Seal BUILDING
Permit Payment Receipt


CITY OF FRISCO
6101 Frisco Square Blvd, TX 75034
Phone: 972.292.5301
APPROVED DATE: 7/27/2021 PERMIT SUB-TYPE: CNEW PERMIT NO: B21-01486
JOB ADDRESS:
2115 UNIVERSITY DR
FRISCO, TX 75033
DESC:   12664 SF, HOLLYHOCK COMMERICAL BLDG 2
OWNER:
NEW CORNERS LLC

Plano TX 75024

CONTRACTOR:
FIRST INFRA LLC
1925 E Beltline Rd , STE 446
Carrollton TX 75006
ISSUED DATE:
7/27/2021
APPLIED DATE:
3/22/2021
EXPIRED DATE:
4/24/2023
SITE APN:
ADD283439
STATUS:
COMPLETED
APPLICANT:
ravi First Infra
1925 E Belt Line road, Suite 446
carollton TX 75006
LEGAL DESC:
COUNTY:
ZONING:
VALUATION:
1234300
FEE SUMMARY
INSPECTION SUMMARY
FLATWORK COMM 05/19/2022 CW$35.00
CREDIT CARD FEE$38.50
PERCENT CREDIT CARD FEE$0.70
COMM BUILDING PERMIT FEE$50.00
ILLEGAL JUMPER$500.00
AUTO PROCESSING FEE$6.00
COMMERCIAL FEE$523.72
COMMERCIAL BUILDING PERMIT FEE$3,509.40
COMMERCIAL MECHANICAL FEE$43.50
COMMERCIAL NEW APPLICATION FEE$300.00
COMMERCIAL PLUMBING FEE$1,140.87
SEWER IMPACT FEE$21,428.00
THOROUGHFARE IMPACT FEE$46,755.00
WATER IMPACT FEE$38,760.00
AUTO PROCESSING FEE$11.00
2 INCH T-10 METER$825.00
WATER METER DEPOSIT COMMERCIAL$1,100.00
Total Fees:$115,026.69
______  PIER COMM
______  ELECT ROUGH COMM
______  ELECT ROUGH COMM
______  PLUMBING ROUGH-IN
______  FLATWORK COMM
______  SLAB COMM
______  FIRELANE INSPECTION
______  T-POLE COMM
______  FRAME COMM
______  SHEATHING COMM
______  BRICKWALL TIE COMM
______  T-POLE COMM
______  LATH COMM
______  LATH COMM
______  CMUWALL
______  ELECT ROUGH COMM
______  PLUMB TOP OUT COMM
______  METER PAYMENT
______  PLUMB TOP OUT COMM
______  SET 2 T-10 METER
______  FRAME COMM
______  ELECT ROUGH COMM
______  INSULATION COMM
______  MECHANICAL ROUGH
______  MECHANICAL FINAL
______  FLATWORK COMM
______  ELECT RELEASE COMM
______  ELECT RELEASE COMM
______  FLATWORK COMM
______  ELECT RELEASE COMM
______  ELECT FINAL COMM
______  MECHANICAL FINAL
______  ELECT FINAL COMM
______  FIRE FINAL
______  BUILDING FINAL
______  BUILDING FINAL
______  BUILDING FINAL
______  BUILDING FINAL
Notes: