APPROVED DATE: 4/12/2010 PERMIT SUB-TYPE: CNEW PERMIT NO: B10-0541
JOB ADDRESS:
15950 ELDORADO PKWY
FRISCO, TX 75035
DESC:   12002 SQ FT, CNEW / CUSTER STAR RETAIL "C"
OWNER:
ELDORADO CROSSING LLC
7001 PRESTON RD STE 500
DALLAS TX 75205-1175

CONTRACTOR:
RIDGEMONT COMMERCIAL CO
1520 WEST WALNUT HILL LANE
IRVING TX 75038
ISSUED DATE:
6/4/2010
APPLIED DATE:
3/10/2010
EXPIRED DATE:
5/12/2018
SITE APN:
C2648773
STATUS:
COMPLETED
APPLICANT:
HODGES & ASSOCIATES PLLC
13642 OMEGA
DALLAS TX 75205
LEGAL DESC:
COUNTY:
ZONING:
VALUATION:
600100
FEE SUMMARY
INSPECTION SUMMARY
ELECTRICAL RELEASE 07/07/2010$35.00
WATER METER DEPOSIT$75.00
2 INCH PD METER$635.00
WATER IMPACT FEE$20,066.00
SEWER IMPACT FEE$12,427.00
THOROUGHFARE IMPACT FEE$24,285.00
FIRE FINAL 09/29/2010 ROC$50.00
FIRE DEPT INSPECTION FEES$50.00
FIRE DEPT INSPECTION FEES$50.00
FIRE DEPT INSPECTION FEES$360.06
FIRE DEPT 1ST INSP FAILED FEE$50.00
MISCELLANEOUS ELECTRICAL FEES$355.04
MISCELLANOUS MECHANICAL FEES$55.45
MISCELLANEOUS PLUMBING FEES$133.00
COMMERCIAL BUILDING PERMIT FEE$2,228.10
PLAN REVIEW FEE$200.00
COMM SLAB 06/16/2010 WKT$35.00
Total Fees:$61,089.65
______  PIER
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  UNDRGR FIRE MAIN VIS
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  METER PAYMENT
______  COMM SLAB
______  PLUMBING ROUGH-IN
______  UNDRGR FIRE MAIN HYD
______  SET 2 PD METER
______  COMM SLAB
______  COMM SLAB
______  PLUMBING ROUGH-IN
______  COMM SLAB
______  LANDSCAPE
______  ELECTRICAL ROUGH IN
______  UNDRGR FIRE MAIN FLU
______  MISC
______  PAVING
______  ELECTRICAL RELEASE
______  ELECTRICAL ROUGH IN
______  SHEATHING
______  SHEATHING
______  BRICK
______  BRICK/WALL TIES
______  SHEATHING
______  BRICK/WALL TIES
______  PIER
______  COMM PLUMB TOP OUT
______  FOOTINGS
______  COMM PLUMB TOP OUT
______  ELECTRICAL ROUGH IN
______  INSULATION
______  INSULATION
______  BRICK
______  COMM FRAME
______  FLATWORK
______  PLUMBING FINAL
______  PAVING
______  AUTOFIRE SPRK HYDRO
______  AUTOFIRE SPRK VISUAL
______  PAVING
______  ELECTRICAL RELEASE
______  ELECTRICAL RELEASE
______  PLUMBING FINAL
______  ELECTRICAL FINAL
______  FIRE FINAL
______  FIRE FINAL
______  FIRE FINAL
______  ELECTRICAL FINAL
______  BUILDING FINAL
______  LANDSCAPE
______  BUILDING FINAL
______  MECHANICAL FINAL
______  BUILDING FINAL
______  MECHANICAL FINAL
The project described shall be built in accordance with plans and specifications submitted at time of applications. All provisions of law and ordinances governing this type of work will be complied with whether specified or not. Granting of a permit does not presume to give authority to violate or cancel the provisions of any other local or state law regulating construction or the performance of construction. (The City will not assume responsibility for workability of sanitary sewer on all lots. NOTICE: A Certificate of Occupancy Must be Issued Before Any Building is Occupied.)

(THIS IS A BASIC PERMIT VIEW ONLY)