BUILDING
PERMIT
Inspections Line: 972.292.5386 cut-off at 4 PM the business day before
OR
Request Inspections online at https:\\etrakit.friscotexas.gov\etrakit until 7:00 AM same day
Contact assigned inspector for cancellation.
|
CITY OF FRISCO
6101 Frisco Square Blvd, TX 75034
Phone: 972.292.5301
|
APPROVED DATE: 7/1/2008
|
PERMIT SUB-TYPE: SNEW
|
PERMIT NO: B08-2299
|
JOB ADDRESS: 11145 LAMAR LN FRISCO, TX 75034 |
DESC:
4429 AC, 5106 SF, SFR / 2 STORY |
|
OWNER:
SOTHERBY HOMES
2400 DALLAS PARKWAY #580 PLANO TX 75093
|
CONTRACTOR:
SHADDOCK HOMES
2400 DALLAS PKWY, STE 560 PLANO TX 75093
|
ISSUED DATE: 8/4/2008
APPLIED DATE:6/25/2008
EXPIRED DATE:1/31/2009
SITE APN:D288637
STATUS:COMPLETED
|
|
APPLICANT:
SHADDOCK HOMES
2400 DALLAS PKWY, STE 560 PLANO TX 75093
|
LEGAL DESC:
COUNTY:
ZONING:
VALUATION: 330447.69
|
|
FEE SUMMARY
|
INSPECTION SUMMARY
|
PLUMBING ROUGH- 9/4/2008 | $30.00 |
PLUMBING ROUGH- 9/12/2008 | $30.00 |
2NDS/FRAMING 10/31/2008 | $30.00 |
T-POLE 9/5/2008 TLB | $30.00 |
PLUMBING TOP OU 10/15/2008 | $30.00 |
PLUMBING FINAL 1/14/2009 | $30.00 |
PLUMBING FINAL 1/30/2009 RM | $30.00 |
PLUMBING FINAL 1/23/2009 | $30.00 |
FENCE FEE | $20.00 |
BUILDING PERMIT FEE | $2,148.75 |
MISCELLANEOUS PLUMBING FEES | $246.00 |
MISCELLANOUS MECHANICAL FEES | $136.00 |
RESIDENTIAL ELECTRIC FEE | $153.18 |
CO/BUILDING FINAL 2/11/2009 | $30.00 |
CONVENIENCE FEE | $0.90 |
CONVENIENCE FEE | $2.70 |
1 INCH METER | $290.00 |
WATER METER DEPOSIT | $75.00 |
Total Fees: | $3,342.53 |
|
|
| ______ METER PAYMENT |
______ SET 1 PD METER |
______ PLUMBING ROUGH-IN |
______ T-POLE |
______ PLUMBING ROUGH-IN |
______ T-POLE |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ SLAB |
______ CAMERA |
______ LATH |
______ PLUMBING TOP OUT |
______ PLUMBING TOP OUT |
______ ELECTRICAL ROUGH IN |
______ 2NDS/FRAMING |
______ 2NDS/FRAMING |
______ INSULATION |
______ DRY WALL |
______ BRICK/WALL TIES |
______ FLATWORK |
______ FLATWORK |
______ ELECTRICAL FINAL |
______ ELECTRICAL FINAL |
______ PLUMBING FINAL |
______ PLUMBING FINAL |
______ PLUMBING FINAL |
______ GAS RELEASE |
______ PLUMBING FINAL |
______ UTILITY / ROW |
______ PLUMBING FINAL |
______ CO/BUILDING FINAL |
______ CO/BUILDING FINAL |
|
The project described shall be built in accordance with plans and specifications submitted at time of applications. All provisions of law and ordinances governing this type of work will be complied with whether specified or not. Granting of a permit does not presume to give authority to violate or cancel the provisions of any other local or state law regulating construction or the performance of construction. (The City will not assume responsibility for workability of sanitary sewer on all lots. NOTICE: A Certificate of Occupancy Must be Issued Before Any Building is Occupied.)
|
(THIS IS A BASIC PERMIT VIEW ONLY)
|
|