APPROVED DATE: 1/10/2019
|
PERMIT SUB-TYPE: CIFO
|
PERMIT NO: B18-06771
|
JOB ADDRESS: 6770 WINNING DR 900 FRISCO, TX 75034 |
DESC:
11215 SQ FT, CIFO / TROPHY PARK |
|
OWNER:
BLUE STAR FRISCO RETAIL LP
FRISCO TX 75034-1962
|
CONTRACTOR:
GREEN TAG CONSTRUCTION
EXP COI MELISSA TX 75454
|
ISSUED DATE: 1/11/2019
APPLIED DATE:12/12/2018
EXPIRED DATE:9/20/2020
SITE APN:C2712517
STATUS:COMPLETED
|
|
APPLICANT:
COEVAL STUDIO
DALLAS TX 75207
|
LEGAL DESC:
COUNTY:
ZONING:
VALUATION: 800000
|
|
FEE SUMMARY
|
INSPECTION SUMMARY
|
CREDIT CARD FEE | $6.73 |
CREDIT CARD FEE | $1.50 |
HEALTH FINAL 03/17/2020 BLJ | $35.00 |
PLAN REVIEW FEE | $50.00 |
COMMERCIAL BUILDING PERMIT FEE | $2,795.25 |
COMMERCIAL ELECTRIC FEE | $478.60 |
MISCELLANEOUS PLUMBING FEES | $1,039.35 |
MISCELLANOUS MECHANICAL FEES | $590.75 |
PLAN REVIEW FEE | $50.00 |
COMMERCIAL BUILDING PERMIT FEE | $50.00 |
FIRE DEPT INSPECTION FEES | $336.45 |
FIRE DEPT INSPECTION FEES | $75.00 |
FIRE DEPT INSPECTION FEES | $150.00 |
FIRE DEPT INSPECTION FEES | $75.00 |
FIRE DEPT INSPECTION FEES | $50.00 |
CREDIT CARD FEE | $1.00 |
FIRE DEPT INSPECTION FEES | $50.00 |
CEILING 08/05/2019 REED | $35.00 |
ELECTRICAL FINAL 10/10/2019 REED | $35.00 |
BRICKWALL TIE COMM 12/05/2019 REED | $35.00 |
Total Fees: | $5,939.63 |
|
|
| ______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ COMM SLAB |
______ COMM SLAB |
______ COMM PLUMB TOP OUT |
______ COMM DRYWALL |
______ INSULATION RES |
______ FRAME AND ELEC WALL |
______ COMM DRYWALL |
______ MECHANICAL ROUGH |
______ AUTOFIRE SPRK VISUAL |
______ CEILING |
______ CEILING |
______ MECHANICAL ROUGH |
______ ELEC WALL |
______ ELECTRICAL RELEASE |
______ ELECT FINAL RES |
______ GAS PRESSURE |
______ MECHANICAL ROUGH |
______ GAS PRESSURE |
______ MECHANICAL ROUGH |
______ MECHANICAL ROUGH |
______ ELECTRICAL ROUGH IN |
______ FOOTINGS |
______ MECHANICAL ROUGH |
______ CEILING |
______ PLUMBING ROUGH-IN |
______ CEILING |
______ MISC ELECTRIC |
______ MECHANICAL ROUGH |
______ GAS PRESSURE |
______ GAS RELEASE |
______ PLUMBING ROUGH-IN |
______ AUTOFIRE SPRK HYDRO |
______ PLUMBING FINAL |
______ MECHANICAL FINAL |
______ COURTESY HEALTH INSP |
______ PLUMBING FINAL |
______ ELECT FINAL RES |
______ ELECT FINAL COMM |
______ PLUMBING FINAL |
______ HEALTH FINAL |
______ COMM CO |
______ FIRE FINAL |
______ FIRE FINAL |
______ COMM CO |
______ COMM CO |
______ ELECT ROUGH COMM |
______ BRICKWALL TIE COMM |
______ FRAME COMM |
______ BRICKWALL TIE COMM |
______ COMM CO |
______ COMM CO |
______ COMM CO |
______ ELECT FINAL COMM |
______ PLUMB MECH FINAL |
______ HEALTH FINAL |
______ COMM CO |
______ HEALTH FINAL |
______ FIRE FINAL |
______ COMM CO |
|
The project described shall be built in accordance with plans and specifications submitted at time of applications. All provisions of law and ordinances governing this type of work will be complied with whether specified or not. Granting of a permit does not presume to give authority to violate or cancel the provisions of any other local or state law regulating construction or the performance of construction. (The City will not assume responsibility for workability of sanitary sewer on all lots. NOTICE: A Certificate of Occupancy Must be Issued Before Any Building is Occupied.)
|