Seal BUILDING
PERMIT
Inspections Line: 972.292.5386 cut-off at 4 PM the business day before
OR
Request Inspections online at https:\\etrakit.friscotexas.gov\etrakit until 7:00 AM same day
Contact assigned inspector for cancellation.
CITY OF FRISCO
6101 Frisco Square Blvd, TX 75034
Phone: 972.292.5301
APPROVED DATE: 10/10/2008 PERMIT SUB-TYPE: CNEW PERMIT NO: B08-3415
JOB ADDRESS:
4131 FALLBROOK DRIVE
FRISCO, TX
DESC:   4105 SF, CNEW / NEWMAN VILLAGE AMENITY CENTER (discovery)
OWNER:
DARLING FRISCO PARTNERS LTD
2500 LEGACY STE # 100
FRISCO TX 75034

CONTRACTOR:
DARLING HOMES
2500 LEGACY STE # 100
FRISCO TX 75034
ISSUED DATE:
10/16/2008
APPLIED DATE:
10/9/2008
EXPIRED DATE:
4/14/2009
SITE APN:
STATUS:
COMPLETED
APPLICANT:
DARLING HOMES
2500 LEGACY STE # 100
FRISCO TX 75034
LEGAL DESC:
COUNTY:
ZONING:
VALUATION:
247033.71
FEE SUMMARY
INSPECTION SUMMARY
CONVENIENCE FEE$3.15
CONVENIENCE FEE$1.05
INSULATION 3/4/2009 CSW$30.00
PLUMBING FINAL 6/2/2009$35.00
RESIDENTIAL ELECTRIC FEE$123.15
BUILDING PERMIT FEE$1,733.75
MISCELLANEOUS PLUMBING FEES$241.00
MISCELLANOUS MECHANICAL FEES$82.50
COMM FRAME 1/29/2009$35.00
INSULATION 2/27/2009$35.00
GAS PRESSURE 3/19/2009 JTH$30.00
THOROUGHFARE IMPACT FEE$3,602.00
WATER IMPACT FEE$1,911.00
SEWER IMPACT FEE$1,553.00
WATER METER DEPOSIT$75.00
1 INCH METER$290.00
BUILDING FINAL 6/9/2009 MC$35.00
FIRE DEPT INSPECTION FEES$50.00
CREDIT CARD FEE$1.50
FIRE DEPT INSPECTION FEES$61.59
PLUMBING ROUGH- 11/6/2008$35.00
GAS RELEASE 3/13/2009$35.00
GAS RELEASE 4/29/2009$35.00
PLUMBING FINAL 5/27/2009$35.00
MECHANICAL FINA 5/27/2009$35.00
FIRE DEPT INSPECTION FEES$75.00
GAS PRESSURE 3/17/2009$30.00
Total Fees:$10,208.69
______  METER PAYMENT
______  SET 1 PD METER
______  T-POLE
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  UNDERGROUND ELEC
______  SLAB
______  SLAB
______  CAMERA
______  LATH
______  COMM PLUMB TOP OUT
______  MECHANICAL
______  ELECTRICAL ROUGH IN
______  COMM FRAME
______  COMM FRAME
______  AUTOFIRE SPRK HYDRO
______  COMM FRAME
______  BRICK/WALL TIES
______  BRICK/WALL TIES
______  AUTOFIRE SPRK HYDRO
______  AUTOFIRE SPRK VISUAL
______  INSULATION
______  BRICK/WALL TIES
______  INSULATION
______  UNDRGR FIRE MAIN VIS
______  GAS RELEASE
______  ELECTRICAL RELEASE
______  INSULATION
______  GAS PRESSURE
______  DRY WALL
______  GAS PRESSURE
______  GAS PRESSURE
______  GAS PRESSURE
______  UNDRGR FIRE MAIN HYD
______  UNDRGR FIRE MAIN FLU
______  GAS RELEASE
______  GAS RELEASE
______  GAS RELEASE
______  ELECTRICAL FINAL
______  PLUMBING FINAL
______  MECHANICAL FINAL
______  PLUMBING FINAL
______  PLUMBING FINAL
______  MECHANICAL FINAL
______  PLUMBING FINAL
______  MECHANICAL FINAL
______  PLUMBING FINAL
______  MECHANICAL FINAL
______  FIRE FINAL
______  BUILDING FINAL
______  BUILDING FINAL
The project described shall be built in accordance with plans and specifications submitted at time of applications. All provisions of law and ordinances governing this type of work will be complied with whether specified or not. Granting of a permit does not presume to give authority to violate or cancel the provisions of any other local or state law regulating construction or the performance of construction. (The City will not assume responsibility for workability of sanitary sewer on all lots. NOTICE: A Certificate of Occupancy Must be Issued Before Any Building is Occupied.)