APPROVED DATE: 4/1/2009 PERMIT SUB-TYPE: CIFO PERMIT NO: B09-0477
JOB ADDRESS:
2875 MAIN ST #104
FRISCO, TX
DESC:   1345 AC, CIFO / PRETTI NEW
OWNER:
Hebron Heights, LP
800 FM Hwy 720 West, Suite 112
Little Elm TX 75068

CONTRACTOR:
SRM BEAR DESIGN BUILD (TRICON
2995 LBJ FRWY
DALLAS TX 75234
ISSUED DATE:
4/3/2009
APPLIED DATE:
3/14/2009
EXPIRED DATE:
2/3/2018
SITE APN:
R622900102002
STATUS:
COMPLETED
APPLICANT:
SRM BEAR DESIGN BUILD (TRICON
2995 LBJ FRWY
DALLAS TX 75234
LEGAL DESC:
COUNTY:
ZONING:
VALUATION:
20000
FEE SUMMARY
INSPECTION SUMMARY
CONVENIENCE FEE$1.05
CONVENIENCE FEE$1.05
CONVENIENCE FEE$1.05
MECHANICAL FINA 5/11/2009$35.00
PLUMBING FINAL 5/12/2009$35.00
MISCELLANOUS MECHANICAL FEES$99.75
MISCELLANEOUS PLUMBING FEES$70.00
COMMERCIAL ELECTRIC FEE$73.80
COMMERCIAL BUILDING PERMIT FEE$192.75
FIRE DEPT INSPECTION FEES$21.18
MECHANICAL ROUGH 4/24/2009 T$35.00
Total Fees:$565.63
______  ELECTRICAL ROUGH IN
______  MECHANICAL ROUGH
______  PLUMBING ROUGH-IN
______  MISCFRAME
______  COMM PLUMB TOP OUT
______  INSULATION
______  COMM SLAB
______  COMM PLUMB TOP OUT
______  PLUMBING ROUGH-IN
______  MECHANICAL ROUGH
______  INSULATION
______  SLAB
______  COMM PLUMB TOP OUT
______  DRY WALL
______  CAMERA
______  PLUMBING FINAL
______  ELECTRICAL FINAL
______  ELECTRICAL RELEASE
______  MECHANICAL FINAL
______  ELECTRICAL FINAL
______  ELECTRICAL RELEASE
______  MECHANICAL FINAL
______  PLUMBING FINAL
______  PLUMBING FINAL
______  ELECTRICAL FINAL
______  COMM CO
______  AUTOFIRE SPRK HYDRO
______  AUTOFIRE SPRK VISUAL
The project described shall be built in accordance with plans and specifications submitted at time of applications. All provisions of law and ordinances governing this type of work will be complied with whether specified or not. Granting of a permit does not presume to give authority to violate or cancel the provisions of any other local or state law regulating construction or the performance of construction. (The City will not assume responsibility for workability of sanitary sewer on all lots. NOTICE: A Certificate of Occupancy Must be Issued Before Any Building is Occupied.)