APPROVED DATE: 1/22/2015
|
PERMIT SUB-TYPE: SNEW
|
PERMIT NO: B14-9699
|
JOB ADDRESS: 14026 PATERNO DR FRISCO, TX 75035 |
DESC:
4081 AC, 4843 SF, SFR / 2 STORY |
|
OWNER:
FIRST TEXAS CUSTOM HOMES
DALLAS TX 75201
|
CONTRACTOR:
FIRST TEXAS CUSTOM HOMES
DALLAS TX 75201
|
ISSUED DATE: 1/23/2015
APPLIED DATE:12/22/2014
EXPIRED DATE:2/3/2016
SITE APN:C2650152
STATUS:COMPLETED
|
|
APPLICANT:
FIRST TEXAS CUSTOM HOMES
DALLAS TX 75201
|
LEGAL DESC:
COUNTY:
ZONING:
VALUATION: 304483.41
|
|
FEE SUMMARY
|
INSPECTION SUMMARY
|
RESIDENTIAL ELECTRIC FEE | $145.29 |
MISCELLANOUS MECHANICAL FEES | $146.00 |
MISCELLANEOUS PLUMBING FEES | $256.00 |
BUILDING PERMIT FEE | $2,018.75 |
FENCE FEE | $20.00 |
2NDS/FRAMING 04/06/2015 CW | $30.00 |
CREDIT CARD FEE | $1.20 |
CREDIT CARD FEE | $1.20 |
WATER METER DEPOSIT | $100.00 |
1 INCH PD METER | $400.00 |
FLATWORK 06/19/2015 JCF | $30.00 |
ELECTRICAL FINAL 06/19/2015 JCF | $30.00 |
PLUMBMECHFINAL 08/03/2015 MLM | $30.00 |
PLUMBMECHFINAL 08/04/2015 MLM | $30.00 |
INSULATION 04/14/2015 REED | $30.00 |
THOROUGHFARE IMPACT FEE | $4,001.00 |
WATER IMPACT FEE | $1,911.00 |
SEWER IMPACT FEE | $1,553.00 |
Total Fees: | $10,733.44 |
|
|
| ______ METER PAYMENT |
______ SET 1 PD METER |
______ T-POLE |
______ PLUMBING ROUGH-IN |
______ SLAB |
______ CAMERA |
______ ELECTRICAL ROUGH IN |
______ PLUMBTOPOUT AND MECHRGH |
______ 2NDS/FRAMING |
______ 2NDS/FRAMING |
______ INSULATION |
______ INSULATION |
______ DRY WALL |
______ BRICK/WALL TIES |
______ GAS RELEASE |
______ ELECTRICAL FINAL |
______ FLATWORK |
______ ELECTRICAL FINAL |
______ FLATWORK |
______ FLATWORK |
______ FLATWORK |
______ UTILITY / ROW |
______ PLUMBMECHFINAL |
______ PLUMBMECHFINAL |
______ PLUMBMECHFINAL |
______ PLUMBMECHFINAL |
______ CO/BUILDING FINAL |
______ CO/BUILDING FINAL |
|
The project described shall be built in accordance with plans and specifications submitted at time of applications. All provisions of law and ordinances governing this type of work will be complied with whether specified or not. Granting of a permit does not presume to give authority to violate or cancel the provisions of any other local or state law regulating construction or the performance of construction. (The City will not assume responsibility for workability of sanitary sewer on all lots. NOTICE: A Certificate of Occupancy Must be Issued Before Any Building is Occupied.)
|