APPROVED DATE: 3/20/2007
|
PERMIT SUB-TYPE: SCHL
|
PERMIT NO: B06-4333
|
JOB ADDRESS: 9889 WADE BLVD FRISCO, TX |
DESC:
138088 SQ FT, SCHL / FISD CAREER & TECHNOLOGY CENTER (CATE) |
|
OWNER:
Frisco Independent School Dist
6942 Maple Street Frisco Tx 75034
|
CONTRACTOR:
CADENCE MCSHANE CORP.
14860 Montfort Drive Dallas Tx 75248
|
ISSUED DATE: 4/5/2007
APPLIED DATE:11/21/2006
EXPIRED DATE:2/3/2018
SITE APN:
STATUS:COMPLETED
|
|
APPLICANT:
SHW GROUP
4000 McEWEN RD. N. Dallas TX 75244
|
LEGAL DESC:
COUNTY:
ZONING:
VALUATION: 24000000
|
|
FEE SUMMARY
|
INSPECTION SUMMARY
|
CREDIT CARD FEE | $3.15 |
SET 2 TURB METER 12/17/2007 | $30.00 |
CREDIT CARD FEE | $4.05 |
CREDIT CARD FEE | $2.10 |
1 1/2 INCH CURBSTOP REPAIR | $0.00 |
COMMDRYWALL 1/29/2008 CW | $35.00 |
T-POLE 6/14/2007 JB | $35.00 |
BRICK/WALL TIES 10/31/2007 J | $35.00 |
WATER METER DEPOSIT | $75.00 |
WATER METER DEPOSIT | $75.00 |
WATER METER DEPOSIT | $75.00 |
2 INCH TURB METER | $615.00 |
2 INCH TURB METER | $615.00 |
2 INCH TURB METER | $615.00 |
WATER METER DEPOSIT | $75.00 |
WATER METER DEPOSIT | $75.00 |
WATER METER DEPOSIT | $75.00 |
4 INCH COMP METER | $2,400.00 |
4 INCH COMP METER | $2,400.00 |
2 INCH PD METER | $400.00 |
2 INCH PD METER | $90.00 |
GAS AIR TEST 2/11/2008 | $35.00 |
ROOF DRAINS 4/23/2008 | $35.00 |
GREASE TRAP 11/28/2007 | $35.00 |
DUCT ROUGH 6/3/2008 | $35.00 |
MECHANICAL FINA 7/11/2008 | $35.00 |
DUCT ROUGH 2/11/2008 TW | $35.00 |
MISCELLANEOUS ELECTRICAL FEES | $6,038.52 |
MISCELLANOUS MECHANICAL FEES | $3,357.20 |
MISCELLANEOUS PLUMBING FEES | $2,552.00 |
COMMERCIAL BUILDING PERMIT FEE | $46,837.14 |
Total Fees: | $66,724.16 |
|
|
| ______ T-POLE |
______ PIER |
______ FOOTINGS |
______ PIER |
______ MISC |
______ ELECTRICAL ROUGH IN |
______ ELECTRICAL ROUGH IN |
______ PIER |
______ T-POLE |
______ PIER |
______ PLUMBING ROUGH-IN |
______ PIER |
______ PLUMBING ROUGH-IN |
______ PIER |
______ T-POLE |
______ ELECTRICAL ROUGH IN |
______ PIER |
______ ELECTRICAL ROUGH IN |
______ PLUMBING ROUGH-IN |
______ ELECTRICAL ROUGH IN |
______ ELECTRICAL ROUGH IN |
______ PIER |
______ ELECTRICAL ROUGH IN |
______ PIER |
______ PIER |
______ PIER |
______ PIER |
______ ELECTRICAL |
______ PLUMBING ROUGH-IN |
______ PAVING |
______ PIER |
______ SLAB |
______ CAMERA |
______ CAMERA |
______ ROOF DRAINS |
______ SLAB |
______ SLAB |
______ PLUMBING ROUGH-IN |
______ PAVING |
______ CAMERA |
______ PAVING |
______ PIER |
______ ELECTRICAL ROUGH IN |
______ PLUMBING ROUGH-IN |
______ FIRELANE INSPECTION |
______ PLUMBING ROUGH-IN |
______ PAVING |
______ FIRELANE INSPECTION |
______ SLAB |
______ PLUMBING ROUGH-IN |
______ CAMERA |
______ FIRELANE INSPECTION |
______ PAVING |
______ PLUMBING ROUGH-IN |
______ PIER |
______ PIER |
______ PLUMBING ROUGH-IN |
______ PAVING |
______ PAVING |
______ PIER |
______ PAVING |
______ SLAB |
______ BRICK/WALL TIES |
______ BRICK/WALL TIES |
______ CAMERA |
______ CAMERA |
______ BRICK/WALL TIES |
______ BRICK/WALL TIES |
______ PAVING |
______ PAVING |
______ BRICK/WALL TIES |
______ BRICK/WALL TIES |
______ BRICK/WALL TIES |
______ PIER |
______ BRICK/WALL TIES |
______ SLAB |
______ PAVING |
______ SLAB |
______ BRICK/WALL TIES |
______ BRICK/WALL TIES |
______ CAMERA |
______ BRICK/WALL TIES |
______ BRICK/WALL TIES |
______ BRICK/WALL TIES |
______ GREASE TRAP |
______ BRICK/WALL TIES |
______ PIER |
______ BRICK/WALL TIES |
______ PIER |
______ BRICK/WALL TIES |
______ TILT WALL PANELS |
______ BRICK/WALL TIES |
______ BRICK/WALL TIES |
______ SLAB |
______ BRICK/WALL TIES |
______ CAMERA |
______ CAMERA |
______ CAMERA |
______ CAMERA |
______ CAMERA |
______ CAMERA |
______ CAMERA |
______ CAMERA |
______ CAMERA |
______ CAMERA |
______ CAMERA |
______ BRICK/WALL TIES |
______ BRICK/WALL TIES |
______ TILT WALL PANELS |
______ SLAB |
______ BRICK/WALL TIES |
______ TILT WALL PANELS |
______ BRICK/WALL TIES |
______ TILT WALL PANELS |
______ SLAB |
______ BRICK/WALL TIES |
______ CAMERA |
______ PIER |
______ BRICK/WALL TIES |
______ BRICK/WALL TIES |
______ BRICK/WALL TIES |
______ BRICK/WALL TIES |
______ BRICK/WALL TIES |
______ BRICK/WALL TIES |
______ BRICK/WALL TIES |
______ SLAB |
______ BRICK/WALL TIES |
______ CAMERA |
______ BRICK/WALL TIES |
______ PIER |
______ BRICK/WALL TIES |
______ BRICK/WALL TIES |
______ PIER |
______ LATH |
______ BRICK/WALL TIES |
______ BRICK/WALL TIES |
______ BRICK/WALL TIES |
______ BRICK/WALL TIES |
______ BRICK/WALL TIES |
______ SLAB |
______ LATH |
______ BRICK/WALL TIES |
______ BRICK/WALL TIES |
______ SLAB |
______ BRICK/WALL TIES |
______ CAMERA |
______ CAMERA |
______ SLAB |
______ BRICK/WALL TIES |
______ BRICK/WALL TIES |
______ BRICK/WALL TIES |
______ BRICK/WALL TIES |
______ BRICK/WALL TIES |
______ BRICK/WALL TIES |
______ BRICK/WALL TIES |
______ GREASE TRAP |
______ GREASE TRAP |
______ BRICK/WALL TIES |
______ GREASE TRAP |
______ GREASE TRAP |
______ BRICK/WALL TIES |
______ GREASE TRAP |
______ LATH |
______ ELEC WALL |
______ METER PAYMENT |
______ METER PAYMENT |
______ METER PAYMENT |
______ SET 2 TURB METER |
______ SET 2 TURB METER |
______ BRICK/WALL TIES |
______ PLUMBING ROUGH-IN |
______ ROOF DRAINS |
______ COMM PLUMB TOP OUT |
______ ROOF DRAINS |
______ ROOF DRAINS |
______ LATH |
______ LATH |
______ COMM PLUMB TOP OUT |
______ ELEC WALL |
______ MISCFRAME |
______ ROOF DRAINS |
______ ELEC WALL |
______ DUCT ROUGH |
______ MISCFRAME |
______ MECHANICAL |
______ GAS PRESSURE |
______ MECHANICAL |
______ MISCFRAME |
______ SET 2 TURB METER |
______ SET 2 TURB METER |
______ INSULATION |
______ COMMDRYWALL |
______ METER PAYMENT |
______ METER PAYMENT |
______ METER PAYMENT |
______ 4 PD METER |
______ 4 PD METER |
______ DRY WALL |
______ DRY WALL |
______ PAVING |
______ DUCT ROUGH |
______ COMM PLUMB TOP OUT |
______ GAS AIR TEST |
______ PLUMBING ROUGH-IN |
______ DUCT ROUGH |
______ COMM PLUMB TOP OUT |
______ DRY WALL |
______ PAVING |
______ DUCT ROUGH |
______ COMM FRAME |
______ CEILING |
______ COMM FRAME |
______ DUCT ROUGH |
______ ROOF DRAINS |
______ COMM PLUMB TOP OUT |
______ ELECTRICAL RELEASE |
______ DUCT ROUGH |
______ ELECTRICAL RELEASE |
______ GAS AIR TEST |
______ COMM PLUMB TOP OUT |
______ PLUMBING ROUGH-IN |
______ COMM PLUMB TOP OUT |
______ COMM PLUMB TOP OUT |
______ DRY WALL |
______ DRY WALL |
______ COMM PLUMB TOP OUT |
______ ELECTRICAL RELEASE |
______ CEILING |
______ COMM FRAME |
______ COMM PLUMB TOP OUT |
______ CEILING |
______ COMM PLUMB TOP OUT |
______ COMM PLUMB TOP OUT |
______ SET 2 PD METER |
______ ROOF DRAINS |
______ ELECTRICAL ROUGH IN |
______ SIDEWALK |
______ RETAINING WALL |
______ ELEC WALL |
______ ROOF DRAINS |
______ COMM PLUMB TOP OUT |
______ ROOF DRAINS |
______ ROOF DRAINS |
______ CEILING |
______ CEILING |
______ DUCT ROUGH |
______ VENT HOOD |
______ VENT HOOD |
______ CEILING |
______ CEILING |
______ CEILING |
______ DUCT ROUGH |
______ CEILING |
______ GAS RELEASE |
______ CEILING |
______ CEILING |
______ GAS RELEASE |
______ CEILING |
______ MECHANICAL ROUGH |
______ PLUMBING FINAL |
______ MECHANICAL FINAL |
______ ELECTRICAL FINAL |
______ MECHANICAL FINAL |
______ PLUMBING FINAL |
______ MECHANICAL FINAL |
______ ELECTRICAL FINAL |
______ ELECTRICAL FINAL |
______ PLUMBING FINAL |
______ MECHANICAL FINAL |
______ COURTESY HEALTH INSP |
______ PLUMBING FINAL |
______ COURTESY HEALTH INSP |
______ MECHANICAL FINAL |
______ ELECTRICAL FINAL |
______ CEILING |
______ INSULATION |
______ ELECTRICAL FINAL |
______ MECHANICAL FINAL |
______ HEALTH FINAL |
______ BUILDING FINAL |
______ COURTESY HEALTH INSP |
______ BUILDING FINAL |
______ SET 2 PD METER |
|
The project described shall be built in accordance with plans and specifications submitted at time of applications. All provisions of law and ordinances governing this type of work will be complied with whether specified or not. Granting of a permit does not presume to give authority to violate or cancel the provisions of any other local or state law regulating construction or the performance of construction. (The City will not assume responsibility for workability of sanitary sewer on all lots. NOTICE: A Certificate of Occupancy Must be Issued Before Any Building is Occupied.)
|