BUILDING
PERMIT
Inspections Line: 972.292.5386 cut-off at 4 PM the business day before
OR
Request Inspections online at https:\\etrakit.friscotexas.gov\etrakit until 7:00 AM same day
Contact assigned inspector for cancellation.
|
CITY OF FRISCO
6101 Frisco Square Blvd, TX 75034
Phone: 972.292.5301
|
APPROVED DATE: 1/31/2011
|
PERMIT SUB-TYPE: CIFO
|
PERMIT NO: B11-0147
|
JOB ADDRESS: 3492 LEGACY DR #207 FRISCO, TX 75034 |
DESC:
2326 SQ FT, CIFO / NAIL IDOL dba NAIL PLAZA |
|
OWNER:
LEGACYGOLD LLC
4304 FOXTAIL LN PLANO TX 75024-4819
|
CONTRACTOR:
KENNY NGUYEN DBA NAIL IDOL
3492 LEGACY DR SUITE 207 FRISCO TX 75034
|
ISSUED DATE: 2/8/2011
APPLIED DATE:1/17/2011
EXPIRED DATE:8/7/2011
SITE APN:C2619029
STATUS:COMPLETED
|
|
APPLICANT:
KHA NGUYEN
NOT REGISTERED LITTLE ELM TX 75068
|
LEGAL DESC:
COUNTY:
ZONING:
VALUATION: 45000
|
|
FEE SUMMARY
|
INSPECTION SUMMARY
|
AUTOFIRE SPRK VISUAL 02/24/201 | $50.00 |
MISCELLANOUS MECHANICAL FEES | $237.50 |
MISCELLANEOUS PLUMBING FEES | $210.00 |
COMMERCIAL ELECTRIC FEE | $93.04 |
COMMERCIAL BUILDING PERMIT FEE | $355.95 |
FIRE DEPT INSPECTION FEES | $69.78 |
FIRE DEPT INSPECTION FEES | $50.00 |
PRE POUR INSP 02/17/2011 TW | $35.00 |
COMM PLUMB TOP OUT 02/28/2011 | $35.00 |
MECHANICAL ROUGH 03/04/2011 T | $35.00 |
MECHANICAL ROUGH 03/08/2011 T | $35.00 |
MECHANICAL ROUGH 03/16/2011 T | $35.00 |
PLUMBING FINAL 04/21/2011 TW | $35.00 |
Total Fees: | $1,276.27 |
|
|
| ______ PLUMBING ROUGH-IN |
______ PRE POUR INSP |
______ ELECTRICAL ROUGH IN |
______ AUTOFIRE SPRK VISUAL |
______ COMM PLUMB TOP OUT |
______ ELECTRICAL ROUGH IN |
______ MECHANICAL ROUGH |
______ ELECTRICAL ROUGH IN |
______ MECHANICAL ROUGH |
______ AUTOFIRE SPRK VISUAL |
______ ELECTRICAL ROUGH IN |
______ MECHANICAL ROUGH |
______ MECHANICAL ROUGH |
______ COMM PLUMB TOP OUT |
______ MECHANICAL ROUGH |
______ COMM FRAME |
______ INSULATION |
______ COMMDRYWALL |
______ CEILING |
______ COMM SLAB |
______ COURTESY HEALTH INSP |
______ ELECTRICAL FINAL |
______ MECHANICAL FINAL |
______ ELECTRICAL RELEASE |
______ GAS RELEASE |
______ FIRE FINAL |
______ MECHANICAL FINAL |
______ ELECTRICAL FINAL |
______ PLUMBING FINAL |
______ COMM PLUMB FINAL |
______ COMM CO |
______ FIRE FINAL |
______ FIRE FINAL |
|
The project described shall be built in accordance with plans and specifications submitted at time of applications. All provisions of law and ordinances governing this type of work will be complied with whether specified or not. Granting of a permit does not presume to give authority to violate or cancel the provisions of any other local or state law regulating construction or the performance of construction. (The City will not assume responsibility for workability of sanitary sewer on all lots. NOTICE: A Certificate of Occupancy Must be Issued Before Any Building is Occupied.)
|
(THIS IS A BASIC PERMIT VIEW ONLY)
|
|