APPROVED DATE: 1/5/2006 PERMIT SUB-TYPE: CNEW PERMIT NO: B05-3838
JOB ADDRESS:
7277 FRISCO LAKES DR
FRISCO, TX 75034
DESC:   32000 SQ FT, CNEW / FRISCO LAKES AMENITY CENTER
OWNER:
PULTE HOMES
1234 LAKESHORE DR, #750A
COPPELL TX 75019

CONTRACTOR:
S4 CONSTRUCTION, LTD
P.O. BOX 1098
FRISCO TX 75034
ISSUED DATE:
1/11/2006
APPLIED DATE:
11/8/2005
EXPIRED DATE:
5/22/2006
SITE APN:
STATUS:
COMPLETED
APPLICANT:
Carter & Burgess, Inc.
7950 Elmbrook Dr., Suite 250
Dallas TX 752474951
LEGAL DESC:
COUNTY:
ZONING:
VALUATION:
10000000
FEE SUMMARY
INSPECTION SUMMARY
WATER IMPACT FEE$512.00
SEWER IMPACT FEE$696.00
WATER METER DEPOSIT$75.00
2 INCH PD METER$490.00
WATER METER DEPOSIT$75.00
2 INCH PD METER$490.00
MISCELLANOUS MECHANICAL FEES$310.70
MISCELLANEOUS PLUMBING FEES$394.00
COMMERCIAL ELECTRIC FEE$1,300.00
COMMERCIAL BUILDING PERMIT FEE$20,377.14
ELECTRICAL FINA 12/20/06$35.00
COMM PLUMB TOP 9/6/06$35.00
PLUMBING FINAL 12/18/06$35.00
Total Fees:$24,824.84
______  PLUMBING ROUGH-IN
______  ELECTRICAL
______  SLAB
______  PLUMBING ROUGH-IN
______  SLAB
______  ELECTRICAL
______  SLAB
______  SLAB
______  SLAB
______  SLAB
______  PLUMBING ROUGH-IN
______  SEWER
______  T-POLE
______  ELECTRICAL RELEASE
______  ELECTRICAL
______  PLUMBING ROUGH-IN
______  SLAB
______  ELECTRICAL
______  WATER
______  FIRELANE INSPECTION
______  FIRELANE INSPECTION
______  PAVING
______  PAVING
______  PAVING
______  FIRELANE INSPECTION
______  PAVING
______  PAVING
______  FRAME
______  METER PAYMENT
______  SLAB
______  SET 2 PD METER
______  BRICK/WALL TIES
______  LATH
______  COMM PLUMB TOP OUT
______  MECHANICAL
______  BRICK/WALL TIES
______  COMM PLUMB TOP OUT
______  PLUMBING ROUGH-IN
______  COMM PLUMB TOP OUT
______  ELEC WALL
______  COMM FRAME
______  INSULATION
______  COMM PLUMB TOP OUT
______  COMM PLUMB TOP OUT
______  COMM PLUMB TOP OUT
______  INSULATION
______  COMM PLUMB TOP OUT
______  ELECTRICAL RELEASE
______  COMM FRAME
______  ELECTRICAL ROUGH IN
______  COMM SLAB
______  ELECTRICAL ROUGH IN
______  INSULATION
______  DRY WALL
______  COMM SLAB
______  ELECTRICAL ROUGH IN
______  CEILING
______  DUCT ROUGH
______  PIER
______  ELEC WALL
______  INSULATION
______  ELEC WALL
______  FOOTINGS
______  CEILING
______  FOOTINGS
______  CEILING
______  PLUMBING ROUGH-IN
______  B-STEEL
______  SLAB
______  PIER
______  COURTESY HEALTH INSP
______  PLUMBING ROUGH-IN
______  GAS PRESSURE
______  METER PAYMENT
______  FOOTINGS
______  SET 2 PD METER
______  MECHANICAL FINAL
______  PLUMBING FINAL
______  ELECTRICAL FINAL
______  FOOTINGS
______  HEALTH FINAL
______  ELECTRICAL ROUGH IN
______  PLUMBING FINAL
______  ELECTRICAL FINAL
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  HEALTH FINAL
______  BUILDING FINAL
______  BUILDING FINAL
______  BUILDING FINAL
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  COMM SLAB
______  SLAB
______  COMM PLUMB TOP OUT
______  PLUMBING ROUGH-IN
______  COMM PLUMB TOP OUT
______  ELECTRICAL RELEASE
______  GAS PRESSURE
______  BUILDING FINAL
______  ELECTRICAL FINAL
______  PLUMBING FINAL
______  PLUMBING FINAL
______  BUILDING FINAL
______  MISCCO
______  COMM CO
The project described shall be built in accordance with plans and specifications submitted at time of applications. All provisions of law and ordinances governing this type of work will be complied with whether specified or not. Granting of a permit does not presume to give authority to violate or cancel the provisions of any other local or state law regulating construction or the performance of construction. (The City will not assume responsibility for workability of sanitary sewer on all lots. NOTICE: A Certificate of Occupancy Must be Issued Before Any Building is Occupied.)

(THIS IS A BASIC PERMIT VIEW ONLY)