APPROVED DATE: 12/7/2005
|
PERMIT SUB-TYPE: SNEW
|
PERMIT NO: B05-4412
|
JOB ADDRESS: 13809 BADGER CREEK DR FRISCO, TX |
DESC:
1875 AC, 2364 SF, SFR / 1 STORY |
|
OWNER:
DR HORTON
1901 ASCENSION BLVD.,#100 ARLINGTON TX 76006
|
CONTRACTOR:
DR HORTON
1901 ASCENSION BLVD.,#100 ARLINGTON TX 76006
|
ISSUED DATE: 2/1/2006
APPLIED DATE:11/30/2005
EXPIRED DATE:7/31/2006
SITE APN:D283958
STATUS:COMPLETED
|
|
APPLICANT:
DR HORTON
1901 ASCENSION BLVD.,#100 ARLINGTON TX 76006
|
LEGAL DESC:
COUNTY:
ZONING:
VALUATION: 139893.75
|
|
FEE SUMMARY
|
INSPECTION SUMMARY
|
LAWNSPRINKLERSYSTEM | $35.00 |
PLUMBING TOP OU 7/7/2006 | $30.00 |
SET 1 PD METER 2/7/2006 RGH | $30.00 |
SET 1 PD METER 3/17/2006 RGH | $30.00 |
T-POLE 2/9/2006 CSW | $30.00 |
T-POLE 2/10/2006 CSW | $30.00 |
RESIDENTIAL ELECTRIC FEE | $70.92 |
MISCELLANOUS MECHANICAL FEES | $83.50 |
MISCELLANEOUS PLUMBING FEES | $188.00 |
BUILDING PERMIT FEE | $1,193.75 |
FENCE FEE | $20.00 |
T-POLE 1995/12/32 JM | $30.00 |
RESIDENTIAL RED TAG FEE | $30.00 |
PLUMBING ROUGH-IN 4/24/2006 | $30.00 |
PLUMBING ROUGH-IN 4/27/2006 | $30.00 |
PLUMBING ROUGH-IN 4/28/2006 | $30.00 |
WATER METER DEPOSIT | $75.00 |
1 INCH METER | $290.00 |
PLUMBING TOP OU 7/25/06 | $30.00 |
PLUMBING TOP OU 7/26/06 | $30.00 |
PLUMBING TOP OU 7/27/06 | $30.00 |
PLUMBING TOP OU 7/31/06 | $30.00 |
RESIDENTIAL RED TAG FEE | $30.00 |
SLAB 5/17/2006 WKT | $30.00 |
Total Fees: | $2,436.17 |
|
|
| ______ METER PAYMENT |
______ SET 1 PD METER |
______ T-POLE |
______ T-POLE |
______ SET 1 PD METER |
______ SET 1 PD METER |
______ PLUMBING ROUGH-IN |
______ T-POLE |
______ T-POLE |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ SLAB |
______ FLATWORK |
______ SLAB |
______ SLAB |
______ CAMERA |
______ PLUMBING TOP OUT |
______ PLUMBING TOP OUT |
______ PLUMBING TOP OUT |
______ PLUMBING TOP OUT |
______ PLUMBING TOP OUT |
______ PLUMBING TOP OUT |
______ PLUMBING TOP OUT |
______ PLUMBING TOP OUT |
______ PLUMBING TOP OUT |
______ 2NDS/FRAMING |
______ INSULATION |
______ DRY WALL |
______ BRICK/WALL TIES |
______ ELECTRICAL FINAL |
______ PLUMBING FINAL |
______ PLUMBING FINAL |
______ UTILITY / ROW |
______ CO/BUILDING FINAL |
______ CO/BUILDING FINAL |
|
The project described shall be built in accordance with plans and specifications submitted at time of applications. All provisions of law and ordinances governing this type of work will be complied with whether specified or not. Granting of a permit does not presume to give authority to violate or cancel the provisions of any other local or state law regulating construction or the performance of construction. (The City will not assume responsibility for workability of sanitary sewer on all lots. NOTICE: A Certificate of Occupancy Must be Issued Before Any Building is Occupied.)
|