APPROVED DATE: 5/29/2013 PERMIT SUB-TYPE: SCHL PERMIT NO: B13-1161
JOB ADDRESS:
12333 BRIAR RIDGE RD
FRISCO, TX
DESC:   88332 SQ FT, SCHL / JAMES R NEWMAN ELEMENTARY SCHOOL
OWNER:
FRISCO ISD

FRISCO TX 75035

CONTRACTOR:
RATCLIFF CONSTRUCTORS
REC'VD VALID
ADDISON TX 75001
ISSUED DATE:
5/31/2013
APPLIED DATE:
4/5/2013
EXPIRED DATE:
12/10/2014
SITE APN:
D296925
STATUS:
COMPLETED
APPLICANT:
SHW GROUP

PLANO TX 75024
LEGAL DESC:
COUNTY:
ZONING:
VALUATION:
12500000
FEE SUMMARY
INSPECTION SUMMARY
ELECTRICAL ROUGH IN 02/04/2014 JB$35.00
ELECTRICAL ROUGH IN 02/06/2014 JB$35.00
ELECTRICAL ROUGH IN 02/24/2014 JB$35.00
PLUMBING FINAL 05/12/2014 KSH$35.00
4 INCH COMP METER$3,000.00
WATER METER DEPOSIT COMMERCIAL$1,100.00
FIRE DEPT INSPECTION FEES$50.00
FIRE DEPT INSPECTION FEES$150.00
MISCELLANOUS MECHANICAL FEES$3,300.76
MISCELLANEOUS PLUMBING FEES$2,475.57
COMMERCIAL ELECTRIC FEE$3,533.28
COMMERCIAL BUILDING PERMIT FEE$25,102.14
SATURDAY WORK FEES$150.00
CREDIT CARD FEE$1.00
FIRE DEPT INSPECTION FEES$2,649.96
FIRE DEPT INSPECTION FEES$400.00
WATER 08/06/2013 TRC$35.00
Total Fees:$42,087.71
______  UNDRGR FIRE MAIN VIS
______  WATER
______  UNDRGR FIRE MAIN VIS
______  WATER
______  UNDRGR FIRE MAIN HYD
______  PIER
______  FOOTINGS
______  ELECTRICAL ROUGH IN
______  PAVING
______  PAVING
______  FOOTINGS
______  ELECTRICAL ROUGH IN
______  PAVING
______  FOOTINGS
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  PAVING
______  PLUMBING ROUGH-IN
______  COMM SLAB
______  ELECTRICAL ROUGH IN
______  COMM SLAB
______  PLUMBING ROUGH-IN
______  MISC
______  PLUMBING ROUGH-IN
______  FOOTINGS
______  PLUMBING ROUGH-IN
______  TILT WALL PANELS
______  FOOTINGS
______  COMM SLAB
______  COMM SLAB
______  PLUMBING ROUGH-IN
______  COMM SLAB
______  TILT WALL PANELS
______  PLUMBING ROUGH-IN
______  FOOTINGS
______  COMM SLAB
______  GREASE TRAP
______  PLUMBING ROUGH-IN
______  TILT WALL PANELS
______  COMM SLAB
______  UNDRGR FIRE MAIN FLU
______  UNDRGR FIRE MAIN HYD
______  PLUMBING ROUGH-IN
______  TILT WALL PANELS
______  COMM SLAB
______  COMM SLAB
______  TILT WALL PANELS
______  COMM SLAB
______  TILT WALL PANELS
______  COMM SLAB
______  TILT WALL PANELS
______  TILT WALL PANELS
______  ELECTRICAL ROUGH IN
______  MECHANICAL ROUGH
______  COMM FRAME
______  ELEC WALL
______  COMM FRAME
______  ELEC WALL
______  COMM FRAME
______  PLUMBING ROUGH-IN
______  COMM PLUMB TOP OUT
______  BRICK/WALL TIES
______  COMM FRAME
______  BRICK/WALL TIES
______  COMM PLUMB TOP OUT
______  COMM FRAME
______  INSULATION
______  COMM PLUMB TOP OUT
______  ELECTRICAL ROUGH IN
______  ELECTRICAL ROUGH IN
______  COMM PLUMB TOP OUT
______  COMM FRAME
______  INSULATION
______  BRICK
______  COMM PLUMB TOP OUT
______  AUTOFIRE SPRK VISUAL
______  COMM PLUMB TOP OUT
______  ELECTRICAL ROUGH IN
______  COMM PLUMB TOP OUT
______  COMM FRAME
______  BRICK
______  COMM PLUMB TOP OUT
______  MECHANICAL ROUGH
______  ELECTRICAL ROUGH IN
______  COMM FRAME
______  COMM FRAME
______  COMM PLUMB TOP OUT
______  COMM SLAB
______  PLUMBING ROUGH-IN
______  ELECTRICAL ROUGH IN
______  AUTOFIRE SPRK PARTI
______  ELECTRICAL ROUGH IN
______  ELECTRICAL ROUGH IN
______  COMM FRAME
______  MECHANICAL ROUGH
______  COMM PLUMB TOP OUT
______  ELECTRICAL ROUGH IN
______  COMM PLUMB TOP OUT
______  COMM FRAME
______  ELECTRICAL RELEASE
______  MECHANICAL ROUGH
______  ELECTRICAL ROUGH IN
______  COMM PLUMB TOP OUT
______  CEILING
______  MECHANICAL ROUGH
______  4 PD METER
______  METER PAYMENT
______  LATH
______  AUTOFIRE SPRK HYDRO
______  AUTOFIRE SPRK VISUAL
______  ELECTRICAL ROUGH IN
______  AUTOFIRE SPRK HYDRO
______  AUTOFIRE SPRK VISUAL
______  GAS PRESSURE
______  ELECTRICAL ROUGH IN
______  GAS RELEASE
______  ELECTRICAL ROUGH IN
______  AUTOFIRE SPRK HYDRO
______  AUTOFIRE SPRK VISUAL
______  CEILING
______  FLATWORK
______  FLATWORK
______  FLATWORK
______  FLATWORK
______  FLATWORK
______  PLUMBING FINAL
______  COMM PLUMB TOP OUT
______  CEILING
______  ELECTRICAL ROUGH IN
______  PLUMBING FINAL
______  HEALTH FINAL
______  MECHANICAL FINAL
______  FLATWORK
______  AUTOFIRE SPRK HYDRO
______  AUTOFIRE SPRK VISUAL
______  LIFESAFETY
______  COMM FRAME
______  ELECTRICAL FINAL
______  LIFESAFETY
______  ELECTRICAL FINAL
______  FIRE FINAL
______  LANDSCAPE
______  COMM CO
______  FIRE FINAL
Notes: