APPROVED DATE: 7/26/2006 PERMIT SUB-TYPE: CNEW PERMIT NO: B06-2428
JOB ADDRESS:
5616 WARREN PKWY
FRISCO, TX 75034
DESC:   13752 SQ FT, CNEW / BUCH MEDICAL OFFICE BUILDING
OWNER:
JPB DEVELOPMENT, LP
1600 COIT RD #408
PLANO TX 75075

CONTRACTOR:
FJW
905 W. MITCHELL
ARLINGTON TX 76013
ISSUED DATE:
8/7/2006
APPLIED DATE:
6/14/2006
EXPIRED DATE:
SITE APN:
ADD79483
STATUS:
COMPLETED
APPLICANT:
ML REID ARCHITECTS
3735 GRAMERCY
HOUSTON TX 77025
LEGAL DESC:
COUNTY:
ZONING:
VALUATION:
2477000
FEE SUMMARY
INSPECTION SUMMARY
ELECTRICAL 3/27/2007 JB$35.00
PLUMBING FINAL 5/24/2007 JTH$30.00
THOROUGHFARE IMPACT FEE$91,006.00
WATER IMPACT FEE$24,843.00
SEWER IMPACT FEE$12,427.00
MISCELLANOUS MECHANICAL FEES$287.80
MISCELLANEOUS PLUMBING FEES$398.00
COMMERCIAL ELECTRIC FEE$570.08
COMMERCIAL BUILDING PERMIT FEE$6,158.67
MISCELLANEOUS PLUMBING FEES$166.00
PLAN REVIEW FEE$50.00
COMMERCIAL ELECTRIC FEE$45.00
PLAN REVIEW FEE$400.00
WATER METER DEPOSIT$75.00
2 INCH PD METER$490.00
2 INCH TURB METER$615.00
WATER METER DEPOSIT$75.00
Total Fees:$137,671.55
______  ELECTRICAL
______  ELECTRICAL
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  ELECTRICAL
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  COMM PLUMB TOP OUT
______  MISC
______  MISCFRAME
______  COMM FRAME
______  INSULATION
______  ELEC WALL
______  COMM PLUMB TOP OUT
______  ELECTRICAL RELEASE
______  COMM PLUMB TOP OUT
______  MECHANICAL
______  ELECTRICAL RELEASE
______  COMM PLUMB TOP OUT
______  DRY WALL
______  COMM PLUMB TOP OUT
______  BRICK
______  PLUMBING ROUGH-IN
______  METER PAYMENT
______  SET 2 PD METER
______  ELECTRICAL RELEASE
______  CEILING
______  ELECTRICAL
______  ELECTRICAL
______  ELECTRICAL RELEASE
______  ELECTRICAL RELEASE
______  METER PAYMENT
______  SET 2 TURB METER
______  FLATWORK
______  FLATWORK
______  COMM PLUMB TOP OUT
______  ELECTRICAL
______  FLATWORK
______  ELECTRICAL
______  ELECTRICAL
______  ELECTRICAL FINAL
______  PLUMBING FINAL
______  COMM PLUMB FINAL
______  ELECTRICAL FINAL
______  MISCCO
The project described shall be built in accordance with plans and specifications submitted at time of applications. All provisions of law and ordinances governing this type of work will be complied with whether specified or not. Granting of a permit does not presume to give authority to violate or cancel the provisions of any other local or state law regulating construction or the performance of construction. (The City will not assume responsibility for workability of sanitary sewer on all lots. NOTICE: A Certificate of Occupancy Must be Issued Before Any Building is Occupied.)