BUILDING
PERMIT
Inspections Line: 972.292.5386 cut-off at 4 PM the business day before
OR
Request Inspections online at https:\\etrakit.friscotexas.gov\etrakit until 7:00 AM same day
Contact assigned inspector for cancellation.
|
CITY OF FRISCO
6101 Frisco Square Blvd, TX 75034
Phone: 972.292.5301
|
APPROVED DATE: 8/19/2016
|
PERMIT SUB-TYPE: SNEW
|
PERMIT NO: B16-3716
|
JOB ADDRESS: 1774 CORALBEAD RD FRISCO, TX 75033 |
DESC:
4097 AC, 5075 SF, SFR / 2 STORY |
|
OWNER:
BRITTON HOMES / PERRY HOMES CO
PLANO TX 75034
|
CONTRACTOR:
BRITTON HOMES / PERRY HOMES CO
PLANO TX 75034
|
ISSUED DATE: 8/22/2016
APPLIED DATE:8/15/2016
EXPIRED DATE:3/28/2018
SITE APN:ADD154217
STATUS:COMPLETED
|
|
APPLICANT:
BRITTON HOMES / PERRY HOMES CO
PLANO TX 75034
|
LEGAL DESC:
COUNTY:
ZONING:
VALUATION: 305602.56
|
|
FEE SUMMARY
|
INSPECTION SUMMARY
|
2NDS/FRAMING 05/04/2017 ARG | $30.00 |
INSULATION 05/17/2017 ARG | $30.00 |
UTILITIES INSPECTION 08/21/2017 CB | $80.00 |
WATER IMPACT FEE | $426.00 |
SEWER IMPACT FEE | $1,619.00 |
CREDIT CARD FEE | $10.00 |
CREDIT CARD FEE | $1.60 |
SHEATHING 04/17/2017 EW | $30.00 |
SHEATHING 04/19/2017 EW | $30.00 |
SHEATHING 04/24/2017 EW | $30.00 |
BUILDING PERMIT FEE | $2,023.75 |
FENCE FEE | $20.00 |
MISCELLANEOUS PLUMBING FEES | $291.00 |
MISCELLANOUS MECHANICAL FEES | $159.00 |
RESIDENTIAL ELECTRIC FEE | $152.25 |
LATH 05/24/2017 JDR | $30.00 |
WATER METER DEPOSIT | $100.00 |
1 INCH PD METER | $410.00 |
REPLACE DAMAGED/UNREADABLE REGISTER | $500.00 |
Total Fees: | $5,972.60 |
|
|
| ______ METER PAYMENT |
______ SET 1 PD METER |
______ T-POLE |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ SLAB |
______ CAMERA |
______ PLUMBTOPOUT AND MECHRGH |
______ PLUMBTOPOUT AND MECHRGH |
______ SHEATHING |
______ SHEATHING |
______ SHEATHING |
______ SHEATHING |
______ 2NDS/FRAMING |
______ 2NDS/FRAMING |
______ INSULATION |
______ INSULATION |
______ LATH |
______ DRY WALL |
______ LATH |
______ BRICK/WALL TIES |
______ DRY WALL |
______ FLATWORK |
______ FLATWORK |
______ FLATWORK |
______ GAS RELEASE |
______ ELECTRICAL FINAL |
______ ELECTRICAL FINAL |
______ GAS RELEASE |
______ GAS RELEASE |
______ ELECTRICAL FINAL |
______ GAS RELEASE |
______ GAS RELEASE |
______ GAS RELEASE |
______ MECHANICAL FINAL |
______ SWROWINSP |
______ UTILITIES INSPECTION |
______ WATER REGISTER |
______ MECHANICAL FINAL |
______ UTILITIES INSPECTION |
______ PLUMBMECHFINAL |
______ CO/BUILDING FINAL |
______ CO/BUILDING FINAL |
______ CO/BUILDING FINAL |
|
The project described shall be built in accordance with plans and specifications submitted at time of applications. All provisions of law and ordinances governing this type of work will be complied with whether specified or not. Granting of a permit does not presume to give authority to violate or cancel the provisions of any other local or state law regulating construction or the performance of construction. (The City will not assume responsibility for workability of sanitary sewer on all lots. NOTICE: A Certificate of Occupancy Must be Issued Before Any Building is Occupied.)
|