BUILDING
Permit Payment Receipt
|
CITY OF FRISCO
6101 Frisco Square Blvd, TX 75034
Phone: 972.292.5301
|
APPROVED DATE: 9/7/2017
|
PERMIT SUB-TYPE: SNEW
|
PERMIT NO: B17-08461
|
JOB ADDRESS: 13148 STRIKE GOLD BLVD FRISCO, TX |
DESC:
3677 AC, 4492 SF, SFR / 2 STORY |
|
OWNER:
LANDON HOMES
PLANO TX 75093
|
CONTRACTOR:
LANDON HOMES
PLANO TX 75093
|
ISSUED DATE: 9/7/2017
APPLIED DATE:8/28/2017
EXPIRED DATE:3/6/2023
SITE APN:C2741978
STATUS:COMPLETED
|
|
APPLICANT:
LANDON HOMES
PLANO TX 75093
|
LEGAL DESC:
COUNTY:
ZONING:
VALUATION: 254569.32
|
|
FEE SUMMARY
|
INSPECTION SUMMARY
|
SLAB 12/28/2017 ARG | $30.00 |
UTILITIES INSPECTION 03/23/2018 CB | $80.00 |
FLATWORK RES 08/16/2022 CMM2 | $30.00 |
ELECT ROUGH RES 08/16/2022 CMM2 | $30.00 |
PLAN REVIEW FEE | $50.00 |
BUILDING PERMIT FEE | $1,768.75 |
FENCE FEE | $20.00 |
MISCELLANEOUS PLUMBING FEES | $263.00 |
MISCELLANOUS MECHANICAL FEES | $146.00 |
RESIDENTIAL ELECTRIC FEE | $126.81 |
PLAN REVIEW FEE | $50.00 |
RESIDENTIAL FEE | $7.95 |
RESIDENTIAL BUILDING PERMIT FEE | $321.25 |
WATER IMPACT FEE | $2,441.00 |
SEWER IMPACT FEE | $1,619.00 |
CREDIT CARD FEE | $127.69 |
CREDIT CARD FEE | $7.58 |
CREDIT CARD FEE | $12.80 |
PERCENT CREDIT CARD FEE | $1.00 |
PERCENT CREDIT CARD FEE | $1.20 |
SLAB 09/15/2017 EW | $30.00 |
WATER METER DEPOSIT | $125.00 |
1 INCH PD METER | $410.00 |
REPLACE DAMAGED/UNREADABLE REGISTER | $500.00 |
Total Fees: | $8,199.03 |
|
|
| ______ METER PAYMENT |
______ SET 1 PD METER |
______ T-POLE |
______ PLUMBING ROUGH-IN |
______ SLAB |
______ SLAB |
______ SLAB |
______ SLAB |
______ SLAB |
______ PLUMBTOPOUT AND MECHRGH |
______ 2NDS/FRAMING |
______ 2NDS/FRAMING |
______ INSULATION |
______ INSULATION |
______ INSULATION |
______ BRICK/WALL TIES |
______ DRY WALL |
______ ELECTRICAL FINAL |
______ GAS RELEASE |
______ UTILITIES INSPECTION |
______ WATER REGISTER |
______ UTILITIES INSPECTION |
______ PLUMBMECHFINAL |
______ CO/BUILDING FINAL |
______ FLATWORK RES |
______ FLATWORK RES |
______ ELECT ROUGH RES |
______ FLATWORK RES |
______ ELECT ROUGH RES |
______ PLUMB MECH FINAL |
______ ELECT ROUGH RES |
______ MISC FRAME RES |
______ ELECT FINAL RES |
______ CO AND BUILD FINAL |
|
|
|