APPROVED DATE: 8/4/2010
|
PERMIT SUB-TYPE: SNEW
|
PERMIT NO: B10-1742
|
JOB ADDRESS: 11439 GERANIUM FRISCO, TX 75035 |
DESC:
2583 AC, 3131 SF, SFR / 2 STORY |
|
OWNER:
DR HORTON
1901 ASCENSION BLVD.,#100 ARLINGTON TX 76006
|
CONTRACTOR:
DR HORTON
1901 ASCENSION BLVD.,#100 ARLINGTON TX 76006
|
ISSUED DATE: 8/19/2010
APPLIED DATE:8/3/2010
EXPIRED DATE:2/3/2018
SITE APN:C2613683
STATUS:COMPLETED
|
|
APPLICANT:
DR HORTON
1901 ASCENSION BLVD.,#100 ARLINGTON TX 76006
|
LEGAL DESC:
COUNTY:
ZONING:
VALUATION: 192717.63
|
|
FEE SUMMARY
|
INSPECTION SUMMARY
|
WATER METER DEPOSIT | $75.00 |
1 INCH PD METER | $355.00 |
CREDIT CARD FEE | $0.90 |
DRY WALL 10/06/2010 GLQ | $30.00 |
RESIDENTIAL ELECTRIC FEE | $93.93 |
MISCELLANOUS MECHANICAL FEES | $123.00 |
MISCELLANEOUS PLUMBING FEES | $211.00 |
BUILDING PERMIT FEE | $1,458.75 |
FENCE FEE | $20.00 |
PLUMBING FINAL 11/08/2010 JTH | $30.00 |
WATER IMPACT FEE | $388.00 |
SEWER IMPACT FEE | $523.00 |
Total Fees: | $3,308.58 |
|
|
| ______ METER PAYMENT |
______ T-POLE |
______ SET 1 PD METER |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ SLAB |
______ FLATWORK |
______ CAMERA |
______ CAMERA |
______ PLUMBTOPOUT AND MECHRGH |
______ ELECTRICAL ROUGH IN |
______ 2NDS/FRAMING |
______ INSULATION |
______ INSULATION |
______ BRICK/WALL TIES |
______ DRY WALL |
______ DRY WALL |
______ PLUMBTOPOUT AND MECHRGH |
______ ELECTRICAL ROUGH IN |
______ ELECTRICAL FINAL |
______ PLUMBING FINAL |
______ PLUMBING FINAL |
______ UTILITY / ROW |
______ CO/BUILDING FINAL |
______ CO/BUILDING FINAL |
|
The project described shall be built in accordance with plans and specifications submitted at time of applications. All provisions of law and ordinances governing this type of work will be complied with whether specified or not. Granting of a permit does not presume to give authority to violate or cancel the provisions of any other local or state law regulating construction or the performance of construction. (The City will not assume responsibility for workability of sanitary sewer on all lots. NOTICE: A Certificate of Occupancy Must be Issued Before Any Building is Occupied.)
|