Seal BUILDING
Permit Payment Receipt


CITY OF FRISCO
6101 Frisco Square Blvd, TX 75034
Phone: 972.292.5301
APPROVED DATE: 3/20/2007 PERMIT SUB-TYPE: SCHL PERMIT NO: B06-4333
JOB ADDRESS:
9889 WADE BLVD
FRISCO, TX
DESC:   138088 SQ FT, SCHL / FISD CAREER & TECHNOLOGY CENTER (CATE)
OWNER:
Frisco Independent School Dist
6942 Maple Street
Frisco Tx 75034

CONTRACTOR:
CADENCE MCSHANE CORP.
14860 Montfort Drive
Dallas Tx 75248
ISSUED DATE:
4/5/2007
APPLIED DATE:
11/21/2006
EXPIRED DATE:
2/3/2018
SITE APN:
STATUS:
COMPLETED
APPLICANT:
SHW GROUP
4000 McEWEN RD. N.
Dallas TX 75244
LEGAL DESC:
COUNTY:
ZONING:
VALUATION:
24000000
FEE SUMMARY
INSPECTION SUMMARY
CREDIT CARD FEE$3.15
SET 2 TURB METER 12/17/2007$30.00
CREDIT CARD FEE$4.05
CREDIT CARD FEE$2.10
1 1/2 INCH CURBSTOP REPAIR$0.00
COMMDRYWALL 1/29/2008 CW$35.00
T-POLE 6/14/2007 JB$35.00
BRICK/WALL TIES 10/31/2007 J$35.00
WATER METER DEPOSIT$75.00
WATER METER DEPOSIT$75.00
WATER METER DEPOSIT$75.00
2 INCH TURB METER$615.00
2 INCH TURB METER$615.00
2 INCH TURB METER$615.00
WATER METER DEPOSIT$75.00
WATER METER DEPOSIT$75.00
WATER METER DEPOSIT$75.00
4 INCH COMP METER$2,400.00
4 INCH COMP METER$2,400.00
2 INCH PD METER$400.00
2 INCH PD METER$90.00
GAS AIR TEST 2/11/2008$35.00
ROOF DRAINS 4/23/2008$35.00
GREASE TRAP 11/28/2007$35.00
DUCT ROUGH 6/3/2008$35.00
MECHANICAL FINA 7/11/2008$35.00
DUCT ROUGH 2/11/2008 TW$35.00
MISCELLANEOUS ELECTRICAL FEES$6,038.52
MISCELLANOUS MECHANICAL FEES$3,357.20
MISCELLANEOUS PLUMBING FEES$2,552.00
COMMERCIAL BUILDING PERMIT FEE$46,837.14
Total Fees:$66,724.16
______  T-POLE
______  PIER
______  FOOTINGS
______  PIER
______  ELECTRICAL ROUGH IN
______  MISC
______  ELECTRICAL ROUGH IN
______  PIER
______  T-POLE
______  PIER
______  PLUMBING ROUGH-IN
______  PIER
______  ELECTRICAL ROUGH IN
______  PIER
______  PLUMBING ROUGH-IN
______  T-POLE
______  PIER
______  ELECTRICAL ROUGH IN
______  PLUMBING ROUGH-IN
______  ELECTRICAL ROUGH IN
______  ELECTRICAL ROUGH IN
______  PIER
______  ELECTRICAL ROUGH IN
______  PIER
______  PIER
______  PIER
______  PIER
______  ELECTRICAL
______  PAVING
______  PLUMBING ROUGH-IN
______  PIER
______  SLAB
______  CAMERA
______  CAMERA
______  ROOF DRAINS
______  SLAB
______  SLAB
______  PAVING
______  PLUMBING ROUGH-IN
______  CAMERA
______  PAVING
______  PIER
______  ELECTRICAL ROUGH IN
______  PLUMBING ROUGH-IN
______  FIRELANE INSPECTION
______  PLUMBING ROUGH-IN
______  FIRELANE INSPECTION
______  PAVING
______  SLAB
______  PLUMBING ROUGH-IN
______  CAMERA
______  FIRELANE INSPECTION
______  PAVING
______  PLUMBING ROUGH-IN
______  PIER
______  PIER
______  PAVING
______  PLUMBING ROUGH-IN
______  PAVING
______  PIER
______  PAVING
______  BRICK/WALL TIES
______  SLAB
______  BRICK/WALL TIES
______  CAMERA
______  CAMERA
______  BRICK/WALL TIES
______  BRICK/WALL TIES
______  PAVING
______  BRICK/WALL TIES
______  PAVING
______  BRICK/WALL TIES
______  BRICK/WALL TIES
______  PIER
______  BRICK/WALL TIES
______  PAVING
______  SLAB
______  BRICK/WALL TIES
______  SLAB
______  BRICK/WALL TIES
______  CAMERA
______  BRICK/WALL TIES
______  BRICK/WALL TIES
______  BRICK/WALL TIES
______  BRICK/WALL TIES
______  GREASE TRAP
______  PIER
______  BRICK/WALL TIES
______  PIER
______  BRICK/WALL TIES
______  TILT WALL PANELS
______  BRICK/WALL TIES
______  BRICK/WALL TIES
______  SLAB
______  BRICK/WALL TIES
______  CAMERA
______  CAMERA
______  CAMERA
______  CAMERA
______  CAMERA
______  CAMERA
______  CAMERA
______  CAMERA
______  CAMERA
______  CAMERA
______  CAMERA
______  BRICK/WALL TIES
______  BRICK/WALL TIES
______  SLAB
______  TILT WALL PANELS
______  BRICK/WALL TIES
______  BRICK/WALL TIES
______  SLAB
______  TILT WALL PANELS
______  TILT WALL PANELS
______  BRICK/WALL TIES
______  CAMERA
______  BRICK/WALL TIES
______  PIER
______  BRICK/WALL TIES
______  BRICK/WALL TIES
______  BRICK/WALL TIES
______  BRICK/WALL TIES
______  BRICK/WALL TIES
______  BRICK/WALL TIES
______  SLAB
______  BRICK/WALL TIES
______  CAMERA
______  BRICK/WALL TIES
______  BRICK/WALL TIES
______  PIER
______  BRICK/WALL TIES
______  PIER
______  BRICK/WALL TIES
______  LATH
______  BRICK/WALL TIES
______  BRICK/WALL TIES
______  BRICK/WALL TIES
______  BRICK/WALL TIES
______  LATH
______  SLAB
______  BRICK/WALL TIES
______  BRICK/WALL TIES
______  SLAB
______  BRICK/WALL TIES
______  CAMERA
______  CAMERA
______  BRICK/WALL TIES
______  SLAB
______  BRICK/WALL TIES
______  BRICK/WALL TIES
______  BRICK/WALL TIES
______  BRICK/WALL TIES
______  BRICK/WALL TIES
______  BRICK/WALL TIES
______  GREASE TRAP
______  GREASE TRAP
______  BRICK/WALL TIES
______  GREASE TRAP
______  BRICK/WALL TIES
______  GREASE TRAP
______  GREASE TRAP
______  LATH
______  ELEC WALL
______  METER PAYMENT
______  METER PAYMENT
______  METER PAYMENT
______  SET 2 TURB METER
______  SET 2 TURB METER
______  BRICK/WALL TIES
______  COMM PLUMB TOP OUT
______  PLUMBING ROUGH-IN
______  ROOF DRAINS
______  ROOF DRAINS
______  ROOF DRAINS
______  LATH
______  COMM PLUMB TOP OUT
______  ELEC WALL
______  LATH
______  MISCFRAME
______  ROOF DRAINS
______  ELEC WALL
______  DUCT ROUGH
______  MISCFRAME
______  GAS PRESSURE
______  MECHANICAL
______  MECHANICAL
______  MISCFRAME
______  COMMDRYWALL
______  INSULATION
______  SET 2 TURB METER
______  SET 2 TURB METER
______  4 PD METER
______  4 PD METER
______  METER PAYMENT
______  METER PAYMENT
______  METER PAYMENT
______  DRY WALL
______  DRY WALL
______  PAVING
______  COMM PLUMB TOP OUT
______  DUCT ROUGH
______  DUCT ROUGH
______  GAS AIR TEST
______  PLUMBING ROUGH-IN
______  COMM PLUMB TOP OUT
______  DRY WALL
______  PAVING
______  DUCT ROUGH
______  CEILING
______  COMM FRAME
______  COMM FRAME
______  COMM PLUMB TOP OUT
______  DUCT ROUGH
______  ROOF DRAINS
______  ELECTRICAL RELEASE
______  DUCT ROUGH
______  ELECTRICAL RELEASE
______  COMM PLUMB TOP OUT
______  GAS AIR TEST
______  PLUMBING ROUGH-IN
______  COMM PLUMB TOP OUT
______  COMM PLUMB TOP OUT
______  DRY WALL
______  CEILING
______  COMM PLUMB TOP OUT
______  DRY WALL
______  ELECTRICAL RELEASE
______  COMM FRAME
______  COMM PLUMB TOP OUT
______  CEILING
______  COMM PLUMB TOP OUT
______  COMM PLUMB TOP OUT
______  SET 2 PD METER
______  ROOF DRAINS
______  ELECTRICAL ROUGH IN
______  ELEC WALL
______  RETAINING WALL
______  SIDEWALK
______  ROOF DRAINS
______  COMM PLUMB TOP OUT
______  ROOF DRAINS
______  ROOF DRAINS
______  CEILING
______  CEILING
______  DUCT ROUGH
______  VENT HOOD
______  VENT HOOD
______  CEILING
______  CEILING
______  CEILING
______  DUCT ROUGH
______  CEILING
______  GAS RELEASE
______  CEILING
______  CEILING
______  GAS RELEASE
______  CEILING
______  MECHANICAL ROUGH
______  PLUMBING FINAL
______  MECHANICAL FINAL
______  ELECTRICAL FINAL
______  MECHANICAL FINAL
______  PLUMBING FINAL
______  MECHANICAL FINAL
______  ELECTRICAL FINAL
______  ELECTRICAL FINAL
______  MECHANICAL FINAL
______  PLUMBING FINAL
______  COURTESY HEALTH INSP
______  PLUMBING FINAL
______  COURTESY HEALTH INSP
______  CEILING
______  ELECTRICAL FINAL
______  INSULATION
______  MECHANICAL FINAL
______  ELECTRICAL FINAL
______  MECHANICAL FINAL
______  HEALTH FINAL
______  BUILDING FINAL
______  COURTESY HEALTH INSP
______  BUILDING FINAL
______  SET 2 PD METER
Notes: