BUILDING
PERMIT
Inspections Line: 972.292.5386 cut-off at 4 PM the business day before
OR
Request Inspections online at https:\\etrakit.friscotexas.gov\etrakit until 7:00 AM same day
Contact assigned inspector for cancellation.
|
CITY OF FRISCO
6101 Frisco Square Blvd, TX 75034
Phone: 972.292.5301
|
APPROVED DATE: 1/10/2015
|
PERMIT SUB-TYPE: SNEW
|
PERMIT NO: B14-9658
|
JOB ADDRESS: 12272 LENOX LN FRISCO, TX 75033 |
DESC:
* KEY LOT * 8306 AC, 10867 SF, SFR / 2 STORY |
|
OWNER:
REYNOLDS SIGNATURE HOMES
PO BOX 2131 FRISCO TX 75034
|
CONTRACTOR:
REYNOLDS SIGNATURE HOMES
PO BOX 2131 FRISCO TX 75034
|
ISSUED DATE: 6/12/2015
APPLIED DATE:12/16/2014
EXPIRED DATE:2/20/2017
SITE APN:D613217
STATUS:COMPLETED
|
|
APPLICANT:
REYNOLDS SIGNATURE HOMES
PO BOX 2131 FRISCO TX 75034
|
LEGAL DESC:
COUNTY:
ZONING:
VALUATION: 619710.66
|
|
FEE SUMMARY
|
INSPECTION SUMMARY
|
SET 1 1/2 PD METER 06/19/2015 PXF | $80.00 |
PLUMBING ROUGH-IN 08/11/2015 CI | $30.00 |
PLUMBTOPOUT/MECHRGH 01/11/2016 CK | $30.00 |
CREDIT CARD FEE | $2.20 |
CREDIT CARD FEE | $1.80 |
CREDIT CARD FEE | $1.80 |
CREDIT CARD FEE | $1.80 |
RESIDENTIAL ELECTRIC FEE | $326.01 |
MISCELLANOUS MECHANICAL FEES | $231.50 |
MISCELLANEOUS PLUMBING FEES | $387.00 |
PLAN REVIEW FEE | $50.00 |
BUILDING PERMIT FEE | $3,803.75 |
FENCE FEE | $20.00 |
SLAB 09/18/2015 JLM | $30.00 |
THOROUGHFARE IMPACT FEE | $3,971.00 |
WATER IMPACT FEE | $2,106.00 |
SEWER IMPACT FEE | $1,712.00 |
WATER METER DEPOSIT | $100.00 |
1.5 INCH PD METER | $585.00 |
FIRE DEPT INSPECTION FEES | $326.01 |
SLAB 09/17/2015 RRW | $30.00 |
SLAB 09/21/2015 RRW | $30.00 |
GAS RELEASE 06/10/2016 SDC | $30.00 |
ELECTRICAL ROUGH IN 01/11/2016 TGC | $30.00 |
ELECTRICAL FINAL 06/20/2016 WBH | $30.00 |
ELECTRICAL FINAL 06/21/2016 WBH | $30.00 |
PLUMBMECHFINAL 07/26/2016 ZH | $30.00 |
Total Fees: | $14,005.87 |
|
|
| ______ METER PAYMENT |
______ SET 1 1/2 PD METER |
______ SET 1 1/2 PD METER |
______ T-POLE |
______ PIER |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ SLAB |
______ SLAB |
______ SLAB |
______ SLAB |
______ CAMERA |
______ AUTOFIRE SPRK HYDRO |
______ ELECTRICAL ROUGH IN |
______ PLUMBTOPOUT AND MECHRGH |
______ PLUMBTOPOUT AND MECHRGH |
______ ELECTRICAL ROUGH IN |
______ PLUMBTOPOUT AND MECHRGH |
______ SHEATHING |
______ 2NDS/FRAMING |
______ 2NDS/FRAMING |
______ INSULATION |
______ INSULATION |
______ LATH |
______ DRY WALL |
______ GAS RELEASE |
______ ELECTRICAL FINAL |
______ GAS RELEASE |
______ ELECTRICAL FINAL |
______ ELECTRICAL FINAL |
______ ELECTRICAL FINAL |
______ FLATWORK |
______ PLUMBMECHFINAL |
______ PLUMBMECHFINAL |
______ PLUMBMECHFINAL |
______ MISCCO |
______ MISCCO |
______ UTILITY / ROW |
______ CO/BUILDING FINAL |
|
The project described shall be built in accordance with plans and specifications submitted at time of applications. All provisions of law and ordinances governing this type of work will be complied with whether specified or not. Granting of a permit does not presume to give authority to violate or cancel the provisions of any other local or state law regulating construction or the performance of construction. (The City will not assume responsibility for workability of sanitary sewer on all lots. NOTICE: A Certificate of Occupancy Must be Issued Before Any Building is Occupied.)
|
(THIS IS A BASIC PERMIT VIEW ONLY)
|
|