APPROVED DATE: 8/30/2010
|
PERMIT SUB-TYPE: SNEW
|
PERMIT NO: B10-1907
|
JOB ADDRESS: 2240 DAMPTON DR FRISCO, TX 75034 |
DESC:
4003 AC, 5098 SF, SFR / 2 STORY |
|
OWNER:
JPA DEVELOPMENT CORPORATION
5729 LEBANON DR #144-201 FRISCO TX 75034
|
CONTRACTOR:
JPA DEVELOPMENT CORPORATION
5729 LEBANON DR #144-201 FRISCO TX 75034
|
ISSUED DATE: 9/3/2010
APPLIED DATE:8/23/2010
EXPIRED DATE:3/2/2011
SITE APN:D524362
STATUS:COMPLETED
|
|
APPLICANT:
JPA DEVELOPMENT CORPORATION
5729 LEBANON DR #144-201 FRISCO TX 75034
|
LEGAL DESC:
COUNTY:
ZONING:
VALUATION: 298663.83
|
|
FEE SUMMARY
|
INSPECTION SUMMARY
|
SLAB 09/23/2010 CSW | $30.00 |
WATER METER DEPOSIT | $75.00 |
1 INCH PD METER | $355.00 |
CREDIT CARD FEE | $3.60 |
CREDIT CARD FEE | $1.80 |
RESIDENTIAL ELECTRIC FEE | $152.94 |
MISCELLANOUS MECHANICAL FEES | $129.50 |
MISCELLANEOUS PLUMBING FEES | $246.00 |
BUILDING PERMIT FEE | $1,988.75 |
FENCE FEE | $20.00 |
THOROUGHFARE IMPACT FEE | $1,952.00 |
WATER IMPACT FEE | $388.00 |
SEWER IMPACT FEE | $523.00 |
2NDS/FRAMING 11/02/2010 REED | $30.00 |
DRY WALL 11/15/2010 REED | $30.00 |
PLUMBING FINAL 01/04/2011 TRC | $30.00 |
PLUMBING FINAL 01/05/2011 TRC | $30.00 |
PLUMBING FINAL 01/06/2011 TRC | $30.00 |
Total Fees: | $6,015.59 |
|
|
| ______ METER PAYMENT |
______ T-POLE |
______ SET 1 PD METER |
______ PLUMBING ROUGH-IN |
______ SLAB |
______ SLAB |
______ CAMERA |
______ ELECTRICAL ROUGH IN |
______ PLUMBTOPOUT AND MECHRGH |
______ PLUMBTOPOUT AND MECHRGH |
______ 2NDS/FRAMING |
______ 2NDS/FRAMING |
______ INSULATION |
______ INSULATION |
______ INSULATION |
______ BRICK/WALL TIES |
______ DRY WALL |
______ DRY WALL |
______ FLATWORK |
______ ELECTRICAL FINAL |
______ GAS RELEASE |
______ PLUMBING FINAL |
______ PLUMBING FINAL |
______ UTILITY / ROW |
______ PLUMBING FINAL |
______ PLUMBING FINAL |
______ GAS RELEASE |
______ PLUMBING FINAL |
______ CO/BUILDING FINAL |
______ CO/BUILDING FINAL |
______ CO/BUILDING FINAL |
|
The project described shall be built in accordance with plans and specifications submitted at time of applications. All provisions of law and ordinances governing this type of work will be complied with whether specified or not. Granting of a permit does not presume to give authority to violate or cancel the provisions of any other local or state law regulating construction or the performance of construction. (The City will not assume responsibility for workability of sanitary sewer on all lots. NOTICE: A Certificate of Occupancy Must be Issued Before Any Building is Occupied.)
|