BUILDING
PERMIT
Inspections Line: 972.292.5386 cut-off at 4 PM the business day before
OR
Request Inspections online at https:\\etrakit.friscotexas.gov\etrakit until 7:00 AM same day
Contact assigned inspector for cancellation.
|
CITY OF FRISCO
6101 Frisco Square Blvd, TX 75034
Phone: 972.292.5301
|
APPROVED DATE: 4/13/2010
|
PERMIT SUB-TYPE: SNEW
|
PERMIT NO: B10-0657
|
JOB ADDRESS: 8659 MARKHAM DR FRISCO, TX 75035 |
DESC:
4513 AC, 5401 SF, SFR / 2 STORY |
|
OWNER:
HIGHLAND HOMES
12850 HILLCREST STE 20-0 DALLAS TX 75230
|
CONTRACTOR:
HIGHLAND HOMES
12850 HILLCREST STE 20-0 DALLAS TX 75230
|
ISSUED DATE: 4/16/2010
APPLIED DATE:3/30/2010
EXPIRED DATE:10/13/2010
SITE APN:C2649880
STATUS:COMPLETED
|
|
APPLICANT:
HIGHLAND HOMES
12850 HILLCREST STE 20-0 DALLAS TX 75230
|
LEGAL DESC:
COUNTY:
ZONING:
VALUATION: 336714.93
|
|
FEE SUMMARY
|
INSPECTION SUMMARY
|
PLUMBING ROUGH-IN 04/26/2010 | $30.00 |
THOROUGHFARE IMPACT FEE | $1,967.00 |
WATER IMPACT FEE | $1,911.00 |
SEWER IMPACT FEE | $1,553.00 |
WATER METER DEPOSIT | $75.00 |
1 INCH PD METER | $355.00 |
GAS RELEASE 08/10/2010 TRC | $30.00 |
GAS RELEASE 08/12/2010 TRC | $30.00 |
PLUMBING FINAL 08/20/2010 TRC | $30.00 |
RESIDENTIAL ELECTRIC FEE | $162.03 |
MISCELLANOUS MECHANICAL FEES | $149.00 |
MISCELLANEOUS PLUMBING FEES | $295.00 |
BUILDING PERMIT FEE | $2,178.75 |
FENCE FEE | $20.00 |
Total Fees: | $8,785.78 |
|
|
| ______ METER PAYMENT |
______ SET 1 PD METER |
______ T-POLE |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ SLAB |
______ FLATWORK |
______ SLAB |
______ FLATWORK |
______ CAMERA |
______ PLUMBTOPOUT AND MECHRGH |
______ ELECTRICAL ROUGH IN |
______ PLUMBTOPOUT AND MECHRGH |
______ 2NDS/FRAMING |
______ INSULATION |
______ INSULATION |
______ INSULATION |
______ LATH |
______ DRY WALL |
______ BRICK/WALL TIES |
______ ELECTRICAL FINAL |
______ GAS RELEASE |
______ FLATWORK |
______ GAS RELEASE |
______ GAS RELEASE |
______ GAS RELEASE |
______ PLUMBING FINAL |
______ UTILITY / ROW |
______ PLUMBING FINAL |
______ CO/BUILDING FINAL |
______ CO/BUILDING FINAL |
|
The project described shall be built in accordance with plans and specifications submitted at time of applications. All provisions of law and ordinances governing this type of work will be complied with whether specified or not. Granting of a permit does not presume to give authority to violate or cancel the provisions of any other local or state law regulating construction or the performance of construction. (The City will not assume responsibility for workability of sanitary sewer on all lots. NOTICE: A Certificate of Occupancy Must be Issued Before Any Building is Occupied.)
|
(THIS IS A BASIC PERMIT VIEW ONLY)
|
|