BUILDING
PERMIT
Inspections Line: 972.292.5386 cut-off at 4 PM the business day before
OR
Request Inspections online at https:\\etrakit.friscotexas.gov\etrakit until 7:00 AM same day
Contact assigned inspector for cancellation.
|
CITY OF FRISCO
6101 Frisco Square Blvd, TX 75034
Phone: 972.292.5301
|
APPROVED DATE: 6/13/2017
|
PERMIT SUB-TYPE: SNEW
|
PERMIT NO: B17-03961
|
JOB ADDRESS: 11285 MEDALLION LN FRISCO, TX 75035 |
DESC:
4781 AC, 5716 SF, SFR / 2 STORY |
|
OWNER:
SHADDOCK HOMES LTD
PLANO TX 75093
|
CONTRACTOR:
SHADDOCK HOMES LTD
PLANO TX 75093
|
ISSUED DATE: 6/20/2017
APPLIED DATE:5/27/2017
EXPIRED DATE:4/25/2018
SITE APN:C2736769
STATUS:COMPLETED
|
|
APPLICANT:
SHADDOCK HOMES LTD
PLANO TX 75093
|
LEGAL DESC:
COUNTY:
ZONING:
VALUATION: 0
|
|
FEE SUMMARY
|
INSPECTION SUMMARY
|
CREDIT CARD FEE | $2.20 |
CREDIT CARD FEE | $0.60 |
GAS RELEASE 10/09/2017 SDC | $30.00 |
PLUMBMECHFINAL 10/20/2017 SDC | $30.00 |
BRICK/WALL TIES 08/25/2017 WND | $30.00 |
2NDS/FRAMING 08/23/2017 WND | $30.00 |
PLUMBTOPOUT/MECHRGH 08/16/2017 MLM | $30.00 |
PLUMBTOPOUT/MECHRGH 08/14/2017 MLM | $30.00 |
1 INCH PD METER | $410.00 |
WATER METER DEPOSIT | $125.00 |
RESIDENTIAL ELECTRIC FEE | $171.48 |
MISCELLANOUS MECHANICAL FEES | $185.50 |
MISCELLANEOUS PLUMBING FEES | $294.00 |
FENCE FEE | $20.00 |
BUILDING PERMIT FEE | $0.00 |
CREDIT CARD FEE | $1.60 |
UTILITIES INSPECTION 10/11/2017 CB | $80.00 |
CREDIT CARD FEE | $2.40 |
SEWER IMPACT FEE | $1,619.00 |
WATER IMPACT FEE | $1,797.00 |
THOROUGHFARE IMPACT FEE | $3,280.00 |
SET 1 PD METER 06/21/2017 BS | $80.00 |
Total Fees: | $8,248.78 |
|
|
| ______ METER PAYMENT |
______ SET 1 PD METER |
______ T-POLE |
______ SET 1 PD METER |
______ PLUMBING ROUGH-IN |
______ SLAB |
______ CAMERA |
______ PLUMBTOPOUT AND MECHRGH |
______ PLUMBTOPOUT AND MECHRGH |
______ PLUMBTOPOUT AND MECHRGH |
______ 2NDS/FRAMING |
______ 2NDS/FRAMING |
______ 2NDS/FRAMING |
______ BRICK/WALL TIES |
______ BRICK/WALL TIES |
______ INSULATION |
______ DRY WALL |
______ FLATWORK |
______ FLATWORK |
______ LATH |
______ ELECTRICAL FINAL |
______ GAS RELEASE |
______ GAS RELEASE |
______ UTILITIES INSPECTION |
______ GAS RELEASE |
______ UTILITIES INSPECTION |
______ PLUMBMECHFINAL |
______ PLUMBMECHFINAL |
______ PLUMBMECHFINAL |
______ CO/BUILDING FINAL |
______ CO/BUILDING FINAL |
|
The project described shall be built in accordance with plans and specifications submitted at time of applications. All provisions of law and ordinances governing this type of work will be complied with whether specified or not. Granting of a permit does not presume to give authority to violate or cancel the provisions of any other local or state law regulating construction or the performance of construction. (The City will not assume responsibility for workability of sanitary sewer on all lots. NOTICE: A Certificate of Occupancy Must be Issued Before Any Building is Occupied.)
|
(THIS IS A BASIC PERMIT VIEW ONLY)
|
|