APPROVED DATE: 7/5/2005
|
PERMIT SUB-TYPE: SNEW
|
PERMIT NO: B05-2435
|
JOB ADDRESS: 10039 CARRIAGE HILL LN FRISCO, TX 75035 |
DESC:
3445 AC, 3915 SF, SFR / 2 STORY |
|
OWNER:
GRAND HOMES
8350 N CENTRAL EXPRSWY, SUITE DALLAS TX 75206
|
CONTRACTOR:
GRAND HOMES
8350 N CENTRAL EXPRSWY, SUITE DALLAS TX 75206
|
ISSUED DATE: 7/6/2005
APPLIED DATE:6/29/2005
EXPIRED DATE:1/2/2006
SITE APN:C2537044
STATUS:COMPLETED
|
|
APPLICANT:
GRAND HOMES
8350 N CENTRAL EXPRSWY, SUITE DALLAS TX 75206
|
LEGAL DESC:
COUNTY:
ZONING:
VALUATION: 257031.45
|
|
FEE SUMMARY
|
INSPECTION SUMMARY
|
SLAB 7/27/2005 CW | $30.00 |
SLAB 7/28/2005 CW | $30.00 |
WATER METER DEPOSIT | $75.00 |
1 INCH METER | $290.00 |
UTILITY / ROW 11/22/2005 GAS | $0.00 |
2NDS/FRAMING 9/21/2005 JM | $30.00 |
2NDS/FRAMING 9/22/2005 JM | $30.00 |
DRY WALL 1995/12/32 JTH | $30.00 |
ELECTRICAL FINAL 1995/12/32 | $30.00 |
CO/BUILDING FINAL 12/2/2005 | $30.00 |
SET 1 PD METER 8/12/2005 RGH | $30.00 |
CO/BUILDING FINAL 12/13/2005 | $30.00 |
SLAB 7/29/2005 TP | $30.00 |
2NDS/FRAMING 9/8/2005 TP | $30.00 |
RESIDENTIAL ELECTRIC FEE | $117.45 |
MISCELLANOUS MECHANICAL FEES | $129.50 |
MISCELLANEOUS PLUMBING FEES | $225.00 |
BUILDING PERMIT FEE | $1,783.75 |
FENCE FEE | $20.00 |
Total Fees: | $2,970.70 |
|
|
| ______ METER PAYMENT |
______ PLUMBING ROUGH-IN |
______ T-POLE |
______ SLAB |
______ SLAB |
______ SLAB |
______ SLAB |
______ SLAB |
______ CAMERA |
______ SET 1 PD METER |
______ PLUMBING TOP OUT |
______ SET 1 PD METER |
______ PLUMBING TOP OUT |
______ PLUMBING TOP OUT |
______ 2NDS/FRAMING |
______ FLATWORK |
______ 2NDS/FRAMING |
______ 2NDS/FRAMING |
______ 2NDS/FRAMING |
______ 2NDS/FRAMING |
______ INSULATION |
______ DRY WALL |
______ DRY WALL |
______ BRICK/WALL TIES |
______ PLUMBING FINAL |
______ ELECTRICAL FINAL |
______ ELECTRICAL FINAL |
______ UTILITY / ROW |
______ UTILITY / ROW |
______ CO/BUILDING FINAL |
______ CO/BUILDING FINAL |
______ CO/BUILDING FINAL |
______ CO/BUILDING FINAL |
|
The project described shall be built in accordance with plans and specifications submitted at time of applications. All provisions of law and ordinances governing this type of work will be complied with whether specified or not. Granting of a permit does not presume to give authority to violate or cancel the provisions of any other local or state law regulating construction or the performance of construction. (The City will not assume responsibility for workability of sanitary sewer on all lots. NOTICE: A Certificate of Occupancy Must be Issued Before Any Building is Occupied.)
|