|
BUILDING
PERMIT
Inspections Line: 972.292.5386 cut-off at 4 PM the business day before
OR
Request Inspections online at https:\\etrakit.friscotexas.gov\etrakit until 7:00 AM same day
Contact assigned inspector for cancellation.
|
CITY OF FRISCO
6101 Frisco Square Blvd, TX 75034
Phone: 972.292.5301
|
APPROVED DATE: 1/4/2017
|
PERMIT SUB-TYPE: SNEW
|
PERMIT NO: B16-05310
|
JOB ADDRESS: 1845 PEPPERVINE RD FRISCO, TX |
DESC:
4160 AC, 5099 SF, SFR / 2 STORY |
|
OWNER:
MHI COVENTRY PLANTATION
HOUSTON TX 77063
|
CONTRACTOR:
MHI COVENTRY PLANTATION
HOUSTON TX 77063
|
ISSUED DATE: 1/5/2017
APPLIED DATE:11/14/2016
EXPIRED DATE:1/15/2018
SITE APN:D681856
STATUS:COMPLETED
|
|
APPLICANT:
MHI COVENTRY PLANTATION
HOUSTON TX 77063
|
LEGAL DESC:
COUNTY:
ZONING:
VALUATION: 310377.6
|
|
FEE SUMMARY
|
INSPECTION SUMMARY
|
SET 1 PD METER 01/12/2017 DAX | $80.00 |
2NDS/FRAMING 04/06/2017 CCM | $30.00 |
WATER IMPACT FEE | $426.00 |
SEWER IMPACT FEE | $1,619.00 |
CREDIT CARD FEE | $94.92 |
CREDIT CARD FEE | $2.20 |
CREDIT CARD FEE | $1.20 |
SHEATHING 03/03/2017 EW | $30.00 |
PLAN REVIEW FEE | $50.00 |
BUILDING PERMIT FEE | $2,048.75 |
FENCE FEE | $20.00 |
MISCELLANEOUS PLUMBING FEES | $277.00 |
MISCELLANOUS MECHANICAL FEES | $152.50 |
RESIDENTIAL ELECTRIC FEE | $152.97 |
PLAN REVIEW FEE | $50.00 |
WATER METER DEPOSIT | $100.00 |
1 INCH PD METER | $410.00 |
PLUMBTOPOUT/MECHRGH 03/28/2017 MLM | $30.00 |
Total Fees: | $5,574.54 |
|
|
| ______ METER PAYMENT |
______ T-POLE |
______ SET 1 PD METER |
______ SET 1 PD METER |
______ PLUMBING ROUGH-IN |
______ FLATWORK |
______ FLATWORK |
______ SLAB |
______ CAMERA |
______ SHEATHING |
______ SHEATHING |
______ SHEATHING |
______ PLUMBTOPOUT AND MECHRGH |
______ LATH |
______ PLUMBTOPOUT AND MECHRGH |
______ PLUMBTOPOUT AND MECHRGH |
______ PLUMBTOPOUT AND MECHRGH |
______ ELECTRICAL ROUGH IN |
______ 2NDS/FRAMING |
______ 2NDS/FRAMING |
______ BRICK/WALL TIES |
______ INSULATION |
______ DRY WALL |
______ GAS RELEASE |
______ ELECTRICAL FINAL |
______ ELECTRICAL FINAL |
______ UTILITY / ROW |
______ PLUMBMECHFINAL |
______ CO/BUILDING FINAL |
______ CO/BUILDING FINAL |
______ CO/BUILDING FINAL |
|
The project described shall be built in accordance with plans and specifications submitted at time of applications. All provisions of law and ordinances governing this type of work will be complied with whether specified or not. Granting of a permit does not presume to give authority to violate or cancel the provisions of any other local or state law regulating construction or the performance of construction. (The City will not assume responsibility for workability of sanitary sewer on all lots. NOTICE: A Certificate of Occupancy Must be Issued Before Any Building is Occupied.)
|
(THIS IS A BASIC PERMIT VIEW ONLY)
|
|