APPROVED DATE: 7/27/2006 PERMIT SUB-TYPE: CNEW PERMIT NO: B06-1783
JOB ADDRESS:
5858 MAIN ST
FRISCO, TX 75033
DESC:   54574 SQ FT, CNEW / MAIN STREET AND WORLD CUP WAY
OWNER:
Main Dallas Parkway Crossing,
8235 Douglas Ave, #950
Dallas TX 75225

CONTRACTOR:
CMG COMMERCIAL CONTRACTING INC
2175 MANANA #100
DALLAS TX 75220
ISSUED DATE:
10/26/2006
APPLIED DATE:
5/8/2006
EXPIRED DATE:
4/25/2006
SITE APN:
C2657439
STATUS:
COMPLETED
APPLICANT:
O'BRIEN & ASSOCIATES
5310 HARVEST HILL RD
DALLAS TX 75230
LEGAL DESC:
COUNTY:
ZONING:
VALUATION:
2750000
FEE SUMMARY
INSPECTION SUMMARY
LAWNSPRINKLERSYSTEM$35.00
SET 2 TURB METER 9/12/2007 B$30.00
CREDIT CARD FEE$0.90
CONVENIENCE FEE$1.05
SEWER IMPACT FEE$12,426.70
THOROUGHFARE IMPACT FEE$302,406.00
WATER IMPACT FEE$30,576.00
COMMERCIAL BUILDING PERMIT FEE$6,674.64
COMMERCIAL ELECTRIC FEE$2,202.96
MISCELLANEOUS PLUMBING FEES$244.00
MISCELLANOUS MECHANICAL FEES$105.20
WATER METER DEPOSIT$75.00
2 INCH PD METER$490.00
WATER METER DEPOSIT$75.00
2 INCH TURB METER$615.00
ELECTRICAL FINAL 9/4/2007 JB$35.00
SEWER IMPACT FEE$0.30
ILLEGAL JUMPER$500.00
PLUMBING ROUGH- 1/10/07$35.00
Total Fees:$356,527.75
______  ELECTRICAL
______  PIER
______  ELECTRICAL
______  MISC SLAB
______  MISC SLAB
______  ELECTRICAL ROUGH IN
______  ELECTRICAL
______  PRE POUR INSP
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  MISC SLAB
______  SLAB
______  SLAB
______  SLAB
______  ELECTRICAL ROUGH IN
______  T-POLE
______  SLAB
______  T-POLE
______  PAVING
______  SLAB
______  SLAB
______  CAMERA
______  MECHANICAL
______  COMMDRYWALL
______  BRICK
______  COMM PLUMB TOP OUT
______  COMM PLUMB TOP OUT
______  ELEC WALL
______  ELEC WALL
______  ELECTRICAL
______  INSULATION
______  MISCFRAME
______  DRY WALL
______  INSULATION
______  CEILING
______  CEILING
______  DRY WALL
______  FLATWORK
______  FLATWORK
______  ELECTRICAL
______  ELECTRICAL RELEASE
______  CEILING
______  ELECTRICAL FINAL
______  ELECTRICAL FINAL
______  MECHANICAL FINAL
______  METER PAYMENT
______  METER PAYMENT
______  SET 2 PD METER
______  SET 2 TURB METER
______  SET 2 TURB METER
______  ELECTRICAL FINAL
______  ELECTRICAL FINAL
______  PLUMBING FINAL
______  ELECTRICAL FINAL
______  FIRE FINAL
______  FIRE FINAL
______  MISCCO
______  MISCCO
The project described shall be built in accordance with plans and specifications submitted at time of applications. All provisions of law and ordinances governing this type of work will be complied with whether specified or not. Granting of a permit does not presume to give authority to violate or cancel the provisions of any other local or state law regulating construction or the performance of construction. (The City will not assume responsibility for workability of sanitary sewer on all lots. NOTICE: A Certificate of Occupancy Must be Issued Before Any Building is Occupied.)