BUILDING
Permit Payment Receipt
|
CITY OF FRISCO
6101 Frisco Square Blvd, TX 75034
Phone: 972.292.5301
|
|
APPROVED DATE: 8/15/2015
|
PERMIT SUB-TYPE: SNEW
|
PERMIT NO: B15-3397
|
| JOB ADDRESS: 2353 LILAC LN FRISCO, TX 75034 |
DESC:
6933 AC, 9782 SF, SFR / 2 STORY |
|
OWNER:
PREMIER RENOVATIONS INC
DALLAS TX 75252
|
CONTRACTOR:
PREMIER RENOVATIONS INC
DALLAS TX 75252
|
|
ISSUED DATE: 8/21/2015
APPLIED DATE:7/24/2015
EXPIRED DATE:7/29/2018
SITE APN:D611677
STATUS:COMPLETED
|
|
APPLICANT:
PREMIER RENOVATIONS INC
DALLAS TX 75252
| |
LEGAL DESC:
COUNTY:
ZONING:
VALUATION: 517271.13
|
|
|
FEE SUMMARY
|
INSPECTION SUMMARY
|
| UTILITIES INSPECTION 10/18/2017 CB | $80.00 |
| RESIDENTIAL ELECTRIC FEE | $293.46 |
| MISCELLANOUS MECHANICAL FEES | $205.00 |
| MISCELLANEOUS PLUMBING FEES | $357.00 |
| BUILDING PERMIT FEE | $3,319.25 |
| FENCE FEE | $20.00 |
| CREDIT CARD FEE | $0.60 |
| CREDIT CARD FEE | $0.60 |
| CREDIT CARD FEE | $1.80 |
| CREDIT CARD FEE | $0.60 |
| CREDIT CARD FEE | $0.60 |
| CREDIT CARD FEE | $0.60 |
| CREDIT CARD FEE | $1.60 |
| 2NDS/FRAMING 07/01/2016 GLQ | $30.00 |
| SHEATHING 02/12/2016 JDR | $30.00 |
| ELECTRICAL FINAL 06/02/2017 JDR | $30.00 |
| ELECTRICAL FINAL 06/05/2017 JDR | $30.00 |
| GAS RELEASE 07/10/2017 JWF | $30.00 |
| 1 INCH PD METER | $400.00 |
| WATER METER DEPOSIT | $100.00 |
| FIRE DEPT INSPECTION FEES | $293.46 |
| PLUMBTOPOUT/MECHRGH 06/20/2016 PJ | $30.00 |
| PLUMBTOPOUT/MECHRGH 06/29/2016 PJ | $30.00 |
| THOROUGHFARE IMPACT FEE | $0.00 |
| WATER IMPACT FEE | $0.00 |
| SEWER IMPACT FEE | $1,619.00 |
| PLUMBTOPOUT/MECHRGH 06/24/2016 ZH | $30.00 |
| Total Fees: | $6,933.57 |
|
|
|
| | ______ T-POLE |
| ______ T-POLE |
| ______ PIER |
| ______ METER PAYMENT |
| ______ SET 1 PD METER |
| ______ PLUMBING ROUGH-IN |
| ______ PLUMBING ROUGH-IN |
| ______ SLAB |
| ______ CAMERA |
| ______ CAMERA |
| ______ SHEATHING |
| ______ SHEATHING |
| ______ AUTOFIRE SPRK HYDRO |
| ______ PLUMBTOPOUT AND MECHRGH |
| ______ PLUMBTOPOUT AND MECHRGH |
| ______ PLUMBTOPOUT AND MECHRGH |
| ______ PLUMBTOPOUT AND MECHRGH |
| ______ PLUMBTOPOUT AND MECHRGH |
| ______ 2NDS/FRAMING |
| ______ 2NDS/FRAMING |
| ______ LATH |
| ______ INSULATION |
| ______ LATH |
| ______ DRY WALL |
| ______ BRICK/WALL TIES |
| ______ ELECTRICAL FINAL |
| ______ ELECTRICAL FINAL |
| ______ ELECTRICAL FINAL |
| ______ ELECTRICAL FINAL |
| ______ GAS RELEASE |
| ______ GAS RELEASE |
| ______ GAS RELEASE |
| ______ FLATWORK |
| ______ SWROWINSP |
| ______ UTILITIES INSPECTION |
| ______ PLUMBMECHFINAL |
| ______ UTILITIES INSPECTION |
| ______ PLUMBMECHFINAL |
| ______ CO/BUILDING FINAL |
| ______ CO/BUILDING FINAL |
| ______ CO/BUILDING FINAL |
|
|
|
|