Seal BUILDING
Permit Payment Receipt


CITY OF FRISCO
6101 Frisco Square Blvd, TX 75034
Phone: 972.292.5301
APPROVED DATE: 6/9/2021 PERMIT SUB-TYPE: SNEW PERMIT NO: B21-01699
JOB ADDRESS:
6148 BLYTHE DR
FRISCO, TX 75035
DESC:   1702 AC, 2172 SF, 2 STORY
OWNER:
GABLES LLC MEGATEL
2101 CEDAR SPRINGS RD STE 700
DALLAS TX 75201-1504

CONTRACTOR:
MEGATEL HOMES INC
2101 Cedar Springs Rd #700
Dallas TX 75201
ISSUED DATE:
6/9/2021
APPLIED DATE:
5/17/2021
EXPIRED DATE:
10/25/2023
SITE APN:
ADD159034
STATUS:
COMPLETED
APPLICANT:
Hannah Rodgers
2101 Cedar Springs Rd #700
Dallas TX 75201
LEGAL DESC:
COUNTY:
ZONING:
VALUATION:
0
FEE SUMMARY
INSPECTION SUMMARY
PLAN REVIEW FEE$50.00
2NDS AND FRAMING 10/27/2022 CMM2$30.00
2NDS AND FRAMING 11/18/2022 CMM2$30.00
SHEATHING RES 11/23/2022 CMM2$30.00
2NDS AND FRAMING 12/05/2022 DC2$30.00
2NDS AND FRAMING 12/09/2022 DC2$30.00
INSULATION RES 12/21/2022 DC2$30.00
DRYWALL RES 01/10/2023 DC2$30.00
PLAN REVIEW FEE$10.00
SLAB RES 09/10/2021 DW2$30.00
SLAB RES 09/20/2021 DW2$30.00
DRYWALL RES 01/11/2023 DW2$30.00
SLAB RES 09/09/2021 DWF$30.00
CREDIT CARD FEE$3.80
PERCENT CREDIT CARD FEE$1.80
PERCENT CREDIT CARD FEE$0.00
PERCENT CREDIT CARD FEE$2.40
PERCENT CREDIT CARD FEE$0.20
PERCENT CREDIT CARD FEE$0.60
PERCENT CREDIT CARD FEE$12.00
PERCENT CREDIT CARD FEE$2.00
SET 1 PD METER 07/06/2021 JRC$100.00
1 INCH PD METER$450.00
WATER METER DEPOSIT$125.00
PTO AND MECH ROUGH 08/26/2022 MLM$30.00
AUTO PROCESSING FEE$0.00
FENCE FEE$20.00
RESIDENTIAL NEW PERMIT FEE$763.64
RESIDENTIAL FEE$65.16
RESIDENTIAL MECHANICAL FEE$106.50
RESIDENTIAL NEW APPLICATION FEE$300.00
RESIDENTIAL PLUMBING FEE$205.00
SEWER IMPACT FEE$1,619.00
THOROUGHFARE IMPACT FEE$0.00
WATER IMPACT FEE$1,939.00
PTO AND MECH ROUGH 09/22/2022 SDC$30.00
GAS RELEASE 03/20/2023 SME2$30.00
UTILITIES INSPECTION 04/04/2023 TL$100.00
REPLACE READABLE REGISTER$310.00
UTILITIES INSPECTION 04/10/2023 TL$100.00
UTILITIES INSPECTION 04/17/2023 TL$100.00
Total Fees:$6,806.10
______  T-POLE RES
______  SET 1 PD METER
______  PLUMBING ROUGH-IN
______  SET 1 PD METER
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  SLAB RES
______  SLAB RES
______  SLAB RES
______  SLAB RES
______  SLAB RES
______  SLAB RES
______  MISC FRAME RES
______  MISC FRAME RES
______  SHEATHING RES
______  PTO AND MECH ROUGH
______  PTO AND MECH ROUGH
______  PTO AND MECH ROUGH
______  PTO AND MECH ROUGH
______  PTO AND MECH ROUGH
______  2NDS AND FRAMING
______  2NDS AND FRAMING
______  2NDS AND FRAMING
______  SHEATHING RES
______  SHEATHING RES
______  2NDS AND FRAMING
______  2NDS AND FRAMING
______  2NDS AND FRAMING
______  BRICKWALL TIES RES
______  INSULATION RES
______  INSULATION RES
______  INSULATION RES
______  INSULATION RES
______  DRYWALL RES
______  DRYWALL RES
______  DRYWALL RES
______  FLATWORK RES
______  FLATWORK RES
______  ELECT FINAL RES
______  PLUMB MECH FINAL
______  GAS RELEASE
______  GAS RELEASE
______  UTILITIES INSPECTION
______  UTILITIES INSPECTION
______  WATER REGISTER
______  UTILITIES INSPECTION
______  UTILITIES INSPECTION
______  PLUMB MECH FINAL
______  UTILITIES INSPECTION
______  UTILITIES INSPECTION
______  PLUMB MECH FINAL
______  PLUMB MECH FINAL
______  PLUMB MECH FINAL
______  CO AND BUILD FINAL
______  CO AND BUILD FINAL
______  CO AND BUILD FINAL
______  CO AND BUILD FINAL
______  METER PAYMENT
Notes: