APPROVED DATE: 11/20/2006 PERMIT SUB-TYPE: SNEW PERMIT NO: B06-4319
JOB ADDRESS:
10561 TOBIAS LANE
FRISCO, TX
DESC:   5545 AC, 7042 SF, SFR / 2 STORY
OWNER:
JIM JOHNSON BUILDERS X11/07
115 EXECUTIVE WAY
DESOTO TX 75115

CONTRACTOR:
JIM JOHNSON BUILDERS X11/07
115 EXECUTIVE WAY
DESOTO TX 75115
ISSUED DATE:
11/20/2006
APPLIED DATE:
11/17/2006
EXPIRED DATE:
5/19/2007
SITE APN:
STATUS:
COMPLETED
APPLICANT:
JIM JOHNSON BUILDERS X11/07
115 EXECUTIVE WAY
DESOTO TX 75115
LEGAL DESC:
COUNTY:
ZONING:
VALUATION:
413712.45
FEE SUMMARY
INSPECTION SUMMARY
LAWNSPRINKLERSYSTEM$35.00
WATER METER DEPOSIT$75.00
1 INCH METER$290.00
THOROUGHFARE IMPACT FEE$3,602.00
WATER IMPACT FEE$1,911.00
SEWER IMPACT FEE$1,553.00
CREDIT CARD FEE$3.60
SET 1 PD METER 11/28/2006 RG$30.00
T-HEAT 4/10/2007 RM$30.00
PLUMBING TOP OU 2/9/2007$30.00
PLUMBING TOP OU 2/14/2007$30.00
SLAB 12/11/06$30.00
RESIDENTIAL ELECTRIC FEE$211.26
MISCELLANOUS MECHANICAL FEES$175.50
MISCELLANEOUS PLUMBING FEES$326.00
PLAN REVIEW FEE$50.00
BUILDING PERMIT FEE$2,563.75
FENCE FEE$20.00
Total Fees:$10,966.11
______  METER PAYMENT
______  SET 1 PD METER
______  SET 1 PD METER
______  PLUMBING ROUGH-IN
______  T-POLE
______  T-POLE
______  PLUMBING ROUGH-IN
______  SLAB
______  SLAB
______  SLAB
______  CAMERA
______  LATH
______  LATH
______  PLUMBING TOP OUT
______  PLUMBING TOP OUT
______  PLUMBING TOP OUT
______  PLUMBING TOP OUT
______  2NDS/FRAMING
______  2NDS/FRAMING
______  INSULATION
______  BRICK/WALL TIES
______  DRY WALL
______  LATH
______  GAS PRESSURE
______  T-HEAT
______  FLATWORK
______  T-HEAT
______  PLUMBING FINAL
______  ELECTRICAL FINAL
______  PLUMBING FINAL
______  UTILITY / ROW
______  CO/BUILDING FINAL
______  CO/BUILDING FINAL
The project described shall be built in accordance with plans and specifications submitted at time of applications. All provisions of law and ordinances governing this type of work will be complied with whether specified or not. Granting of a permit does not presume to give authority to violate or cancel the provisions of any other local or state law regulating construction or the performance of construction. (The City will not assume responsibility for workability of sanitary sewer on all lots. NOTICE: A Certificate of Occupancy Must be Issued Before Any Building is Occupied.)

(THIS IS A BASIC PERMIT VIEW ONLY)