APPROVED DATE: 7/26/2018
|
PERMIT SUB-TYPE: SNEW
|
PERMIT NO: B18-04164
|
JOB ADDRESS: 2112 BEEBRUSH RD FRISCO, TX |
DESC:
3324 AC 4237 SF, SFR / 1 STORY |
|
OWNER:
MHI PARTNERSHIP LTD
HOUSTON TX 77063-1521
|
CONTRACTOR:
MHI COVENTRY PLANTATION
HOUSTON TX 77063
|
ISSUED DATE: 7/29/2018
APPLIED DATE:7/6/2018
EXPIRED DATE:6/26/2019
SITE APN:D695948
STATUS:COMPLETED
|
|
APPLICANT:
MHI COVENTRY PLANTATION
HOUSTON TX 77063
|
LEGAL DESC:
COUNTY:
ZONING:
VALUATION: 248003.64
|
|
FEE SUMMARY
|
INSPECTION SUMMARY
|
1 INCH PD METER | $410.00 |
WATER METER DEPOSIT | $125.00 |
SHEATHING 10/05/2018 ARG | $30.00 |
SHEATHING 10/09/2018 ARG | $30.00 |
BRICK/WALL TIES 11/16/2018 ARG | $30.00 |
FLATWORK 11/26/2018 ARG | $30.00 |
FLATWORK 11/27/2018 ARG | $30.00 |
ELECTRICAL FINAL 11/30/2018 ARG | $30.00 |
WATER IMPACT FEE | $635.00 |
THOROUGHFARE IMPACT FEE | $0.00 |
SEWER IMPACT FEE | $1,619.00 |
PLUMBTOPOUT/MECHRGH 10/08/2018 DOT | $30.00 |
CREDIT CARD FEE | $90.84 |
CREDIT CARD FEE | $2.40 |
CREDIT CARD FEE | $2.40 |
RESIDENTIAL BUILDING PERMIT FEE | $1,738.75 |
FENCE FEE | $20.00 |
RESIDENTIAL FEE | $127.11 |
MISCELLANEOUS PLUMBING FEES | $256.00 |
MISCELLANOUS MECHANICAL FEES | $146.00 |
2NDS/FRAMING 10/11/2018 TWC | $30.00 |
Total Fees: | $5,412.50 |
|
|
| ______ T-POLE |
______ METER PAYMENT |
______ SET 1 PD METER |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ SLAB |
______ T-POLE |
______ SHEATHING |
______ SHEATHING |
______ PLUMBTOPOUT AND MECHRGH |
______ SHEATHING |
______ PLUMBTOPOUT AND MECHRGH |
______ SHEATHING |
______ 2NDS/FRAMING |
______ 2NDS/FRAMING |
______ 2NDS/FRAMING |
______ INSULATION |
______ DRY WALL |
______ DRY WALL |
______ BRICK/WALL TIES |
______ BRICK/WALL TIES |
______ FLATWORK |
______ FLATWORK |
______ FLATWORK |
______ ELECTRICAL FINAL |
______ GAS RELEASE |
______ ELECTRICAL FINAL |
______ UTILITIES INSPECTION |
______ PLUMBMECHFINAL |
______ PLUMBMECHFINAL |
______ PLUMBMECHFINAL |
______ PLUMBMECHFINAL |
______ CO/BUILDING FINAL |
______ CO/BUILDING FINAL |
|
The project described shall be built in accordance with plans and specifications submitted at time of applications. All provisions of law and ordinances governing this type of work will be complied with whether specified or not. Granting of a permit does not presume to give authority to violate or cancel the provisions of any other local or state law regulating construction or the performance of construction. (The City will not assume responsibility for workability of sanitary sewer on all lots. NOTICE: A Certificate of Occupancy Must be Issued Before Any Building is Occupied.)
|
(THIS IS A BASIC PERMIT VIEW ONLY)
|
|