Phone: 972.292.5301
|
APPROVED DATE: 9/25/2014
|
PERMIT SUB-TYPE: SNEW
|
PERMIT NO: B14-7568
|
JOB ADDRESS: 7505 BRYCE CANYON DR FRISCO, TX 75035 |
DESC:
3825 AC, 4487 SF, SFR / 2 STORY |
|
OWNER:
HIGHLAND HOMES
PLANO TX 75024
|
CONTRACTOR:
HIGHLAND HOMES
PLANO TX 75024
|
ISSUED DATE: 11/20/2014
APPLIED DATE:9/15/2014
EXPIRED DATE:11/17/2015
SITE APN:C2682838
STATUS:COMPLETED
|
|
APPLICANT:
HIGHLAND HOMES
PLANO TX 75024
|
LEGAL DESC:
COUNTY:
ZONING:
VALUATION: 285383.25
|
|
FEE SUMMARY
|
INSPECTION SUMMARY
|
SET 1 PD METER 12/08/2014 JAR | $20.00 |
SLAB 12/23/2014 GLQ | $30.00 |
PLUMBMECHFINAL 05/12/2015 GU | $30.00 |
RESIDENTIAL ELECTRIC FEE | $134.61 |
MISCELLANOUS MECHANICAL FEES | $152.50 |
MISCELLANEOUS PLUMBING FEES | $270.00 |
BUILDING PERMIT FEE | $1,923.75 |
FENCE FEE | $20.00 |
2NDS/FRAMING 02/02/2015 JCF | $30.00 |
UTILITY / ROW 04/28/2015 KB | $80.00 |
SET 1 PD METER 12/08/2014 JAR | $60.00 |
WATER METER DEPOSIT | $100.00 |
1 INCH PD METER | $400.00 |
GAS RELEASE 04/02/2015 MRT | $30.00 |
THOROUGHFARE IMPACT FEE | $2,502.00 |
WATER IMPACT FEE | $1,772.00 |
SEWER IMPACT FEE | $1,553.00 |
Total Fees: | $9,107.86 |
|
|
| ______ METER PAYMENT |
______ T-POLE |
______ SET 1 PD METER |
______ SET 1 PD METER |
______ PLUMBING ROUGH-IN |
______ SLAB |
______ SLAB |
______ SLAB |
______ FLATWORK |
______ CAMERA |
______ ELECTRICAL ROUGH IN |
______ PLUMBTOPOUT AND MECHRGH |
______ ELECTRICAL ROUGH IN |
______ PLUMBTOPOUT AND MECHRGH |
______ 2NDS/FRAMING |
______ 2NDS/FRAMING |
______ 2NDS/FRAMING |
______ INSULATION |
______ INSULATION |
______ DRY WALL |
______ DRY WALL |
______ BRICK/WALL TIES |
______ ELECTRICAL FINAL |
______ GAS RELEASE |
______ GAS RELEASE |
______ GAS RELEASE |
______ GAS RELEASE |
______ UTILITY / ROW |
______ PLUMBMECHFINAL |
______ UTILITY / ROW |
______ UTILITY / ROW |
______ PLUMBMECHFINAL |
______ PLUMBMECHFINAL |
______ CO/BUILDING FINAL |
______ CO/BUILDING FINAL |
|
The project described shall be built in accordance with plans and specifications submitted at time of applications. All provisions of law and ordinances governing this type of work will be complied with whether specified or not. Granting of a permit does not presume to give authority to violate or cancel the provisions of any other local or state law regulating construction or the performance of construction. (The City will not assume responsibility for workability of sanitary sewer on all lots. NOTICE: A Certificate of Occupancy Must be Issued Before Any Building is Occupied.)
|