTIAL NEW PERMIT FEE | $3,022.94 |
RESIDENTIAL FEE | $294.57 |
RESIDENTIAL MECHANICAL FEE | $251.00 |
RESIDENTIAL NEW APPLICATION FEE | $300.00 |
RESIDENTIAL PLUMBING FEE | $437.00 |
SEWER IMPACT FEE | $2,294.00 |
THOROUGHFARE IMPACT FEE | $5,322.00 |
WATER IMPACT FEE | $3,085.00 |
SHEATHING RES 03/16/2022 RWK | $30.00 |
CO AND BUILD FINAL 07/06/2023 RWK | $30.00 |
2NDS AND FRAMING 07/20/2022 RWT | $30.00 |
2NDS AND FRAMING 07/25/2022 RWT | $30.00 |
2NDS AND FRAMING 08/04/2022 RWT | $30.00 |
PTO AND MECH ROUGH 05/17/2022 SMH | $30.00 |
PTO AND MECH ROUGH 07/05/2022 SMH | $30.00 |
UTILITIES INSPECTION 06/28/2023 TL | $100.00 |
Total Fees: | $16,199.41 |
|
|
| ______ T-POLE RES |
______ T-POLE RES |
______ METER PAYMENT |
______ SET 1 PD METER |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ SLAB RES |
______ SLAB RES |
______ SHEATHING RES |
______ SHEATHING RES |
______ SHEATHING RES |
______ LATH RES |
______ PTO AND MECH ROUGH |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ PTO AND MECH ROUGH |
______ PTO AND MECH ROUGH |
______ PTO AND MECH ROUGH |
______ ELECT ROUGH RES |
______ PTO AND MECH ROUGH |
______ PTO AND MECH ROUGH |
______ PTO AND MECH ROUGH |
______ 2NDS AND FRAMING |
______ 2NDS AND FRAMING |
______ 2NDS AND FRAMING |
______ 2NDS AND FRAMING |
______ INSULATION RES |
______ 2NDS AND FRAMING |
______ 2NDS AND FRAMING |
______ 2NDS AND FRAMING |
______ 2NDS AND FRAMING |
______ INSULATION RES |
______ DRYWALL RES |
______ DRYWALL RES |
______ FLATWORK RES |
______ FLATWORK RES |
______ GAS RELEASE |
______ GAS RELEASE |
______ GAS RELEASE |
______ ELECT FINAL RES |
______ ELECT FINAL RES |
______ PLUMB MECH FINAL |
______ PLUMB MECH FINAL |
______ UTILITIES INSPECTION |
______ PLUMB MECH FINAL |
______ UTILITIES INSPECTION |
______ PLUMB MECH FINAL |
______ CO AND BUILD FINAL |
______ CO AND BUILD FINAL |
______ CO AND BUILD FINAL |
|
The project described shall be built in accordance with plans and specifications submitted at time of applications. All provisions of law and ordinances governing this type of work will be complied with whether specified or not. Granting of a permit does not presume to give authority to violate or cancel the provisions of any other local or state law regulating construction or the performance of construction. (The City will not assume responsibility for workability of sanitary sewer on all lots. NOTICE: A Certificate of Occupancy Must be Issued Before Any Building is Occupied.)
|
(THIS IS A BASIC PERMIT VIEW ONLY)
|
|