APPROVED DATE: 5/31/2006
|
PERMIT SUB-TYPE: SNEW
|
PERMIT NO: B06-1985
|
JOB ADDRESS: 1401 YUMA DRIVE FRISCO, TX |
DESC:
4087 AC, 4970 SF, SFR / 2 STORY |
|
OWNER:
HUNTINGTON HOMES
12850 HILLCREST RD #200 DALLAS TX 75230
|
CONTRACTOR:
HUNTINGTON HOMES
12850 HILLCREST RD #200 DALLAS TX 75230
|
ISSUED DATE: 6/5/2006
APPLIED DATE:5/18/2006
EXPIRED DATE:12/4/2006
SITE APN:
STATUS:COMPLETED
|
|
APPLICANT:
HUNTINGTON HOMES
12850 HILLCREST RD #200 DALLAS TX 75230
|
LEGAL DESC:
COUNTY:
ZONING:
VALUATION: 304931.07
|
|
FEE SUMMARY
|
INSPECTION SUMMARY
|
LAWNSPRINKLERSYSTEM | $35.00 |
PLUMBING TOP OU 11/10/06 | $30.00 |
2NDS/FRAMING 11/15/2006 WDP | $30.00 |
WATER METER DEPOSIT | $75.00 |
1 INCH METER | $290.00 |
RESIDENTIAL RED TAG FEE | $30.00 |
RESIDENTIAL RED TAG FEE | $30.00 |
PLUMBING FINAL 1/26/2007 | $30.00 |
PLUMBING FINAL 2/6/2007 | $30.00 |
RESIDENTIAL ELECTRIC FEE | $149.10 |
MISCELLANOUS MECHANICAL FEES | $142.50 |
MISCELLANEOUS PLUMBING FEES | $267.00 |
BUILDING PERMIT FEE | $2,018.75 |
FENCE FEE | $20.00 |
DRY WALL 11/28/2006 WDP | $30.00 |
2NDS/FRAMING 11/14/2006 WDP | $30.00 |
PLUMBING FINAL 1/23/2007 | $30.00 |
PLUMBING FINAL 1/19/2007 | $30.00 |
ELECTRICAL FINA 1/11/07 | $30.00 |
RESIDENTIAL RED TAG FEE | $30.00 |
Total Fees: | $3,357.35 |
|
|
| ______ METER PAYMENT |
______ T-POLE |
______ SET 1 PD METER |
______ PLUMBING ROUGH-IN |
______ SLAB |
______ FLATWORK |
______ SLAB |
______ SLAB |
______ FLATWORK |
______ CAMERA |
______ PLUMBING TOP OUT |
______ PLUMBING TOP OUT |
______ 2NDS/FRAMING |
______ 2NDS/FRAMING |
______ 2NDS/FRAMING |
______ INSULATION |
______ DRY WALL |
______ DRY WALL |
______ BRICK/WALL TIES |
______ ELECTRICAL FINAL |
______ ELECTRICAL FINAL |
______ PLUMBING FINAL |
______ PLUMBING FINAL |
______ PLUMBING FINAL |
______ PLUMBING FINAL |
______ UTILITY / ROW |
______ PLUMBING FINAL |
______ CO/BUILDING FINAL |
|
The project described shall be built in accordance with plans and specifications submitted at time of applications. All provisions of law and ordinances governing this type of work will be complied with whether specified or not. Granting of a permit does not presume to give authority to violate or cancel the provisions of any other local or state law regulating construction or the performance of construction. (The City will not assume responsibility for workability of sanitary sewer on all lots. NOTICE: A Certificate of Occupancy Must be Issued Before Any Building is Occupied.)
|
(THIS IS A BASIC PERMIT VIEW ONLY)
|
|