APPROVED DATE: 7/10/2012
|
PERMIT SUB-TYPE: SNEW
|
PERMIT NO: B12-1748
|
JOB ADDRESS: 12723 RIDGE SPRING FRISCO, TX 75035 |
DESC:
2774 AC, 3433SF, SFR / 1 STORY |
|
OWNER:
MHI - COVENTRY, PLANTATION PIO
1501 LBJ FRWY STE 100 DALLAS TX 75234
|
CONTRACTOR:
MHI - COVENTRY, PLANTATION PIO
1501 LBJ FRWY STE 100 DALLAS TX 75234
|
ISSUED DATE: 7/19/2012
APPLIED DATE:7/5/2012
EXPIRED DATE:1/15/2013
SITE APN:C2647656
STATUS:COMPLETED
|
|
APPLICANT:
MHI - COVENTRY, PLANTATION PIO
1501 LBJ FRWY STE 100 DALLAS TX 75234
|
LEGAL DESC:
COUNTY:
ZONING:
VALUATION: 206968.14
|
|
FEE SUMMARY
|
INSPECTION SUMMARY
|
SET 1 PD METER 07/23/2012 KBO | $50.00 |
THOROUGHFARE IMPACT FEE | $4,000.00 |
WATER IMPACT FEE | $1,911.00 |
SEWER IMPACT FEE | $1,553.00 |
RESIDENTIAL ELECTRIC FEE | $102.99 |
MISCELLANOUS MECHANICAL FEES | $103.00 |
MISCELLANEOUS PLUMBING FEES | $209.00 |
BUILDING PERMIT FEE | $1,528.75 |
FENCE FEE | $20.00 |
2NDS/FRAMING 10/08/2012 CW | $30.00 |
INSULATION 10/18/2012 CW | $30.00 |
2NDS/FRAMING 10/18/2012 CW | $30.00 |
WATER METER DEPOSIT | $75.00 |
1 INCH PD METER | $355.00 |
PLUMBING ROUGH-IN 08/31/2012 GU | $30.00 |
T-POLE 09/06/2012 JKT | $30.00 |
PLUMBING ROUGH-IN 09/04/2012 JTH | $30.00 |
PLUMBING ROUGH-IN 09/04/2012 JTH | $30.00 |
Total Fees: | $10,117.74 |
|
|
| ______ METER PAYMENT |
______ SET 1 PD METER |
______ SET 1 PD METER |
______ T-POLE |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ T-POLE |
______ T-POLE |
______ SLAB |
______ CAMERA |
______ PLUMBTOPOUT AND MECHRGH |
______ PLUMBTOPOUT AND MECHRGH |
______ ELECTRICAL ROUGH IN |
______ 2NDS/FRAMING |
______ 2NDS/FRAMING |
______ INSULATION |
______ 2NDS/FRAMING |
______ INSULATION |
______ 2NDS/FRAMING |
______ INSULATION |
______ DRY WALL |
______ DRY WALL |
______ BRICK/WALL TIES |
______ FLATWORK |
______ ELECTRICAL FINAL |
______ GAS RELEASE |
______ UTILITY / ROW |
______ PLUMBING FINAL |
______ PLUMBING FINAL |
______ CO/BUILDING FINAL |
______ CO/BUILDING FINAL |
|
The project described shall be built in accordance with plans and specifications submitted at time of applications. All provisions of law and ordinances governing this type of work will be complied with whether specified or not. Granting of a permit does not presume to give authority to violate or cancel the provisions of any other local or state law regulating construction or the performance of construction. (The City will not assume responsibility for workability of sanitary sewer on all lots. NOTICE: A Certificate of Occupancy Must be Issued Before Any Building is Occupied.)
|
(THIS IS A BASIC PERMIT VIEW ONLY)
|
|