APPROVED DATE: 10/13/2005 PERMIT SUB-TYPE: CNEW PERMIT NO: B05-3380
JOB ADDRESS:
3540 LEGACY BLDG A
FRISCO, TX 75034
DESC:   72573 SQ FT, CNEW / ADVANTAGE SELF STORAGE-BLDG "A"
OWNER:
Legacy Self Storage, LLC
1500 South Central Expressway,
McKinney TX 75070

CONTRACTOR:
RICK JONES CO, LLC
1500 S. CENTRAL EXPWY, # 620
MCKINNEY TX 75070
ISSUED DATE:
10/28/2005
APPLIED DATE:
9/13/2005
EXPIRED DATE:
2/3/2018
SITE APN:
C2619030
STATUS:
COMPLETED
APPLICANT:
RICK JONES CO, LLC
1500 S. CENTRAL EXPWY, # 620
MCKINNEY TX 75070
LEGAL DESC:
COUNTY:
ZONING:
VALUATION:
2550000
FEE SUMMARY
INSPECTION SUMMARY
LAWNSPRINKLERSYSTEM$35.00
WATER METER DEPOSIT$75.00
WATER METER DEPOSIT$75.00
2 INCH PD METER$490.00
2 INCH TURB METER$615.00
CREDIT CARD FEE$4.20
PLUMBING FINAL 11/3/06$35.00
PLUMBING FINAL 11/16/06$35.00
GAS RELEASE 6/26/2006 TRC$35.00
PLUMBING FINAL 11/13/2006 TR$35.00
THOROUGHFARE IMPACT FEE$27,600.00
WATER IMPACT FEE$2,677.00
SEWER IMPACT FEE$1,275.00
MISCELLANEOUS ELECTRICAL FEES$3,186.00
MISCELLANOUS MECHANICAL FEES$432.30
MISCELLANEOUS PLUMBING FEES$484.00
COMMERCIAL BUILDING PERMIT FEE$6,296.64
Total Fees:$43,385.14
______  PIER
______  PIER
______  ELECTRICAL
______  ELECTRICAL
______  SLAB
______  PLUMBING ROUGH-IN
______  SLAB
______  PLUMBING ROUGH-IN
______  SLAB
______  SLAB
______  CAMERA
______  SLAB
______  SLAB
______  SEWER
______  GAS PRESSURE
______  PAVING
______  MECHANICAL
______  PAVING
______  FLATWORK
______  PAVING
______  METER PAYMENT
______  METER PAYMENT
______  SET 2 PD METER
______  SET 2 TURB METER
______  SLAB
______  BRICK
______  FRAME
______  BRICK
______  DRY WALL
______  ELECTRICAL
______  FRAME
______  PLUMBING TOP OUT
______  PLUMBING TOP OUT
______  ELECTRICAL RELEASE
______  MISC
______  CEILING
______  GAS RELEASE
______  CEILING
______  MISCFRAME
______  CEILING
______  MISC
______  MISC
______  ELECTRICAL
______  GAS RELEASE
______  ELECTRICAL
______  ELECTRICAL
______  MECHANICAL
______  CEILING
______  CEILING
______  PLUMBING FINAL
______  MECHANICAL FINAL
______  PLUMBING FINAL
______  MECHANICAL FINAL
______  ELECTRICAL FINAL
______  PLUMBING FINAL
______  PLUMBING FINAL
______  PLUMBING FINAL
______  LANDSCAPE
______  BUILDING FINAL
______  COMM CO
The project described shall be built in accordance with plans and specifications submitted at time of applications. All provisions of law and ordinances governing this type of work will be complied with whether specified or not. Granting of a permit does not presume to give authority to violate or cancel the provisions of any other local or state law regulating construction or the performance of construction. (The City will not assume responsibility for workability of sanitary sewer on all lots. NOTICE: A Certificate of Occupancy Must be Issued Before Any Building is Occupied.)