BUILDING
PERMIT
Inspections Line: 972.292.5386 cut-off at 4 PM the business day before
OR
Request Inspections online at https:\\etrakit.friscotexas.gov\etrakit until 7:00 AM same day
Contact assigned inspector for cancellation.
|
CITY OF FRISCO
6101 Frisco Square Blvd, TX 75034
Phone: 972.292.5301
|
APPROVED DATE: 11/12/2014
|
PERMIT SUB-TYPE: SNEW
|
PERMIT NO: B14-8634
|
JOB ADDRESS: 10309 PERKINS LN FRISCO, TX 75035 |
DESC:
3437 AC, 4205 SF, SFR / 2 STORY |
|
OWNER:
MISHRA BIBHU PRASAD
FRISCO TX 75035-1247
|
CONTRACTOR:
LENNAR HOMES
IRVING TX 75063
|
ISSUED DATE: 12/9/2014
APPLIED DATE:10/16/2014
EXPIRED DATE:12/27/2015
SITE APN:ADD87852
STATUS:COMPLETED
|
|
APPLICANT:
LENNAR HOMES
IRVING TX 75063
|
LEGAL DESC:
COUNTY:
ZONING:
VALUATION: 256434.57
|
|
FEE SUMMARY
|
INSPECTION SUMMARY
|
ELECTRICAL ROUGH IN 02/17/2015 ADE | $30.00 |
RESIDENTIAL ELECTRIC FEE | $126.15 |
MISCELLANOUS MECHANICAL FEES | $152.50 |
MISCELLANEOUS PLUMBING FEES | $270.00 |
BUILDING PERMIT FEE | $1,778.75 |
FENCE FEE | $20.00 |
ELECTRICAL FINAL 06/04/2015 CW | $30.00 |
CREDIT CARD FEE | $0.60 |
CREDIT CARD FEE | $1.80 |
DRY WALL 03/17/2015 GLQ | $30.00 |
PLUMBTOPOUT/MECHRGH 02/17/2015 GU | $30.00 |
THOROUGHFARE IMPACT FEE | $3,083.00 |
WATER IMPACT FEE | $1,772.00 |
SEWER IMPACT FEE | $1,619.00 |
WATER METER DEPOSIT | $100.00 |
1 INCH PD METER | $400.00 |
Total Fees: | $9,443.80 |
|
|
| ______ METER PAYMENT |
______ SET 1 PD METER |
______ PLUMBING ROUGH-IN |
______ T-POLE |
______ SLAB |
______ CAMERA |
______ PLUMBTOPOUT AND MECHRGH |
______ ELECTRICAL ROUGH IN |
______ PLUMBTOPOUT AND MECHRGH |
______ ELECTRICAL ROUGH IN |
______ ELECTRICAL ROUGH IN |
______ ELECTRICAL ROUGH IN |
______ 2NDS/FRAMING |
______ INSULATION |
______ DRY WALL |
______ DRY WALL |
______ BRICK/WALL TIES |
______ FLATWORK |
______ FLATWORK |
______ FLATWORK |
______ ELECTRICAL FINAL |
______ GAS RELEASE |
______ ELECTRICAL FINAL |
______ ELECTRICAL FINAL |
______ PLUMBMECHFINAL |
______ UTILITY / ROW |
______ PLUMBMECHFINAL |
______ CO/BUILDING FINAL |
______ CO/BUILDING FINAL |
|
The project described shall be built in accordance with plans and specifications submitted at time of applications. All provisions of law and ordinances governing this type of work will be complied with whether specified or not. Granting of a permit does not presume to give authority to violate or cancel the provisions of any other local or state law regulating construction or the performance of construction. (The City will not assume responsibility for workability of sanitary sewer on all lots. NOTICE: A Certificate of Occupancy Must be Issued Before Any Building is Occupied.)
|
(THIS IS A BASIC PERMIT VIEW ONLY)
|
|