Seal BUILDING
Permit Payment Receipt


CITY OF FRISCO
6101 Frisco Square Blvd, TX 75034
Phone: 972.292.5301
APPROVED DATE: 3/24/2021 PERMIT SUB-TYPE: SNEW PERMIT NO: B21-01286
JOB ADDRESS:
1139 RUTHERFORD ST
FRISCO, TX 75036
DESC:   3122 AC, 4256 SF, 2 STORY
OWNER:
CTMGT FRISCO 122 LLC
1800 VALLEY VIEW LN STE 300
FARMERS BRANCH TX 75234-8945

CONTRACTOR:
FIRST TEXAS CUSTOM HOMES
500 CRESCENT CT STE 350
DALLAS TX 75201
ISSUED DATE:
3/24/2021
APPLIED DATE:
3/22/2021
EXPIRED DATE:
2/6/2023
SITE APN:
ADD230553
STATUS:
COMPLETED
APPLICANT:
Ana Gutierrez
500 Crescent Court, Suite 350
Dallas TX 75201
LEGAL DESC:
COUNTY:
ZONING:
VALUATION:
0
FEE SUMMARY
INSPECTION SUMMARY
1 INCH PD METER$450.00
WATER METER DEPOSIT$125.00
ELECT FINAL RES 06/16/2022 DWF$30.00
ELECT FINAL RES 06/22/2022 DWF$30.00
CREDIT CARD FEE$1.20
CREDIT CARD FEE$0.60
PERCENT CREDIT CARD FEE$0.60
2NDS AND FRAMING 03/15/2022 RWT$30.00
2NDS AND FRAMING 03/18/2022 RWT$30.00
UTILITIES INSPECTION 07/18/2022 TL$100.00
FLATWORK RES 02/01/2022 RWT$30.00
PLUMB MECH FINAL 08/04/2022 MLM$30.00
PLUMB MECH FINAL 08/03/2022 MLM$30.00
PTO AND MECH ROUGH 03/09/2022 JWI$30.00
PTO AND MECH ROUGH 03/04/2022 JWI$30.00
PTO AND MECH ROUGH 03/01/2022 JWI$30.00
SET 1 PD METER 07/21/2021 ZM$100.00
PERCENT CREDIT CARD FEE$0.60
CREDIT CARD FEE$1.20
CREDIT CARD FEE$1.20
CREDIT CARD FEE$0.60
CREDIT CARD FEE$0.60
CREDIT CARD FEE$2.00
SLAB RES 09/03/2021 BC$30.00
SLAB RES 08/31/2021 BC$30.00
SLAB RES 08/24/2021 BC$30.00
PERCENT CREDIT CARD FEE$2.00
WATER IMPACT FEE$825.00
THOROUGHFARE IMPACT FEE$0.00
SEWER IMPACT FEE$2,344.00
RESIDENTIAL PLUMBING FEE$250.00
RESIDENTIAL NEW APPLICATION FEE$300.00
RESIDENTIAL MECHANICAL FEE$146.00
RESIDENTIAL FEE$127.68
RESIDENTIAL NEW PERMIT FEE$1,476.92
FENCE FEE$20.00
AUTO PROCESSING FEE$0.00
PERCENT CREDIT CARD FEE$1.20
Total Fees:$6,666.40
______  METER PAYMENT
______  T-POLE RES
______  SET 1 PD METER
______  SET 1 PD METER
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  SLAB RES
______  SLAB RES
______  SLAB RES
______  SLAB RES
______  FLATWORK RES
______  FLATWORK RES
______  PTO AND MECH ROUGH
______  PTO AND MECH ROUGH
______  PTO AND MECH ROUGH
______  PTO AND MECH ROUGH
______  PTO AND MECH ROUGH
______  PTO AND MECH ROUGH
______  2NDS AND FRAMING
______  2NDS AND FRAMING
______  2NDS AND FRAMING
______  INSULATION RES
______  DRYWALL RES
______  DRYWALL RES
______  BRICKWALL TIES RES
______  ELECT FINAL RES
______  ELECT FINAL RES
______  ELECT FINAL RES
______  GAS RELEASE
______  GAS RELEASE
______  UTILITIES INSPECTION
______  UTILITIES INSPECTION
______  2NDS AND FRAMING
______  PLUMB MECH FINAL
______  PLUMB MECH FINAL
______  PLUMB MECH FINAL
______  PLUMB MECH FINAL
______  CO AND BUILD FINAL
______  CO AND BUILD FINAL
Notes: