APPROVED DATE: 11/9/2011
|
PERMIT SUB-TYPE: CNEW
|
PERMIT NO: B11-2376
|
JOB ADDRESS: 6515 LONE STAR RANCH PKWY FRISCO, TX 75034 |
DESC:
2982 SQ FT, CNEW / VISTA PARK AT PCR AMENITY CENTER |
|
OWNER:
PCR LAND COMPANY LLC
DALLAS TX 75225
|
CONTRACTOR:
SPRING VALLEY CONST
DALLAS TX 75238
|
ISSUED DATE: 1/31/2012
APPLIED DATE:10/11/2011
EXPIRED DATE:7/29/2012
SITE APN:D75043
STATUS:COMPLETED
|
|
APPLICANT:
PCR LAND COMPANY LLC
DALLAS TX 75225
|
LEGAL DESC:
COUNTY:
ZONING:
VALUATION: 2250000
|
|
FEE SUMMARY
|
INSPECTION SUMMARY
|
LATH 06/05/2012 CW | $30.00 |
CREDIT CARD FEE | $2.70 |
REPLACE DAMAGED/UNREADABLE REGISTER | $500.00 |
FIRE DEPT INSPECTION FEES | $50.00 |
THOROUGHFARE IMPACT FEE | $0.00 |
WATER IMPACT FEE | $0.00 |
SEWER IMPACT FEE | $0.00 |
MISCELLANOUS MECHANICAL FEES | $202.69 |
MISCELLANEOUS PLUMBING FEES | $199.19 |
COMMERCIAL ELECTRIC FEE | $258.92 |
COMMERCIAL BUILDING PERMIT FEE | $5,729.64 |
FIRE DEPT INSPECTION FEES | $100.00 |
WATER METER DEPOSIT | $75.00 |
2 INCH PD METER | $635.00 |
FIRE DEPT INSPECTION FEES | $50.00 |
FIRE DEPT INSPECTION FEES | $50.00 |
FIRE DEPT INSPECTION FEES | $140.07 |
PLUMBING FINAL 10/24/2012 TRC | $35.00 |
PLUMBING FINAL 10/26/2012 TRC | $35.00 |
FLATWORK 11/20/2012 TW | $35.00 |
Total Fees: | $8,128.21 |
|
|
| ______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ ELECTRICAL ROUGH IN |
______ COMM SLAB |
______ AUTOFIRE SPRK VISUAL |
______ PLUMBING ROUGH-IN |
______ ELECTRICAL |
______ SLAB |
______ PLUMBING ROUGH-IN |
______ CAMERA |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ ELECTRICAL ROUGH IN |
______ COMM SLAB |
______ COMM SLAB |
______ ELECTRICAL ROUGH IN |
______ FLATWORK |
______ FLATWORK |
______ ELECTRICAL ROUGH IN |
______ COMM SLAB |
______ MISCFRAME |
______ COMM PLUMB TOP OUT |
______ CMUWALL |
______ LATH |
______ LATH |
______ COMM PLUMB TOP OUT |
______ ELECTRICAL ROUGH IN |
______ LATH |
______ COMM PLUMB TOP OUT |
______ BRICK |
______ BRICK |
______ ELECTRICAL ROUGH IN |
______ BRICK/WALL TIES |
______ AUTOFIRE SPRK HYDRO |
______ AUTOFIRE SPRK VISUAL |
______ MECHANICAL ROUGH |
______ FOOTINGS |
______ AUTOFIRE SPRK VISUAL |
______ MECHANICAL ROUGH |
______ MECHANICAL ROUGH |
______ MECHANICAL ROUGH |
______ COMM FRAME |
______ INSULATION |
______ INSULATION |
______ MECHANICAL ROUGH |
______ COMMDRYWALL |
______ COMMDRYWALL |
______ ELECTRICAL RELEASE |
______ UNDRGR FIRE MAIN VIS |
______ CEILING |
______ PLUMBING FINAL |
______ UNDRGR FIRE MAIN FLU |
______ UNDRGR FIRE MAIN HYD |
______ METER PAYMENT |
______ UNDERGROUND ELEC |
______ SET 2 PD METER |
______ PAVING |
______ PAVING |
______ FLATWORK |
______ ELECTRICAL ROUGH IN |
______ PIER |
______ FLATWORK |
______ FLATWORK |
______ MECHANICAL FINAL |
______ FLATWORK |
______ FOOTINGS |
______ PLUMBING FINAL |
______ PLUMBING FINAL |
______ ELECTRICAL FINAL |
______ PLUMBING FINAL |
______ PLUMBING FINAL |
______ ELECTRICAL FINAL |
______ ELECTRICAL FINAL |
______ MECHANICAL FINAL |
______ WATER REGISTER |
______ FLATWORK |
______ FLATWORK |
______ FIRE FINAL |
______ FLATWORK |
______ BUILDING FINAL |
______ FIRE FINAL |
______ COMM CO |
______ COMM CO |
______ COMM CO |
______ ACCESS CONTROL ACCEP |
______ FIRE FINAL |
______ FIRE FINAL |
|
The project described shall be built in accordance with plans and specifications submitted at time of applications. All provisions of law and ordinances governing this type of work will be complied with whether specified or not. Granting of a permit does not presume to give authority to violate or cancel the provisions of any other local or state law regulating construction or the performance of construction. (The City will not assume responsibility for workability of sanitary sewer on all lots. NOTICE: A Certificate of Occupancy Must be Issued Before Any Building is Occupied.)
|