BUILDING
PERMIT
Inspections Line: 972.292.5386 cut-off at 4 PM the business day before
OR
Request Inspections online at https:\\etrakit.friscotexas.gov\etrakit until 7:00 AM same day
Contact assigned inspector for cancellation.
|
CITY OF FRISCO
6101 Frisco Square Blvd, TX 75034
Phone: 972.292.5301
|
APPROVED DATE: 4/5/2006
|
PERMIT SUB-TYPE: SNEW
|
PERMIT NO: B06-1145
|
JOB ADDRESS: 13893 FALL HARVEST DRIVE FRISCO, TX |
DESC:
1875 AC, 2405 SF, SFR / 1 STORY |
|
OWNER:
DR HORTON
1901 ASCENSION BLVD.,#100 ARLINGTON TX 76006
|
CONTRACTOR:
DR HORTON
1901 ASCENSION BLVD.,#100 ARLINGTON TX 76006
|
ISSUED DATE: 4/11/2006
APPLIED DATE:3/27/2006
EXPIRED DATE:10/11/2006
SITE APN:
STATUS:COMPLETED
|
|
APPLICANT:
DR HORTON
1901 ASCENSION BLVD.,#100 ARLINGTON TX 76006
|
LEGAL DESC:
COUNTY:
ZONING:
VALUATION: 139893.75
|
|
FEE SUMMARY
|
INSPECTION SUMMARY
|
LAWNSPRINKLERSYSTEM | $35.00 |
RESIDENTIAL ELECTRIC FEE | $72.15 |
MISCELLANOUS MECHANICAL FEES | $96.50 |
MISCELLANEOUS PLUMBING FEES | $188.00 |
BUILDING PERMIT FEE | $1,193.75 |
FENCE FEE | $20.00 |
T-POLE 5/1/2006 | $30.00 |
THOROUGHFARE IMPACT FEE | $2,242.00 |
WATER IMPACT FEE | $388.00 |
SEWER IMPACT FEE | $523.00 |
ELECTRICAL FINAL 11/10/2006 | $30.00 |
WATER METER DEPOSIT | $75.00 |
1 INCH METER | $290.00 |
PLUMBING TOP OU 7/24/06 | $30.00 |
RESIDENTIAL RED TAG FEE | $30.00 |
FLATWORK 5/31/2006 WKT | $30.00 |
SLAB 5/31/2006 WKT | $30.00 |
SLAB 6/1/2006 WKT | $30.00 |
Total Fees: | $5,333.40 |
|
|
| ______ METER PAYMENT |
______ T-POLE |
______ T-POLE |
______ SET 1 PD METER |
______ PLUMBING ROUGH-IN |
______ FLATWORK |
______ SLAB |
______ SLAB |
______ FLATWORK |
______ SLAB |
______ SLAB |
______ SLAB |
______ CAMERA |
______ PLUMBING TOP OUT |
______ PLUMBING TOP OUT |
______ PLUMBING TOP OUT |
______ 2NDS/FRAMING |
______ 2NDS/FRAMING |
______ INSULATION |
______ DRY WALL |
______ BRICK/WALL TIES |
______ PLUMBING FINAL |
______ ELECTRICAL FINAL |
______ ELECTRICAL FINAL |
______ ELECTRICAL FINAL |
______ UTILITY / ROW |
______ UTILITY / ROW |
______ CO/BUILDING FINAL |
______ CO/BUILDING FINAL |
|
The project described shall be built in accordance with plans and specifications submitted at time of applications. All provisions of law and ordinances governing this type of work will be complied with whether specified or not. Granting of a permit does not presume to give authority to violate or cancel the provisions of any other local or state law regulating construction or the performance of construction. (The City will not assume responsibility for workability of sanitary sewer on all lots. NOTICE: A Certificate of Occupancy Must be Issued Before Any Building is Occupied.)
|
(THIS IS A BASIC PERMIT VIEW ONLY)
|
|