Seal BUILDING
PERMIT
Inspections Line: 972.292.5386 cut-off at 4 PM the business day before
OR
Request Inspections online at https:\\etrakit.friscotexas.gov\etrakit until 7:00 AM same day
Contact assigned inspector for cancellation.
CITY OF FRISCO
6101 Frisco Square Blvd, TX 75034
Phone: 972.292.5301
APPROVED DATE: 9/16/2013 PERMIT SUB-TYPE: SNEW PERMIT NO: B13-3261
JOB ADDRESS:
6436 SILVER STREAM LN
FRISCO, TX
DESC:   5299 AC, 6360 SF, SFR / 2 STORY
OWNER:
HUNTINGTON HOMES
SUITE 300
FRISCO TX 75035

CONTRACTOR:
HUNTINGTON HOMES
SUITE 300
FRISCO TX 75035
ISSUED DATE:
10/9/2013
APPLIED DATE:
9/13/2013
EXPIRED DATE:
12/15/2014
SITE APN:
D561554
STATUS:
COMPLETED
APPLICANT:
HUNTINGTON HOMES
SUITE 300
FRISCO TX 75035
LEGAL DESC:
COUNTY:
ZONING:
VALUATION:
395358.39
FEE SUMMARY
INSPECTION SUMMARY
SLAB 12/31/2013 ADE$30.00
2NDS/FRAMING 02/25/2014 GLQ$30.00
2NDS/FRAMING 02/27/2014 GLQ$30.00
2NDS/FRAMING 02/28/2014 GLQ$30.00
INSULATION 03/14/2014 GLQ$30.00
FIRE DEPT INSPECTION FEES$190.80
GAS RELEASE 05/13/2014 TRC$30.00
PLUMBMECHFINAL 05/15/2014 TRC$30.00
PLUMBMECHFINAL 06/09/2014 TRC$30.00
FENCE FEE$20.00
BUILDING PERMIT FEE$2,473.75
MISCELLANEOUS PLUMBING FEES$333.00
MISCELLANOUS MECHANICAL FEES$162.00
RESIDENTIAL ELECTRIC FEE$190.80
1 INCH PD METER$400.00
WATER METER DEPOSIT$75.00
SEWER IMPACT FEE$0.00
WATER IMPACT FEE$0.00
THOROUGHFARE IMPACT FEE$0.00
PLUMBTOPOUT/MECHRGH 02/21/2014 GU$20.00
PLUMBTOPOUT/MECHRGH 02/21/2014 GU$10.00
Total Fees:$4,115.35
______  METER PAYMENT
______  T-POLE
______  SET 1 PD METER
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  SLAB
______  SLAB
______  CAMERA
______  ELECTRICAL ROUGH IN
______  PLUMBTOPOUT AND MECHRGH
______  AUTOFIRE SPRK HYDRO
______  AUTOFIRE SPRK VISUAL
______  PLUMBTOPOUT AND MECHRGH
______  2NDS/FRAMING
______  2NDS/FRAMING
______  2NDS/FRAMING
______  SHEATHING
______  2NDS/FRAMING
______  INSULATION
______  INSULATION
______  DRY WALL
______  BRICK/WALL TIES
______  FLATWORK
______  ELECTRICAL FINAL
______  GAS RELEASE
______  PLUMBMECHFINAL
______  GAS RELEASE
______  GAS RELEASE
______  PLUMBMECHFINAL
______  PLUMBMECHFINAL
______  UTILITY / ROW
______  CO/BUILDING FINAL
______  CO/BUILDING FINAL
The project described shall be built in accordance with plans and specifications submitted at time of applications. All provisions of law and ordinances governing this type of work will be complied with whether specified or not. Granting of a permit does not presume to give authority to violate or cancel the provisions of any other local or state law regulating construction or the performance of construction. (The City will not assume responsibility for workability of sanitary sewer on all lots. NOTICE: A Certificate of Occupancy Must be Issued Before Any Building is Occupied.)