BUILDING
PERMIT
Inspections Line: 972.292.5386 cut-off at 4 PM the business day before
OR
Request Inspections online at https:\\etrakit.friscotexas.gov\etrakit until 7:00 AM same day
Contact assigned inspector for cancellation.
|
CITY OF FRISCO
6101 Frisco Square Blvd, TX 75034
Phone: 972.292.5301
|
APPROVED DATE: 6/6/2016
|
PERMIT SUB-TYPE: SNEW
|
PERMIT NO: B16-2249
|
JOB ADDRESS: 1722 TUMBLEGRASS RD FRISCO, TX |
DESC:
3449 AC, 4639 SF, SFR / 2 STORY |
|
OWNER:
WEEKLEY HOMES CORPORATE OFFICE
1111 N Post Oak Road CARROLLTON TX 75007
|
CONTRACTOR:
WEEKLEY HOMES CORPORATE OFFICE
1111 N Post Oak Road CARROLLTON TX 75007
|
ISSUED DATE: 6/13/2016
APPLIED DATE:5/9/2016
EXPIRED DATE:8/26/2017
SITE APN:D681941
STATUS:COMPLETED
|
|
APPLICANT:
WEEKLEY HOMES CORPORATE OFFICE
1111 N Post Oak Road CARROLLTON TX 75007
|
LEGAL DESC:
COUNTY:
ZONING:
VALUATION: 257329.89
|
|
FEE SUMMARY
|
INSPECTION SUMMARY
|
CREDIT CARD FEE | $87.66 |
CREDIT CARD FEE | $1.80 |
CREDIT CARD FEE | $2.40 |
CREDIT CARD FEE | $10.00 |
BUILDING PERMIT FEE | $1,783.75 |
FENCE FEE | $20.00 |
MISCELLANEOUS PLUMBING FEES | $249.00 |
MISCELLANOUS MECHANICAL FEES | $146.00 |
RESIDENTIAL ELECTRIC FEE | $139.17 |
SHEATHING 09/26/2016 JDR | $30.00 |
SHEATHING 10/03/2016 JDR | $30.00 |
SHEATHING 10/07/2016 JDR | $30.00 |
2NDS/FRAMING 10/07/2016 JDR | $30.00 |
INSULATION 10/17/2016 JDR | $30.00 |
DRY WALL 10/24/2016 JDR | $30.00 |
WATER METER DEPOSIT | $100.00 |
1 INCH PD METER | $410.00 |
CREDIT CARD FEE | $10.20 |
REPLACE DAMAGED/UNREADABLE REGISTER | $500.00 |
PLUMBTOPOUT/MECHRGH 09/26/2016 PJ | $30.00 |
WATER IMPACT FEE | $426.00 |
SEWER IMPACT FEE | $1,619.00 |
THOROUGHFARE IMPACT FEE | $0.00 |
Total Fees: | $5,714.98 |
|
|
| ______ METER PAYMENT |
______ SET 1 PD METER |
______ PLUMBING ROUGH-IN |
______ T-POLE |
______ PLUMBING ROUGH-IN |
______ SLAB |
______ SLAB |
______ CAMERA |
______ PLUMBTOPOUT AND MECHRGH |
______ SHEATHING |
______ PLUMBTOPOUT AND MECHRGH |
______ SHEATHING |
______ PLUMBTOPOUT AND MECHRGH |
______ 2NDS/FRAMING |
______ 2NDS/FRAMING |
______ SHEATHING |
______ 2NDS/FRAMING |
______ SHEATHING |
______ INSULATION |
______ INSULATION |
______ INSULATION |
______ DRY WALL |
______ DRY WALL |
______ BRICK/WALL TIES |
______ DRY WALL |
______ ELECTRICAL FINAL |
______ GAS RELEASE |
______ FLATWORK |
______ PLUMBMECHFINAL |
______ UTILITY / ROW |
______ WATER REGISTER |
______ CO/BUILDING FINAL |
______ CO/BUILDING FINAL |
______ CO/BUILDING FINAL |
|
The project described shall be built in accordance with plans and specifications submitted at time of applications. All provisions of law and ordinances governing this type of work will be complied with whether specified or not. Granting of a permit does not presume to give authority to violate or cancel the provisions of any other local or state law regulating construction or the performance of construction. (The City will not assume responsibility for workability of sanitary sewer on all lots. NOTICE: A Certificate of Occupancy Must be Issued Before Any Building is Occupied.)
|
(THIS IS A BASIC PERMIT VIEW ONLY)
|
|