BUILDING
Permit Payment Receipt
|
CITY OF FRISCO
6101 Frisco Square Blvd, TX 75034
Phone: 972.292.5301
|
APPROVED DATE: 3/14/2016
|
PERMIT SUB-TYPE: SNEW
|
PERMIT NO: B16-0960
|
JOB ADDRESS: 2287 COURTLAND DR FRISCO, TX 75034 |
DESC:
4815 AC, 6043 SF, SFR / 2 STORY |
|
OWNER:
DESTINY VENTURES INC
FRISCO TX 75034
|
CONTRACTOR:
DESTINY VENTURES INC
FRISCO TX 75034
|
ISSUED DATE: 3/30/2016
APPLIED DATE:2/24/2016
EXPIRED DATE:4/2/2019
SITE APN:D611727
STATUS:COMPLETED
|
|
APPLICANT:
DESTINY VENTURES INC
FRISCO TX 75034
|
LEGAL DESC:
COUNTY:
ZONING:
VALUATION: 359247.15
|
|
FEE SUMMARY
|
INSPECTION SUMMARY
|
PLUMBING ROUGH-IN 06/10/2016 CK | $30.00 |
CREDIT CARD FEE | $5.60 |
BUILDING PERMIT FEE | $2,293.75 |
FENCE FEE | $20.00 |
MISCELLANEOUS PLUMBING FEES | $308.00 |
MISCELLANOUS MECHANICAL FEES | $159.00 |
RESIDENTIAL ELECTRIC FEE | $181.26 |
PLAN REVIEW FEE | $50.00 |
BRICK/WALL TIES 04/18/2017 DE | $30.00 |
GAS RELEASE 08/23/2017 JWF | $30.00 |
CREDIT CARD FEE | $2.40 |
THOROUGHFARE IMPACT FEE | $0.00 |
WATER IMPACT FEE | $0.00 |
SEWER IMPACT FEE | $1,619.00 |
WATER METER DEPOSIT | $100.00 |
1 INCH PD METER | $410.00 |
CREDIT CARD FEE | $10.00 |
CREDIT CARD FEE | $1.00 |
PLUMBMECHFINAL 09/10/2018 MLM | $30.00 |
PLUMBMECHFINAL 09/17/2018 MLM | $30.00 |
UTILITIES INSPECTION 08/13/2018 NMN | $80.00 |
UTILITIES INSPECTION 09/06/2018 NMN | $80.00 |
PLUMBING ROUGH-IN 06/15/2016 PJ | $30.00 |
2NDS/FRAMING 01/11/2017 TXT | $30.00 |
ELECTRICAL FINAL 08/23/2017 WND | $30.00 |
Total Fees: | $5,560.01 |
|
|
| ______ T-POLE |
______ T-POLE |
______ METER PAYMENT |
______ SET 1 PD METER |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ SLAB |
______ CAMERA |
______ PLUMBTOPOUT AND MECHRGH |
______ PLUMBTOPOUT AND MECHRGH |
______ ELECTRICAL ROUGH IN |
______ 2NDS/FRAMING |
______ FRAME |
______ INSULATION |
______ DRY WALL |
______ BRICK/WALL TIES |
______ BRICK |
______ T-POLE |
______ T-POLE |
______ FLATWORK |
______ GAS RELEASE |
______ ELECTRICAL FINAL |
______ GAS RELEASE |
______ ELECTRICAL FINAL |
______ UTILITIES INSPECTION |
______ PLUMBMECHFINAL |
______ UTILITIES INSPECTION |
______ PLUMBMECHFINAL |
______ PLUMBMECHFINAL |
______ PLUMBMECHFINAL |
______ PLUMBMECHFINAL |
______ UTILITIES INSPECTION |
______ CO/BUILDING FINAL |
______ CO/BUILDING FINAL |
|
|
|