APPROVED DATE: 7/6/2015 PERMIT SUB-TYPE: SNEW PERMIT NO: B15-2483
JOB ADDRESS:
3920 NEWMAN BLVD
FRISCO, TX 75033
DESC:   5878 AC, 8165 SF, SFR / 2 STORY
OWNER:
PENNETT, BARRY & HOLLY

FRISCO TX 75033

CONTRACTOR:
PREMIER RENOVATIONS INC

DALLAS TX 75252
ISSUED DATE:
7/7/2015
APPLIED DATE:
6/4/2015
EXPIRED DATE:
8/1/2017
SITE APN:
D613184
STATUS:
COMPLETED
APPLICANT:
PREMIER RENOVATIONS INC

DALLAS TX 75252
LEGAL DESC:
COUNTY:
ZONING:
VALUATION:
438557.58
FEE SUMMARY
INSPECTION SUMMARY
PLUMBTOPOUT/MECHRGH 02/25/2016 CK$30.00
THOROUGHFARE IMPACT FEE$3,971.00
WATER IMPACT FEE$2,106.00
SEWER IMPACT FEE$1,712.00
REPLACEMENT CARD FEE$10.00
CREDIT CARD FEE$1.80
CREDIT CARD FEE$1.20
CREDIT CARD FEE$0.60
RESIDENTIAL ELECTRIC FEE$244.95
MISCELLANOUS MECHANICAL FEES$185.50
MISCELLANEOUS PLUMBING FEES$308.00
BUILDING PERMIT FEE$2,688.75
FENCE FEE$20.00
T-POLE 07/10/2015 JCF$30.00
PIER 07/16/2015 JCF$30.00
ELECTRICAL FINAL 10/10/2016 JDR$30.00
WATER METER DEPOSIT$100.00
1 INCH PD METER$400.00
1.5 INCH PD METER$185.00
FIRE DEPT INSPECTION FEES$244.95
2NDS/FRAMING 03/22/2016 REED$30.00
SLAB 09/14/2015 RRW$30.00
Total Fees:$12,359.75
______  PIER
______  T-POLE
______  PIER
______  T-POLE
______  METER PAYMENT
______  PIER
______  PIER
______  SET 1 PD METER
______  PLUMBING ROUGH-IN
______  SLAB
______  CAMERA
______  SLAB
______  SLAB
______  CAMERA
______  SLAB
______  PLUMBTOPOUT AND MECHRGH
______  PLUMBTOPOUT AND MECHRGH
______  2NDS/FRAMING
______  2NDS/FRAMING
______  SHEATHING
______  INSULATION
______  AUTOFIRE SPRK HYDRO
______  DRY WALL
______  LATH
______  ELECTRICAL FINAL
______  ELECTRICAL FINAL
______  ELECTRICAL FINAL
______  GAS RELEASE
______  FLATWORK
______  FLATWORK
______  UTILITY / ROW
______  PLUMBMECHFINAL
______  CO/BUILDING FINAL
______  CO/BUILDING FINAL
The project described shall be built in accordance with plans and specifications submitted at time of applications. All provisions of law and ordinances governing this type of work will be complied with whether specified or not. Granting of a permit does not presume to give authority to violate or cancel the provisions of any other local or state law regulating construction or the performance of construction. (The City will not assume responsibility for workability of sanitary sewer on all lots. NOTICE: A Certificate of Occupancy Must be Issued Before Any Building is Occupied.)

(THIS IS A BASIC PERMIT VIEW ONLY)