BUILDING
PERMIT
Inspections Line: 972.292.5386 cut-off at 4 PM the business day before
OR
Request Inspections online at https:\\etrakit.friscotexas.gov\etrakit until 7:00 AM same day
Contact assigned inspector for cancellation.
|
CITY OF FRISCO
6101 Frisco Square Blvd, TX 75034
Phone: 972.292.5301
|
APPROVED DATE: 4/16/2012
|
PERMIT SUB-TYPE: CIFO
|
PERMIT NO: B12-0606
|
JOB ADDRESS: 5757 WARREN PKWY #215 FRISCO, TX 75034 |
DESC:
1399 SQ FT, CIFO / SPEC SPACE 215 |
|
OWNER:
HR ACQUISITION OF SAN ANTONIO
NASHVILLE TN 37203-1097
|
CONTRACTOR:
MAPP CONSTRUCTION LLC
DALLAS TX 75219
|
ISSUED DATE: 4/18/2012
APPLIED DATE:3/22/2012
EXPIRED DATE:10/15/2012
SITE APN:C2632290
STATUS:COMPLETED
|
|
APPLICANT:
MAPP CONSTRUCTION LLC
DALLAS TX 75219
|
LEGAL DESC:
COUNTY:
ZONING:
VALUATION: 97930
|
|
FEE SUMMARY
|
INSPECTION SUMMARY
|
FIRE DEPT INSPECTION FEES | $50.00 |
MISCELLANOUS MECHANICAL FEES | $142.50 |
MISCELLANEOUS PLUMBING FEES | $105.00 |
COMMERCIAL ELECTRIC FEE | $75.84 |
COMMERCIAL BUILDING PERMIT FEE | $587.85 |
PLAN REVIEW FEE | $50.00 |
FIRE DEPT INSPECTION FEES | $50.00 |
CREDIT CARD FEE | $1.00 |
MECHANICAL ROUGH 05/31/2012 TW | $35.00 |
Total Fees: | $1,097.19 |
|
|
| ______ ELECTRICAL ROUGH IN |
______ PLUMBING ROUGH-IN |
______ COMM PLUMB TOP OUT |
______ COMM FRAME |
______ INSULATION |
______ COMMDRYWALL |
______ MECHANICAL ROUGH |
______ CEILING |
______ AUTOFIRE SPRK VISUAL |
______ MECHANICAL ROUGH |
______ CEILING |
______ CEILING |
______ MECHANICAL ROUGH |
______ ELECTRICAL FINAL |
______ MECHANICAL FINAL |
______ FIRE FINAL |
______ COMM CO |
______ PLUMBING FINAL |
______ MECHANICAL FINAL |
|
The project described shall be built in accordance with plans and specifications submitted at time of applications. All provisions of law and ordinances governing this type of work will be complied with whether specified or not. Granting of a permit does not presume to give authority to violate or cancel the provisions of any other local or state law regulating construction or the performance of construction. (The City will not assume responsibility for workability of sanitary sewer on all lots. NOTICE: A Certificate of Occupancy Must be Issued Before Any Building is Occupied.)
|
(THIS IS A BASIC PERMIT VIEW ONLY)
|
|