Seal BUILDING
PERMIT
Inspections Line: 972.292.5386 cut-off at 4 PM the business day before
OR
Request Inspections online at https:\\etrakit.friscotexas.gov\etrakit until 7:00 AM same day
Contact assigned inspector for cancellation.
CITY OF FRISCO
6101 Frisco Square Blvd, TX 75034
Phone: 972.292.5301
APPROVED DATE: 10/12/2021 PERMIT SUB-TYPE: CNEW PERMIT NO: B21-00753
JOB ADDRESS:
12255 UNIVERSITY DR
FRISCO, TX 75035
DESC:   14010 SF, THREE CORNERS PLAZA BLDG 3
OWNER:
3 CORNERS PLAZA LLC

FAIR OAKS RANCH TX 78015-5134

CONTRACTOR:
RIDGEMONT COMMERCIAL CONSTRUCTION
1520 W Walnut Hill Ln
Irving TX 75038
ISSUED DATE:
10/12/2021
APPLIED DATE:
2/12/2021
EXPIRED DATE:
9/6/2023
SITE APN:
ADD279254
STATUS:
COMPLETED
APPLICANT:
HanCheng Liu
3227 McKinney Ave, Suite 201
Dallas TX 75204
LEGAL DESC:
COUNTY:
ZONING:
VALUATION:
8000000
FEE SUMMARY
INSPECTION SUMMARY
2 INCH T-10 METER$825.00
WATER METER DEPOSIT COMMERCIAL$1,100.00
BRICKWALL TIE COMM 04/28/2022 CW$35.00
BRICKWALL TIE COMM 05/05/2022 CW$35.00
ELECT ROUGH COMM 09/21/2022 CW$35.00
CREDIT CARD FEE$0.70
PERCENT CREDIT CARD FEE$1.40
PERCENT CREDIT CARD FEE$2.70
SET 2 T-10 METER 08/23/2022 HDJ$100.00
PLUMB TOP OUT COMM 07/18/2022 JWI$35.00
AUTO PROCESSING FEE$6.00
COMMERCIAL FEE$590.40
COMMERCIAL BUILDING PERMIT FEE$16,297.14
COMMERCIAL MECHANICAL FEE$0.00
COMMERCIAL NEW APPLICATION FEE$300.00
COMMERCIAL PLUMBING FEE$1,290.90
SEWER IMPACT FEE$0.00
THOROUGHFARE IMPACT FEE$0.00
WATER IMPACT FEE$0.00
Total Fees:$20,654.24
______  FOOTINGS COMM
______  ELECT ROUGH COMM
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  FIRELANE INSPECTION
______  FRAME COMM
______  ELECT ROUGH COMM
______  ELECT ROUGH COMM
______  GREASE TRAP
______  GREASE TRAP
______  FRAME COMM
______  BRICKWALL TIE COMM
______  PLUMB TOP OUT COMM
______  PLUMBING ROUGH-IN
______  FRAME COMM
______  SHEATHING COMM
______  BRICKWALL TIE COMM
______  BRICKWALL TIE COMM
______  SHEATHING COMM
______  BRICKWALL TIE COMM
______  ELECT ROUGH COMM
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  LATH COMM
______  LATH COMM
______  PLUMB TOP OUT COMM
______  LATH COMM
______  FOOTINGS COMM
______  ELECT RELEASE COMM
______  METER PAYMENT
______  ELECT RELEASE COMM
______  SET 2 T-10 METER
______  SET 2 T-10 METER
______  ELECT RELEASE COMM
______  PLUMB TOP OUT COMM
______  PLUMBING FINAL
______  ELECT FINAL COMM
______  ELECT ROUGH COMM
______  PLUMBING FINAL
______  PLUMBING FINAL
______  ELECT ROUGH COMM
______  ELECT ROUGH COMM
______  INSULATION COMM
______  FLATWORK COMM
______  FIRE FINAL
______  BUILDING FINAL
______  BUILDING FINAL
______  PLUMBING FINAL
______  BUILDING FINAL
______  BUILDING FINAL
______  PLUMBING FINAL
______  BUILDING FINAL
______  BUILDING FINAL
The project described shall be built in accordance with plans and specifications submitted at time of applications. All provisions of law and ordinances governing this type of work will be complied with whether specified or not. Granting of a permit does not presume to give authority to violate or cancel the provisions of any other local or state law regulating construction or the performance of construction. (The City will not assume responsibility for workability of sanitary sewer on all lots. NOTICE: A Certificate of Occupancy Must be Issued Before Any Building is Occupied.)

(THIS IS A BASIC PERMIT VIEW ONLY)