BUILDING
PERMIT
Inspections Line: 972.292.5386 cut-off at 4 PM the business day before
OR
Request Inspections online at https:\\etrakit.friscotexas.gov\etrakit until 7:00 AM same day
Contact assigned inspector for cancellation.
|
CITY OF FRISCO
6101 Frisco Square Blvd, TX 75034
Phone: 972.292.5301
|
APPROVED DATE: 5/11/2016
|
PERMIT SUB-TYPE: CIFO
|
PERMIT NO: B16-1410
|
JOB ADDRESS: 8075 FM 423 120 FRISCO, TX 75034 |
DESC:
1357 SQ FT, CIFO / DICKEYS BARBEQUE PIT |
|
OWNER:
423 HINDS LP
DALLAS TX 75205
|
CONTRACTOR:
J & K PROJECT MANAGEMENT CONSULTANTS
LEWISVILLE TX 75057
|
ISSUED DATE: 9/14/2016
APPLIED DATE:3/29/2016
EXPIRED DATE:5/6/2018
SITE APN:D634483
STATUS:COMPLETED
|
|
APPLICANT:
FM GROUP INC
SCOTTSDALE AZ 85260
|
LEGAL DESC:
COUNTY:
ZONING:
VALUATION: 200000
|
|
FEE SUMMARY
|
INSPECTION SUMMARY
|
CREDIT CARD FEE | $4.00 |
CREDIT CARD FEE | $0.70 |
COMM PLUMB TOP OUT 10/13/2016 MLM | $35.00 |
FIRE DEPT INSPECTION FEES | $75.00 |
PLUMBING ROUGH-IN 10/06/2016 ZH | $35.00 |
FIRE DEPT INSPECTION FEES | $200.00 |
CREDIT CARD FEE | $2.10 |
MISCELLANOUS MECHANICAL FEES | $97.85 |
MISCELLANEOUS PLUMBING FEES | $152.13 |
COMMERCIAL ELECTRIC FEE | $84.28 |
COMMERCIAL BUILDING PERMIT FEE | $896.25 |
FIRE DEPT INSPECTION FEES | $50.00 |
CEILING 10/31/2016 CW | $35.00 |
HEALTH FINAL 11/04/2016 BLJ | $35.00 |
Total Fees: | $1,702.31 |
|
|
| ______ FRAME/ELEC WALL |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ FRAME/ELEC WALL |
______ COMM SLAB |
______ MISCFRAME |
______ PLUMBING ROUGH-IN |
______ INSULATION |
______ COMM SLAB |
______ T-POLE |
______ ELECTRICAL ROUGH IN |
______ COMM FRAME |
______ ELECTRICAL RELEASE |
______ COMM PLUMB TOP OUT |
______ ELECTRICAL ROUGH IN |
______ COMM FRAME |
______ COMM PLUMB TOP OUT |
______ INSULATION |
______ COMM DRYWALL |
______ MECHANICAL ROUGH |
______ MECHANICAL ROUGH |
______ MECHANICAL ROUGH |
______ CEILING |
______ ELECTRICAL RELEASE |
______ CEILING |
______ ELECTRICAL RELEASE |
______ GAS PRESSURE |
______ GAS RELEASE |
______ GAS RELEASE |
______ CEILING |
______ AUTOFIRE SPRK VISUAL |
______ CEILING |
______ MECHANICAL FINAL |
______ PLUMBING FINAL |
______ HEALTH FINAL |
______ ELECTRICAL FINAL |
______ HEALTH FINAL |
______ ELECTRICAL FINAL |
______ FIRE FINAL |
______ COMM CO |
______ FIRE FINAL |
|
The project described shall be built in accordance with plans and specifications submitted at time of applications. All provisions of law and ordinances governing this type of work will be complied with whether specified or not. Granting of a permit does not presume to give authority to violate or cancel the provisions of any other local or state law regulating construction or the performance of construction. (The City will not assume responsibility for workability of sanitary sewer on all lots. NOTICE: A Certificate of Occupancy Must be Issued Before Any Building is Occupied.)
|
(THIS IS A BASIC PERMIT VIEW ONLY)
|
|