APPROVED DATE: 3/22/2006
|
PERMIT SUB-TYPE: SNEW
|
PERMIT NO: B06-0855
|
JOB ADDRESS: 10151 TATE LANE FRISCO, TX |
DESC:
5029 AC, 6345 SF, SFR / 2 STORY *MODEL* |
|
OWNER:
BRENTWOOD BUILDERS X-03/05
PO BOX 1829 ADDISON TX 75001
|
CONTRACTOR:
BRENTWOOD BUILDERS X-03/05
PO BOX 1829 ADDISON TX 75001
|
ISSUED DATE: 4/10/2006
APPLIED DATE:3/7/2006
EXPIRED DATE:10/9/2006
SITE APN:
STATUS:COMPLETED
|
|
APPLICANT:
BRENTWOOD BUILDERS X-03/05
PO BOX 1829 ADDISON TX 75001
|
LEGAL DESC:
COUNTY:
ZONING:
VALUATION: 375213.69
|
|
FEE SUMMARY
|
INSPECTION SUMMARY
|
CAMERA FAILED | $30.00 |
CAMERA FAILED | $30.00 |
PLUMBING TOP OU 9/11/06 | $30.00 |
CONVENIENCE FEE | $3.60 |
CONVENIENCE FEE | $3.60 |
CONVENIENCE FEE | $3.60 |
CONVENIENCE FEE | $3.60 |
CONVENIENCE FEE | $1.80 |
WATER METER DEPOSIT | $75.00 |
1 INCH METER | $290.00 |
PLUMBING TOP OU 9/6/06 | $30.00 |
PLUMBING TOP OU 9/14/06 | $30.00 |
ELECTRICAL FINAL 2/28/2007 J | $30.00 |
GAS RELEASE 2/28/2007 | $30.00 |
RESIDENTIAL RED TAG FEE | $30.00 |
DRY WALL 11/6/2006 POB | $30.00 |
PLUMBING FINAL 3/5/2007 | $30.00 |
PLUMBING FINAL 3/22/2007 | $30.00 |
PLUMBING FINAL 3/29/2007 | $30.00 |
PLUMBING FINAL 4/4/2007 | $30.00 |
PLAN REVIEW FEE | $50.00 |
RESIDENTIAL ELECTRIC FEE | $190.35 |
MISCELLANOUS MECHANICAL FEES | $169.00 |
MISCELLANEOUS PLUMBING FEES | $291.00 |
BUILDING PERMIT FEE | $2,373.75 |
COMMERCIAL ELECTRIC FEE | $0.00 |
FENCE FEE | $20.00 |
RESIDENTIAL RED TAG FEE | $30.00 |
RESIDENTIAL RED TAG FEE | $30.00 |
RESIDENTIAL RED TAG FEE | $30.00 |
RESIDENTIAL RED TAG FEE | $30.00 |
DRY WALL 11/3/2006 WDP | $30.00 |
Total Fees: | $4,015.30 |
|
|
| ______ METER PAYMENT |
______ T-POLE |
______ SET 1 PD METER |
______ PLUMBING ROUGH-IN |
______ SLAB |
______ CAMERA |
______ SLAB |
______ CAMERA |
______ CAMERA |
______ LATH |
______ PLUMBING TOP OUT |
______ PLUMBING TOP OUT |
______ PLUMBING TOP OUT |
______ PLUMBING TOP OUT |
______ PLUMBING TOP OUT |
______ PLUMBING TOP OUT |
______ PLUMBING TOP OUT |
______ PLUMBING TOP OUT |
______ 2NDS/FRAMING |
______ 2NDS/FRAMING |
______ 2NDS/FRAMING |
______ 2NDS/FRAMING |
______ 2NDS/FRAMING |
______ INSULATION |
______ INSULATION |
______ INSULATION |
______ INSULATION |
______ BRICK/WALL TIES |
______ MISCFRAME |
______ LATH |
______ DRY WALL |
______ DRY WALL |
______ DRY WALL |
______ FLATWORK |
______ ELECTRICAL FINAL |
______ GAS RELEASE |
______ ELECTRICAL FINAL |
______ PLUMBING FINAL |
______ PLUMBING FINAL |
______ CAMERA |
______ PLUMBING FINAL |
______ GAS RELEASE |
______ PLUMBING FINAL |
______ PLUMBING FINAL |
______ UTILITY / ROW |
______ PLUMBING FINAL |
______ CO/BUILDING FINAL |
______ CO/BUILDING FINAL |
|
The project described shall be built in accordance with plans and specifications submitted at time of applications. All provisions of law and ordinances governing this type of work will be complied with whether specified or not. Granting of a permit does not presume to give authority to violate or cancel the provisions of any other local or state law regulating construction or the performance of construction. (The City will not assume responsibility for workability of sanitary sewer on all lots. NOTICE: A Certificate of Occupancy Must be Issued Before Any Building is Occupied.)
|