APPROVED DATE: 11/7/2019
|
PERMIT SUB-TYPE: CNEW
|
PERMIT NO: B19-04682
|
JOB ADDRESS: 5440 WARREN PKWY FRISCO, TX 75034 |
DESC:
4975 SF, BRAKES PLUS |
|
OWNER:
TIMELESS REAL ESTATE INC
RICHARDSON TX 75082-9705
|
CONTRACTOR:
BBD CONSTRUCTION, LLC
5040 TENNYSON PKWY DALLAS TX 75024
|
ISSUED DATE: 2/24/2020
APPLIED DATE:10/23/2019
EXPIRED DATE:4/4/2021
SITE APN:C2721334
STATUS:COMPLETED
|
|
APPLICANT:
ANDY GOLDEN
1880 SOUTHPARK DR BIRMINGHAM AL 35244
|
LEGAL DESC:
COUNTY:
ZONING:
VALUATION: 600000
|
|
FEE SUMMARY
|
INSPECTION SUMMARY
|
CREDIT CARD FEE | $1.00 |
CREDIT CARD FEE | $4.99 |
CREDIT CARD FEE | $2.00 |
COMMERCIAL FEE | $229.00 |
COMMERCIAL BUILDING PERMIT FEE | $2,225.25 |
COMMERCIAL MECHANICAL FEE | $278.75 |
COMMERCIAL PLUMBING FEE | $477.75 |
SEWER IMPACT FEE | $3,348.00 |
THOROUGHFARE IMPACT FEE | $11,582.00 |
WATER IMPACT FEE | $6,056.00 |
FIRE DEPT INSPECTION FEES | $50.00 |
FIRE DEPT INSPECTION FEES | $249.25 |
FIRE DEPT INSPECTION FEES | $100.00 |
T-POLE COMM 05/01/2020 REED | $35.00 |
1 INCH PD METER | $450.00 |
WATER METER DEPOSIT COMMERCIAL | $1,125.00 |
Total Fees: | $26,213.99 |
|
|
| ______ UNDRGR FIRE MAIN VIS |
______ UNDRGR FIRE MAIN HYD |
______ UNDRGR FIRE MAIN FLU |
______ MISC ELECTRIC COMM |
______ UNDRGR FIRE MAIN FLU |
______ T-POLE COMM |
______ T-POLE COMM |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ METER PAYMENT |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ SET 1 PD METER |
______ UNDERGROUND ELEC |
______ FOOTINGS COMM |
______ GREASE TRAP |
______ SLAB COMM |
______ CMUWALL |
______ UNDERGROUND ELEC |
______ FRAME COMM |
______ BRICKWALL TIE COMM |
______ BRICKWALL TIE COMM |
______ BRICKWALL TIE COMM |
______ PLUMB TOP OUT COMM |
______ ELECT ROUGH COMM |
______ FRAME COMM |
______ PLUMBING TOP OUT |
______ INSULATION COMM |
______ PIER COMM |
______ DRYWALL COMM |
______ FOOTINGS COMM |
______ AUTOFIRE SPRK HYDRO |
______ MECHANICAL ROUGH |
______ MECHANICAL ROUGH |
______ ELECT RELEASE COMM |
______ ELECT RELEASE COMM |
______ CEILING |
______ GAS PRESSURE |
______ ELECT FINAL COMM |
______ GAS RELEASE |
______ PLUMBING FINAL |
______ MECHANICAL FINAL |
______ FIRE FINAL |
______ COMM CO |
______ COMM CO |
______ FIRE FINAL |
______ COMM CO |
|
The project described shall be built in accordance with plans and specifications submitted at time of applications. All provisions of law and ordinances governing this type of work will be complied with whether specified or not. Granting of a permit does not presume to give authority to violate or cancel the provisions of any other local or state law regulating construction or the performance of construction. (The City will not assume responsibility for workability of sanitary sewer on all lots. NOTICE: A Certificate of Occupancy Must be Issued Before Any Building is Occupied.)
|