BUILDING
PERMIT
Inspections Line: 972.292.5386 cut-off at 4 PM the business day before
OR
Request Inspections online at https:\\etrakit.friscotexas.gov\etrakit until 7:00 AM same day
Contact assigned inspector for cancellation.
|
CITY OF FRISCO
6101 Frisco Square Blvd, TX 75034
Phone: 972.292.5301
|
APPROVED DATE: 4/25/2005
|
PERMIT SUB-TYPE: SNEW
|
PERMIT NO: B05-1371
|
JOB ADDRESS: 12074 YOAKUM DR , TX 75035 |
DESC:
4289 A/C, 4729 SF, SFR / 2 STORY |
|
OWNER:
BUESCHER HOMES
2591 DALLAS PWY #501 FRISCO TX 75034
|
CONTRACTOR:
BUESCHER HOMES
2591 DALLAS PWY #501 FRISCO TX 75034
|
ISSUED DATE: 4/27/2005
APPLIED DATE:4/12/2005
EXPIRED DATE:10/24/2005
SITE APN:C2554408
STATUS:COMPLETED
|
|
APPLICANT:
BUESCHER HOMES
2591 DALLAS PWY #501 FRISCO TX 75034
|
LEGAL DESC:
COUNTY:
ZONING:
VALUATION: 320002.29
|
|
FEE SUMMARY
|
INSPECTION SUMMARY
|
CAMERA 6/1/2005 CB | $30.00 |
CAMERA 6/1/2005 CB | $30.00 |
CAMERA 8/16/2005 CB | $30.00 |
LAWNSPRINKLERSYSTEM | $35.00 |
2NDS/FRAMING 9/13/2005 CSW | $30.00 |
UTILITY / ROW 01/10/2006 GAS | $30.00 |
CO/BUILDING FINAL 1/17/2006 | $30.00 |
RESIDENTIAL ELECTRIC FEE | $141.87 |
MISCELLANOUS MECHANICAL FEES | $136.00 |
MISCELLANEOUS PLUMBING FEES | $246.00 |
BUILDING PERMIT FEE | $2,098.75 |
FENCE FEE | $20.00 |
2NDS/FRAMING 1995/12/32 JTH | $30.00 |
PLUMBING TOP OU 9/7/2005 | $30.00 |
1 INCH METER | $365.00 |
2NDS/FRAMING 10/31/2005 RM | $30.00 |
2NDS/FRAMING 11/3/2005 RM | $30.00 |
INSULATION 11/9/2005 RM | $30.00 |
ELECTRICAL FINAL 12/20/2005 | $30.00 |
SLAB 5/23/2005 WKT | $30.00 |
Total Fees: | $3,432.62 |
|
|
| ______ T-POLE |
______ METER PAYMENT |
______ WATER METER |
______ PLUMBING ROUGH-IN |
______ SLAB |
______ FLATWORK |
______ FLATWORK |
______ SLAB |
______ CAMERA |
______ CAMERA |
______ PLUMBING TOP OUT |
______ PLUMBING TOP OUT |
______ 2NDS/FRAMING |
______ 2NDS/FRAMING |
______ T-POLE |
______ 2NDS/FRAMING |
______ 2NDS/FRAMING |
______ 2NDS/FRAMING |
______ 2NDS/FRAMING |
______ INSULATION |
______ BRICK/WALL TIES |
______ INSULATION |
______ DRY WALL |
______ PLUMBING FINAL |
______ PLUMBING FINAL |
______ ELECTRICAL FINAL |
______ ELECTRICAL FINAL |
______ UTILITY / ROW |
______ UTILITY / ROW |
______ CO/BUILDING FINAL |
______ CO/BUILDING FINAL |
______ CO/BUILDING FINAL |
|
The project described shall be built in accordance with plans and specifications submitted at time of applications. All provisions of law and ordinances governing this type of work will be complied with whether specified or not. Granting of a permit does not presume to give authority to violate or cancel the provisions of any other local or state law regulating construction or the performance of construction. (The City will not assume responsibility for workability of sanitary sewer on all lots. NOTICE: A Certificate of Occupancy Must be Issued Before Any Building is Occupied.)
|
(THIS IS A BASIC PERMIT VIEW ONLY)
|
|