APPROVED DATE: 7/11/2016
|
PERMIT SUB-TYPE: SNEW
|
PERMIT NO: B16-3077
|
JOB ADDRESS: 2156 ALCOVE DR FRISCO, TX |
DESC:
4729 AC, 5209 SF, SFR / 2 STORY |
|
OWNER:
GRAND HOMES
ADDISON TX 75001
|
CONTRACTOR:
GRAND HOMES
ADDISON TX 75001
|
ISSUED DATE: 7/20/2016
APPLIED DATE:7/1/2016
EXPIRED DATE:10/25/2017
SITE APN:D677559
STATUS:COMPLETED
|
|
APPLICANT:
GRAND HOMES
ADDISON TX 75001
|
LEGAL DESC:
COUNTY:
ZONING:
VALUATION: 352830.69
|
|
FEE SUMMARY
|
INSPECTION SUMMARY
|
UTILITY / ROW 02/28/2017 KB | $80.00 |
2NDS/FRAMING 10/27/2016 CCM | $30.00 |
2NDS/FRAMING 10/28/2016 CCM | $30.00 |
THOROUGHFARE IMPACT FEE | $0.00 |
WATER IMPACT FEE | $0.00 |
SEWER IMPACT FEE | $1,619.00 |
BUILDING PERMIT FEE | $2,258.75 |
FENCE FEE | $20.00 |
MISCELLANEOUS ELECTRICAL FEES | $156.00 |
MISCELLANEOUS PLUMBING FEES | $256.00 |
MISCELLANOUS MECHANICAL FEES | $158.00 |
DRY WALL 11/15/2016 JWF | $30.00 |
DRY WALL 11/16/2016 JWF | $30.00 |
WATER METER DEPOSIT | $100.00 |
1 INCH PD METER | $410.00 |
REPLACE READABLE REGISTER | $270.00 |
GAS RELEASE 01/18/2017 SDC | $30.00 |
GAS RELEASE 01/20/2017 SDC | $30.00 |
GAS RELEASE 01/24/2017 SDC | $30.00 |
INSULATION 11/02/2016 TXT | $30.00 |
INSULATION 11/03/2016 TXT | $30.00 |
Total Fees: | $5,597.75 |
|
|
| ______ METER PAYMENT |
______ T-POLE |
______ SET 1 PD METER |
______ PLUMBING ROUGH-IN |
______ SLAB |
______ CAMERA |
______ PLUMBTOPOUT AND MECHRGH |
______ PLUMBTOPOUT AND MECHRGH |
______ 2NDS/FRAMING |
______ ELECTRICAL ROUGH IN |
______ 2NDS/FRAMING |
______ 2NDS/FRAMING |
______ INSULATION |
______ INSULATION |
______ INSULATION |
______ DRY WALL |
______ DRY WALL |
______ DRY WALL |
______ BRICK/WALL TIES |
______ LATH |
______ GAS RELEASE |
______ ELECTRICAL FINAL |
______ FLATWORK |
______ ELECTRICAL FINAL |
______ GAS RELEASE |
______ ELECTRICAL FINAL |
______ GAS RELEASE |
______ GAS RELEASE |
______ GAS RELEASE |
______ UTILITY / ROW |
______ WATER REGISTER |
______ UTILITY / ROW |
______ PLUMBMECHFINAL |
______ PLUMBMECHFINAL |
______ PLUMBMECHFINAL |
______ PLUMBMECHFINAL |
______ 2NDS/FRAMING |
______ CO/BUILDING FINAL |
______ CO/BUILDING FINAL |
______ CO/BUILDING FINAL |
______ CO/BUILDING FINAL |
|
The project described shall be built in accordance with plans and specifications submitted at time of applications. All provisions of law and ordinances governing this type of work will be complied with whether specified or not. Granting of a permit does not presume to give authority to violate or cancel the provisions of any other local or state law regulating construction or the performance of construction. (The City will not assume responsibility for workability of sanitary sewer on all lots. NOTICE: A Certificate of Occupancy Must be Issued Before Any Building is Occupied.)
|
(THIS IS A BASIC PERMIT VIEW ONLY)
|
|